Oceanus White Meadows

By Oceanus Dwellings Pvt Ltd

RG-KA-84568 · RERA PRM/KA/RERA/1251/310/PR/270623/006023 · Last updated on RERA Karnataka portal: 18 Feb 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
3 of 17Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 90%
46 of 135Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 97 documents Report an error

Oceanus White Meadows is a Residential/Group Housing project by Oceanus Dwellings Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/270623/006023 on 27 Jun 2023. Possession is promised by 31 Dec 2028. 89 of the 135 units on this registration are recorded sold or booked, and 3 of 17 construction stages are filed complete.

At a glance

Project

  • NameOceanus White Meadows
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560083
  • Pincode560083
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/270623/006023
  • ReraGenie IDRG-KA-84568

Builder

  • NameOceanus Dwellings Pvt Ltd
  • Entity typeCompany
  • CINU07010KA2003PTC031632
  • GSTIN29AAACO6011G1ZP
  • Authorized SignatoryP K Chacko
  • Managing DirectorP K Chacko
  • DirectorDaisy Chacko
  • Project HeadVikhar Ahamed Khan
  • Other registrations3 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on27 Jun 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed97 files

Current status

66%89 of 135 units booked
62.9%Of the estimated cost spent so far

Figures as on 18 Feb 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Oceanus White Meadows---1350135

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 18 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 17 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 90%.

Building: 55% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)90%
Retaining wall (All types)90%
RCC or MS Framed structure90%
Masonry Construction90%
Plastering inside , outside & Ceiling90%
Joinery: Doors, Windows, Ventilators etc60%
Basic work of Water supply, Sanitary and Electrification60%
Dadoing, Skirting, Flooring, Tiles work (All types)60%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 18 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes45%
Sewage and Drainage SystemYes15%
Water conservation/rain water harvesting/recharge of ground waterYes45%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes56%
LiftsYes52%
Corridor/LobbiesYes50%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes100%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,070 sq m
Named landowners2
LandownerVillageDistrict
J P M Hospitalities Pvt ltd--
Oceanus Dwellings Pvt. Ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 37.81 cr
Cost incurredRs 23.77 cr
Spent of the estimate62.86%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 34.79 crRs 21.18 cr
On-site expenditure-Site OverheadRs 1.75 cr-
On-site expenditure-Consultants FeesRs 1.27 crRs 2.59 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVS Shrinivas
EngineerLakshmi Keshava
Chartered AccountantPadmanabha Bhat

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed97

As listed on the registration, under the names the promoter filed them with; the newest 80 of 97 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/270623/006023 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 White Meadows - Dec 25.pdf18 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 White Meadows - Dec 25.pdf18 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 White Meadows - Dec 25.pdf18 Feb 2026
Area StatementFile: 1 Area Statement.pdf23 Jun 2023
SIAAC - Clarification letterFile: 2 SIAAC - Clarification letter.pdf23 Jun 2023
KSPCB - Clarification letterFile: 3 KSPCB - Clarification letter.pdf23 Jun 2023
Commencement Certificate - Clarification letterFile: 4 Commencement Certificate - Clarification letter.pdf23 Jun 2023
Clarification on Single layout Map and OrderFile: 5 Clarification on Single layout Map and Order.pdf23 Jun 2023
RTC, survey 21-2-
Mutation, survey 21-2-
Encumbrance Certificate, survey 21-2-
Conversion/Alienation Order, survey 21-2-
Sale/Title/Gift Deed, survey 21-2-
JDA, survey 21-2-
Khatha, survey 21-2-
RTC, survey 21-2-
Mutation, survey 21-2-
Encumbrance Certificate, survey 21-2-
Conversion/Alienation Order, survey 21-2-
Sale/Title/Gift Deed, survey 21-2-
Khatha, survey 21-2-
Registration CertificateFile: Company Incorporation Letter.pdf-
Organization StructureFile: Organisation Chart.pdf-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf-
Balance Sheet 2021 - 2022File: balance sheet 21-22 with schedules.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet - 2020-21.pdf-
Balance Sheet 2019 - 2020File: Balance Sheet 2019-20.pdf-
Audited Profit and Loss Statement 2021 - 2022File: profit and loss 21-22 with schedules.pdf-
Audited Profit and Loss Statement 2020 - 2021File: P & L - 2020-21.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P & L 2019-20.pdf-
Director's Report 2021 - 2022File: director report 2021-22.pdf-
Director's Report 2020 - 2021File: Directors Report 2020-21.pdf-
Director's Report 2019 - 2020File: Directors Report 2019-20.pdf-
Cash Flow Statement 2021 - 2022File: Cash Flow FY 2021-22.pdf-
Cash Flow Statement 2020 - 2021File: Cash Flow - 2020-21.pdf-
Auditor's Report 2021 - 2022File: auditor report FY 2021-22.pdf-
Auditor's Report 2020 - 2021File: auditor report ODPL 2020-21.pdf-
Auditor's Report 2019 - 2020File: ODPL AUDIT REPORT-2019-20.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 2021-22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: IT computation and acknowledgement signed by CS - 2020-21.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: IT computaion and acknowledge 2019-20.pdf-
BBMP License-
BESCOM NOC with fee paid receipt-
BWSSB NOC with fee paid receipt-
BBMP Approved Plan-
BBMP Approved Plan-
BBMP Approved Plan-
Project Specification-
BBMP Approved Plan-
Project Specification-
BBMP Approved Plan-
Structural stability certifcate-
Search report-
JDA and GPA-
Title Deed-
Proforma Agreement of Sale-
Proforma Allotment Letter-
Form B Affidavit-
Sec 3(1) Non-Violation-
JDA Affidavit-
BESCOM NOC with fee paid receipt-
BWSSB NOC with fee paid receipt-
Unnamed document-
Unnamed document-
Fire NOC-
HAL NOC-
Unnamed document-
Unnamed document-
BSNL NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Bengaluru Urban

66%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Oceanus White Meadows on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmOceanus White MeadowsOther 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: Oceanus Dwellings Pvt Ltd

Oceanus Dwellings Pvt Ltd has 4 registrations on RERA Karnataka, including Oceanus White Meadows and Oceanus Classic. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Oceanus White Meadows is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Oceanus White Meadows?

The registered promoter entity is Oceanus Dwellings Pvt Ltd, a company as per the filing. Its CIN U07010KA2003PTC031632 and GSTIN 29AAACO6011G1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Oceanus White Meadows?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Oceanus White Meadows?

The professionals named in the filing: Architect: VS Shrinivas; Engineer: Lakshmi Keshava; Chartered Accountant: Padmanabha Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Oceanus White Meadows?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Oceanus White Meadows. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Oceanus White Meadows to a free account