ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / OM HEIGHTS

Valid until 31 Dec 2030 Mixed Development project

OM HEIGHTS

By MBA DEVELOPERS PRIVATE LIMITED

RG-GJ-86071 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA17034/290626/311230 · Last updated on GujRERA portal: 16 Sep 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2030Possession promisedno revision filed
3 of 27Construction stages doneacross 3 buildings; furthest along: Plinth, 80%
261 of 302Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

OM HEIGHTS is a Mixed Development project by MBA DEVELOPERS PRIVATE LIMITED in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA17034/290626/311230 on 29 Jun 2026. Possession is promised by 31 Dec 2030. 41 of the 302 units on this registration are recorded sold or booked, and 3 of 27 construction stages are filed complete.

At a glance

Project

  • NameOM HEIGHTS
  • TypeMixed Development
  • Location
    • 120 FT. RING ROAD
    • NR. SAKAR PRIME
    • ZUNDAL
    • ZUNDAL
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA17034/290626/311230
  • ReraGenie IDRG-GJ-86071

Builder

  • NameMBA DEVELOPERS PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations1 more →

Key dates

this monthRegisteredJun 2026PromisedDec 2030

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2030
  • Registered on29 Jun 2026
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings3 building records
  • Documents filed45 files

Current status

14%41 of 302 units booked
5.5%Of the estimated cost spent so far

Figures as on 16 Sep 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B+C---722092
F+G---1120112
D+E---811798

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 16 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Plinth, at 80%.

A+B+C20%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
F+G20%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D+E20%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 16 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,305 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 63.50 cr
Cost incurredRs 3.50 cr
Spent of the estimate5.51%
BuildingWingEstimatedIncurred
A+B+CNARs 27.50 crRs 1.50 cr
D+ENARs 18.00 crRs 1.00 cr
F+GNARs 18.00 crRs 1.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAmiben Rajeshbhai Patel
EngineerJIGAR MAHESHKUMAR PATEL

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MAA17034/290626/311230 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)16 Sep 2026
Architect's certificate (Form 1)15 Sep 2026
Engineer's certificate (Form 2)15 Sep 2026
Engineer's certificate annexure15 Sep 2026
Site photograph, A+B+C15 Sep 2026
Site photograph, F+G15 Sep 2026
Site photograph, D+E15 Sep 2026
RERA registration certificate29 Jun 2026
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

14%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep OM HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near ZUNDAL1,600+ in Gandhinagar

2 kmOM HEIGHTSOther 172Dot size: filed unitsN

Filed coordinates, straight-line distance. 172 registered projects within 2 km.

Builder: MBA DEVELOPERS PRIVATE LIMITED

MBA DEVELOPERS PRIVATE LIMITED has 2 registrations on GujRERA, including OM ELEGANCE and OM HEIGHTS. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if OM HEIGHTS is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of OM HEIGHTS?

The registered promoter entity is MBA DEVELOPERS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in OM HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at OM HEIGHTS?

The professionals named in the filing: Architect: Amiben Rajeshbhai Patel; Engineer: JIGAR MAHESHKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM HEIGHTS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.