Home / Browse projects / Bengaluru Urban, Karnataka / NVT A WONDERFUL WORLD PHASE I
NVT A WONDERFUL WORLD PHASE I
By NVT QUALITY LIFESTYLE ESTATE LLP
RG-KA-95273 · RERA PRM/KA/RERA/1251/308/PR/050126/008381 · Last updated on RERA Karnataka portal: 13 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
NVT A WONDERFUL WORLD PHASE I is a Residential/Group Housing project by NVT QUALITY LIFESTYLE ESTATE LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/050126/008381 on 5 Jan 2026. Possession is promised by 31 Dec 2030. 51 of the 123 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.
At a glance
Project
- NameNVT A WONDERFUL WORLD PHASE I
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 562107
- Pincode562107
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/050126/008381
- ReraGenie IDRG-KA-95273
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 Jan 2026
- Promised completion31 Dec 2030
- Revised completionNone
- Buildings1 building record
- Documents filed139 files
Current status
Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NVT A WONDERFUL WORLD PHASE I | - | - | - | 123 | 0 | 123 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 75%.
Building: 11% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 75% |
| Foundation footing work | 46% |
| Upto Plinth Level | 55% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 2% |
| Retaining wall (All types) | 2% |
| RCC or MS Framed structure | 5% |
| Masonry Construction | 2% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities41
As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Civic Amenities | Yes | 0% |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Shuba Pragathi Builders and Developers | - | - |
| Shuba Pragathi Builders and Developers | - | - |
| Shuba Pragathi Builders and Developers | - | - |
| Shuba Pragathi Builders and Developers | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 110.00 cr | Rs 21.89 cr |
| On-site expenditure-Consultants Fees | Rs 26.00 cr | Rs 2.72 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | S Sampath Kumar |
| Engineer | Pavan H K |
| Chartered Accountant | Jawaha S Nagpal |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed139
As listed on the registration, under the names the promoter filed them with; the newest 80 of 139 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/050126/008381 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: NVT A2W_Form 4 Q2.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Archi - NVT A2W.pdf | 13 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Eng - A2W.pdf | 13 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 13 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 13 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 13 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: NVT A2WForm 4 Q1 of FY 2026-27 Form - 4.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Quater 1 A2W ARTH.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Quater 1 A2W Engineer Cert.pdf | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: NVT A2W_Form 4 Q4 of FY 2025-26.pdf | 13 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: A2W Arch Certificate.pdf | 13 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: A2W Engineer Certificate.pdf | 13 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 13 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 13 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 13 Apr 2026 |
| Reason for Delay of ProjectFile: 2 Reason for Delay of Project.pdf | 3 Jan 2026 |
| Structural Stability CertificateFile: 3 Structural Stability Certificate.pdf | 3 Jan 2026 |
| Structural Engineer LicenseFile: 3 Structural Engineer License.pdf | 3 Jan 2026 |
| Project SpecificationFile: 4 Project Specification.pdf | 3 Jan 2026 |
| Proforma of AOSFile: 5 Proforma of AOS.pdf | 3 Jan 2026 |
| Land Cost CalculationFile: 6 Land Cost Calculation.pdf | 3 Jan 2026 |
| Guideline value certificateFile: 6 Guideline value certificate.pdf | 3 Jan 2026 |
| RTC, survey 41/1 | - |
| Mutation, survey 41/1 | - |
| Encumbrance Certificate, survey 41/1 | - |
| Conversion/Alienation Order, survey 41/1 | - |
| JDA, survey 41/1 | - |
| Khatha, survey 41/1 | - |
| RTC, survey 42 | - |
| Mutation, survey 42 | - |
| Encumbrance Certificate, survey 42 | - |
| Conversion/Alienation Order, survey 42 | - |
| JDA, survey 42 | - |
| Khatha, survey 42 | - |
| RTC, survey 43/1 | - |
| Mutation, survey 43/1 | - |
| Encumbrance Certificate, survey 43/1 | - |
| Conversion/Alienation Order, survey 43/1 | - |
| JDA, survey 43/1 | - |
| Khatha, survey 43/1 | - |
| RTC, survey 43/2 | - |
| Mutation, survey 43/2 | - |
| Encumbrance Certificate, survey 43/2 | - |
| Conversion/Alienation Order, survey 43/2 | - |
| JDA, survey 43/2 | - |
| Khatha, survey 43/2 | - |
| Registration CertificateFile: CIN.pdf | - |
| GST CertificateFile: GST.pdf | - |
| Partnership DeedFile: Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: Form 2 Architect Certi.pdf | - |
| Certificate issued by Engineer Form 3File: Form 3 Engineer Certi.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit Non-Litigation.pdf | - |
| Balance Sheet 2024 - 2025File: BS with Schedules 24-25.pdf | - |
| Balance Sheet 2023 - 2024File: BS with Schedules 23-24.pdf | - |
| Balance Sheet 2022 - 2023File: BS with Schedules 22-23.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: P&L 24-25.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: P&L 23-24.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: P&L 22-23.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: ITR 24-25.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ITR 23-24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR 22-23.pdf | - |
| Approval Letter | - |
| Approved Building Plan | - |
| Sectional Drawings | - |
| Structural Stability Certificate | - |
| Specifications | - |
| Brouchure NA | - |
| Relinquishmnet Deed | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| NVT UNDER THE OPEN SKY | Sy No.59/3 and 59/4 , Nimbekalpura Village , Bidarahalli Hobli, , Bengaluru East , Bengaluru Urban, Karnataka - 560049 | Ongoing | Mar 2029 | Not due yet |
| NVT SYMPHONY OF ORCHARDS | Sy No.41/1, 41/2, 41/4, 42/3, 45/1, 45/2, 45/4, 45/5, 50/1, 50/2 of Chambenahalli Village , & Sy No.78, 79/1, 79/2, 85, 87/1, 87/2 of Volagerikallahalli Village, Sarjapura Hobli, Anekal Taluk | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep NVT A WONDERFUL WORLD PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 10 registered projects within 2 km.
SHRIRAM 107SOUTHEAST - PHASE 3
Shriprop Living Space Private Limited
RAJ HIGH GARDENS
SNN Properties LLP
Sobha Madison Heights-Townpark Phase 2 W1 to 4
SOBHA LIMITED
DS MAX SKY SAMPADHA
DS MAX PROPERTIES PRIVATE LIMITED
Sobha Hamptons -Townpark Phase 1 W4 to 6
SOBHA LIMITED
Sobha Hamptons -Townpark Phase 2 W1 to 3
SOBHA LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: NVT QUALITY LIFESTYLE ESTATE LLP
NVT QUALITY LIFESTYLE ESTATE LLP has 3 registrations on RERA Karnataka, including NVT A WONDERFUL WORLD PHASE I and NVT SYMPHONY OF ORCHARDS. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if NVT A WONDERFUL WORLD PHASE I is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of NVT A WONDERFUL WORLD PHASE I?
The registered promoter entity is NVT QUALITY LIFESTYLE ESTATE LLP, a partnership firm as per the filing. Its LLPIN AAF-6902 and GSTIN 29AAMFN8285C1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in NVT A WONDERFUL WORLD PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at NVT A WONDERFUL WORLD PHASE I?
The professionals named in the filing: Architect: S Sampath Kumar; Engineer: Pavan H K; Chartered Accountant: Jawaha S Nagpal. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NVT A WONDERFUL WORLD PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback