Valid until 30 Sep 2023 Residential/Group Housing project

L'OTUS

By BLUE FEATHERS INFRACON

RG-GJ-50324 · RERA PR/GJ/SURAT/CHORASI/SUDA/RAA06077/EX2/240723 · Last updated on GujRERA portal: 12 Jul 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Separate project account declared
Sep 2023Possession promisedmoved 24 months from the original
35 of 48Construction stages doneacross 7 buildings; furthest along: Installation of lifts, 85%
58 of 440Units unsoldnot recorded sold or booked
Jump to the 47 documents Report an error

L'OTUS is a Residential/Group Housing project by BLUE FEATHERS INFRACON in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/CHORASI/SUDA/RAA06077/EX2/240723 on 21 Sep 2019. Possession is promised by 30 Sep 2023. The completion date has moved by 24 months from the original filing. 382 of the 440 units on this registration are recorded sold or booked, and 35 of 48 construction stages are filed complete.

At a glance

Project

  • NameL'OTUS
  • TypeResidential/Group Housing
  • Location
    • BLOC NO. 379/B/2
    • T.P.S NO. 59(PARDI KANDE-SACHIN-KANSAD) O.P. NO. 136/A
    • F.P. NO. 136/B
    • MOJE SACHIN
    • Sachin
    • Chorasi
    • Surat
    • 394230
  • Pincode394230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/CHORASI/SUDA/RAA06077/EX2/240723
  • ReraGenie IDRG-GJ-50324

Builder

  • NameBLUE FEATHERS INFRACON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2019First promiseSep 2021Revised toSep 2023

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2023
  • Registered on21 Sep 2019
  • Promised completion30 Sep 2023
  • Revised completionRevised to 30 Sep 2023 (originally 30 Sep 2021)
  • Buildings7 building records
  • Documents filed47 files

Current status

87%382 of 440 units booked
74.6%Of the estimated cost spent so far

Figures as on 12 Jul 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1---60060
A2---60060
A3---60060
B1---70070
B2---70070
C1---60060
D1---60060

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building7

As on 12 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

35 of 48 construction stages are filed complete across 7 buildings. The stage furthest along is Installation of lifts, at 85%.

A194%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
A294%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing50%
A366%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats60%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing25%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
B197%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing75%
B298%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing85%
C156%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure40%
Internal walls, internal plaster, floorings, doors and windows within flats20%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable
D164%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure30%
Internal walls, internal plaster, floorings, doors and windows within flatsNot applicable
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofingNot applicable
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishingNot applicable

Progress on shared amenities19

As on 12 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes60%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes50%
Storm water drainsYes0%
Landscaping and tree plantingYes75%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes20%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes40%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,925 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.51 cr
Cost incurredRs 9.34 cr
Spent of the estimate74.63%
BuildingWingEstimatedIncurred
A1NARs 1.79 crRs 1.33 cr
A2NARs 1.79 crRs 1.33 cr
A3NARs 1.79 crRs 1.33 cr
B1NARs 1.79 crRs 1.33 cr
B2NARs 1.79 crRs 1.33 cr
C1NARs 1.79 crRs 1.33 cr
D1NARs 1.79 crRs 1.33 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSWATI R. BUTANI
EngineerJAY B. LAKHANAKIYA

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/SURAT/CHORASI/SUDA/RAA06077/EX1/171221Applied Sep 2021; approved Dec 2021
PR/GJ/SURAT/CHORASI/SUDA/RAA06077/EX2/240723Applied Jul 2023; approved Jul 2023

Documents filed47

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/CHORASI/SUDA/RAA06077/EX2/240723 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)12 Jul 2023
Site photograph, A112 Jul 2023
Site photograph, A212 Jul 2023
Site photograph, A312 Jul 2023
Site photograph, B112 Jul 2023
Site photograph, B212 Jul 2023
Site photograph, C112 Jul 2023
Site photograph, D112 Jul 2023
Engineer's certificate (Form 2)7 Apr 2022
Engineer's certificate annexure7 Apr 2022
Accountant's certificate (Form 3)7 Apr 2022
RERA registration certificate21 Sep 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Surat

87%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one moved by 24 months

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep L'OTUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Sachin2,600+ in Surat

2 kmL'OTUSOther 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: BLUE FEATHERS INFRACON

BLUE FEATHERS INFRACON has 1 registration on GujRERA, including L'OTUS. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if L'OTUS is delayed beyond 30 Sep 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of L'OTUS?

The registered promoter entity is BLUE FEATHERS INFRACON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in L'OTUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at L'OTUS?

The professionals named in the filing: Architect: SWATI R. BUTANI; Engineer: JAY B. LAKHANAKIYA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in L'OTUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About L'OTUS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save L'OTUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.