Home / Browse projects / Bengaluru Urban, Karnataka / Nithya Infra Sunshine

Registration approved No litigation declared Residential/Group Housing project

Nithya Infra Sunshine

By Nithya Infra Sunshine

RG-KA-50243 · RERA PRM/KA/RERA/1251/446/PR/170625/007844 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
7 of 14Construction stages donefurthest along: Joinery: Doors, 50%
22 of 40Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 111 documents Report an error

Nithya Infra Sunshine is a Residential/Group Housing project by Nithya Infra Sunshine in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/170625/007844 on 17 Jun 2025. Possession is promised by 31 Dec 2027. 18 of the 40 units on this registration are recorded sold or booked, and 7 of 14 construction stages are filed complete.

At a glance

Project

  • NameNithya Infra Sunshine
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560043
  • Pincode560043
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/170625/007844
  • ReraGenie IDRG-KA-50243

Builder

  • NameNithya Infra Sunshine
  • Entity typePartnership Firm
  • GSTIN29AAXFN0391G1ZQ
  • Authorized SignatoryR Raghava Reddy

Key dates

this monthRegisteredJun 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Jun 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed111 files

Current status

45%18 of 40 units booked
21.9%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Nithya Infra Sunshine---40040

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 14 construction stages are filed complete. The stage furthest along is Joinery: Doors, at 50%.

Building: 71% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc50%
Basic work of Water supply, Sanitary and Electrification50%
Dadoing, Skirting, Flooring, Tiles work (All types)50%
Railing and Grill fixing50%
Electrification, Water supply and Sanitary Finishing50%
Painting50%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes75%
Sewage and Drainage SystemYes80%
Water conservation/rain water harvesting/recharge of ground waterYes75%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes75%
Storm water drainsYes75%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes80%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes75%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes75%
GymNoNot applicable
ParksNoNot applicable
Power BackupYes75%
Piped GasNoNot applicable
Water and SanitationYes75%
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsYes90%
Corridor/LobbiesYes75%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes75%
BasementNoNot applicable
TerraceYes95%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,332 sq m
Named landowners1
LandownerVillageDistrict
Nithya Infra Sunshine--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 26.92 cr
Cost incurredRs 5.88 cr
Spent of the estimate21.85%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 21.86 crRs 5.40 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 2.00 cr-
On-site expenditure-Site OverheadRs 1.50 crRs 48.42 lakh
Payment of taxesRs 1.50 cr-
On-site expenditure-Consultants FeesRs 6.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSRHENIVASA RAO G
EngineerSai krishna Mohan Vardhineni
Chartered AccountantSiva Shankar Ginkala

