ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / NILKANTH RESIDENCY

Valid until 30 Sep 2021 Mixed Development project

NILKANTH RESIDENCY

By NILKANTH DEVELOPERS

RG-GJ-61590 · RERA PR/GJ/SURAT/CHORASI/SUDA/MAA02815/EX1/290121 · Last updated on GujRERA portal: 30 Sep 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2021Possession promisedmoved 12 months from the original
14 of 14Construction stages doneacross 2 buildings; every applicable stage filed complete
9 of 108Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

NILKANTH RESIDENCY is a Mixed Development project by NILKANTH DEVELOPERS in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORASI/SUDA/MAA02815/EX1/290121 on 4 Jun 2018. Possession is promised by 30 Sep 2021. The completion date has moved by 12 months from the original filing. 99 of the 108 units on this registration are recorded sold or booked, and 14 of 14 construction stages are filed complete.

At a glance

Project

  • NameNILKANTH RESIDENCY
  • TypeMixed Development
  • Location
    • 48
    • AT PALI VILLAGE
    • PALI
    • Pali
    • Chorasi
    • Surat
    • 394230
  • Pincode394230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORASI/SUDA/MAA02815/EX1/290121
  • ReraGenie IDRG-GJ-61590

Builder

  • NameNILKANTH DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations18 more →

Key dates

this monthRegisteredJun 2018First promiseSep 2020Revised toSep 2021

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2021
  • Registered on4 Jun 2018
  • Promised completion30 Sep 2021
  • Revised completionRevised to 30 Sep 2021 (originally 30 Sep 2020)
  • Buildings2 building records
  • Documents filed38 files

Current status

92%99 of 108 units booked
100.0%Of the estimated cost spent so far

Figures as on 30 Sep 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B---721890
C---18018

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 30 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 14 construction stages are filed complete across 2 buildings.

A+B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,506 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.00 cr
Cost incurredRs 3.00 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
A+BNARs 1.50 crRs 1.50 cr
CNARs 1.50 crRs 1.50 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/CHORASI/SUDA/MAA02815/EX1/290121Applied Jan 2021; approved Jan 2021

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORASI/SUDA/MAA02815/EX1/290121 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)30 Sep 2021
Engineer's certificate (Form 2)29 Sep 2021
Engineer's certificate annexure29 Sep 2021
Architect's certificate (Form 1)28 Sep 2021
Site photograph, A+B28 Sep 2021
Site photograph, C28 Sep 2021
RERA registration certificate4 Jun 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

92%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 12 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep NILKANTH RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Pali2,600+ in Surat

2 kmNILKANTH RESIDENCYOther 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: NILKANTH DEVELOPERS

NILKANTH DEVELOPERS has 19 registrations on GujRERA, including PAVAN EXOTICA and SHYAM ENCLAVE. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if NILKANTH RESIDENCY is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of NILKANTH RESIDENCY?

The registered promoter entity is NILKANTH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in NILKANTH RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in NILKANTH RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NILKANTH RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NILKANTH RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.