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed111

As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/170625/007844 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate Q2 2026-27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate Q2 2026-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer's Certificate Q2 2026-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate Q4 2025-26_compressed.pdf14 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Achitect Certificate Q4 2025-26.pdf14 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate Q4 2025-26.pdf14 Jul 2026
Q4 2025-26 Water supply and sewage board14 Jul 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q4 2025-26 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate Q1 2026-27_compressed.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate Q1 2026-27.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer's Certificate Q1 2026-27.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate Q3 2025-26_compressed.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate Q3 2025-26.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer's Certificate Q3 2025-26.pdf20 Feb 2026
Q3 2025-26 Water supply and sewage board20 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Feb 2026
Q3 2025-26 KPTCL- BESCOM20 Feb 2026
1. Upload profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedulesFile: 1 1 Nithya Financials Confirmation.pdf12 Jun 2025
1. ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey skFile: 2 1 ADLR Sketch.pdf12 Jun 2025
2. Approved Original Single Plot layout plan.File: 2 2 Single Plot Layout Plan.pdf12 Jun 2025
3. Approved Original Single Plot layout plan work order.File: 2 3 Single Plot Layout Order.pdf12 Jun 2025
4. Building License Original Copy.File: 2 4 BBMP Building Licence.pdf12 Jun 2025
5. Approved building plan ? Original CopyFile: 2 5 BBMP Approved Plan.pdf12 Jun 2025
6. Upload all original sanctioned drawings, floor plan, sectional drawings and elevations in reFile: 2 6 BBMP Approved Section Plan.pdf12 Jun 2025
6. Upload all original sanctioned drawings, floor plan, sectional drawings and elevations in reFile: 2 6 BBMP Approved Floor Plans.pdf12 Jun 2025
7. Upload commencement certificate.File: 2 7 Commencent Certificate.pdf12 Jun 2025
8. Approved Master plan Extract marked the proposed land and certified by the concern AuthorityFile: 2 8 CDP-Horamavu.pdf12 Jun 2025
9. Village map certified by the concern officer with demarcation of proposed land.File: 2 9 Village - chelekre.pdf12 Jun 2025
10. KSPCB NOC.File: 2 10 KSPCB NOC.pdf12 Jun 2025
1) Please upload STP DrawingFile: 3 1 Nitya STP-Model.pdf12 Jun 2025
2) Upload KSPCB NOCFile: 3 2 KSPCB NOC.pdf12 Jun 2025
3) Project Estimation certify by the Engineer not uploaded.File: 3 3 Engineer Cost Abstract.pdf12 Jun 2025
4) Land calculation letter not uploaded,File: 3 4 Land Cost Calculation.pdf12 Jun 2025
5) Open area details not matching with the Sanctioned Plan.File: 3 5 Updated.pdf12 Jun 2025
6) Terrace area not mentioned in the project details.File: 3 6 Updated.pdf12 Jun 2025
7) Upload the revised Stability Certificate as per the specification of the project.File: 3 7 Pre stability certificate Nitya Infra Sunshine.pdf12 Jun 2025
8) Date of completion mentioned in the Annexure 'A' of the Allotment Letter not matching with projecFile: 3 8 Profoma of Allotment Letter.pdf12 Jun 2025
9) Proforma Of sale Sale Agreement With BESCOM NOC DetailsFile: 3 9 Proforma - Agreement for Sale.pdf12 Jun 2025
RTC, survey 113-3-
Mutation, survey 113-3-
Encumbrance Certificate, survey 113-3-
Conversion/Alienation Order, survey 113-3-
Sale/Title/Gift Deed, survey 113-3-
Khatha, survey 113-3-
Registration CertificateFile: 2 Nithya Form-C.jpeg-
GST CertificateFile: 4 GST Certificate NIS.pdf-
Partnership DeedFile: 1 Partnership Deed NIS.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Auditor FORM-1.pdf-
Certificate issued by Architect Form 2File: Architect Form-2 .pdf-
Certificate issued by Engineer Form 3File: Engineer Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: 4 Non litigation Land Affidavit.pdf-
1 BBMP Approved Plan-1-
2 BBMP Approved Plan-2-
Pre-Stability Certificate-Nitya Infra Sunshine-
NIS Specifications-
Not Yet Ready-
Proforma - Agreement for Sale(AFS) - GOK-
Profoma of Allotment Letter-
2 FORM-B Affidavit-
1 Notarized Affidavit for 3(1) Voliation-
Legal Opinion-
1 1 BESCOM NOC-
3 1 BWSSB NOC-
Will Upload Later-
1 INAMS-
2 Sale Deed-2605-1952-53-

How this compares with Bengaluru Urban

45%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Nithya Infra Sunshine on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmNithya Infra SunshineOther 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: Nithya Infra Sunshine

Nithya Infra Sunshine has 1 registration on RERA Karnataka, including Nithya Infra Sunshine. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Nithya Infra Sunshine is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Nithya Infra Sunshine?

The registered promoter entity is Nithya Infra Sunshine, a partnership firm as per the filing. Its GSTIN 29AAXFN0391G1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Nithya Infra Sunshine?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Nithya Infra Sunshine?

The professionals named in the filing: Architect: SRHENIVASA RAO G; Engineer: Sai krishna Mohan Vardhineni; Chartered Accountant: Siva Shankar Ginkala. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nithya Infra Sunshine?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nithya Infra Sunshine. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nithya Infra Sunshine to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.