NAVCHAITNYA ELITE
RG-KA-65948 · RERA PRM/KA/RERA/1249/447/PR/241225/008357 · Last updated on RERA Karnataka portal: 14 Apr 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
NAVCHAITNYA ELITE is a Residential/Group Housing project by NAVCHAITANYA DEVELOPERS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/241225/008357 on 24 Dec 2025. Possession is promised by 31 Dec 2028.
At a glance
Project
- NameNAVCHAITNYA ELITE
- TypeResidential/Group Housing
- Location
- Belagavi
- PincodeNot stated
- RERA no.PRM/KA/RERA/1249/447/PR/241225/008357
- ReraGenie IDRG-KA-65948
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on24 Dec 2025
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed91 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NAVCHAITANYA ELITE | - | - | - | 35 | 0 | 35 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities40
As on 14 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| NAVCAHITANYA DEVELOPERS | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 5.62 cr | - |
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 1.50 cr | - |
| On-site expenditure-Salaries of workers | Rs 15.00 lakh | - |
| On-site expenditure-Consultants Fees | Rs 12.00 lakh | - |
| Payment of taxes | Rs 5.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARUN NETAJI KURADE |
| Engineer | SHRIJAY GOPALKRISHNA KALGHATGI |
| Chartered Accountant | VIJAY R CHAPPAR |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed91
As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/241225/008357 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERT.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Arch Cert.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Cert.pdf | 14 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Cert 311225.pdf | 21 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Arch Cert 311225.pdf | 21 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Cert 311225.pdf | 21 Feb 2026 |
| Q3 2025-26 Water supply and sewage board | 21 Feb 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 21 Feb 2026 |
| Q3 2025-26 KPTCL- BESCOM | 21 Feb 2026 |
| ALLOTMENT LETTERFile: (9) Allotment letter.pdf | 19 Sep 2025 |
| WATER SUPPLY AFFIDAVITFile: water affidavit.pdf | 19 Sep 2025 |
| BANK STATEMENT FOR 100%File: (3) BANK AC 100%.pdf | 16 Sep 2025 |
| BANK STATEMENT FOR 70%File: (3) BANK AC 70%.pdf | 16 Sep 2025 |
| BANK STATEMENT FOR 30%File: (3) BANK AC 30%.pdf | 16 Sep 2025 |
| PROFT AND LOSS A/C 21-22File: PnL 21-22.pdf | 16 Sep 2025 |
| BALANCE SHEET 21-22File: Bal Sheet 21-22.pdf | 16 Sep 2025 |
| PROFIT AND LOSS 22-23File: PnL 22-23.pdf | 16 Sep 2025 |
| BALANCE SHEET 22-23File: Bal Sheet 22-23.pdf | 16 Sep 2025 |
| PROFIT AND LOSS 23-24File: PnL 23-24.pdf | 16 Sep 2025 |
| BALANCE SHEET 23-24File: Bal Sheet 23-24.pdf | 16 Sep 2025 |
| CURRENT YEAR RTCFile: (1) RTC current year.pdf | 16 Sep 2025 |
| MUTATIONFile: (2) Mutation.pdf | 16 Sep 2025 |
| MRFile: (3) MR.pdf | 16 Sep 2025 |
| NOTARIZED AFFIDVIT FORM BFile: (4) Form B.pdf | 16 Sep 2025 |
| NON LITIGATIONSFile: (5) NO LETIGATION AFFIDIVATE.pdf | 16 Sep 2025 |
| ECFile: (6) EC_compressed.pdf | 16 Sep 2025 |
| SINGAL LAYOUT APPROVAL LETTERFile: (1) Layout letter.pdf | 16 Sep 2025 |
| SINGAL LAYOUT PLANFile: (2) Single Layout Plan.pdf | 16 Sep 2025 |
| LAYOUT PLANFile: (2) Layout Plan.pdf | 16 Sep 2025 |
| BUILDING PERMISSION PLANFile: (3) Building Plan Drawing.pdf | 16 Sep 2025 |
| BUILDING LICENCEFile: (4) Building Licence.pdf | 16 Sep 2025 |
| EXTRACT MASTER PLANFile: (5) Master Plan.pdf | 16 Sep 2025 |
| VILLAGE MAP CONCENT LETTERFile: (6) Village Map.pdf | 16 Sep 2025 |
| ZRFile: (7) ZR.pdf | 16 Sep 2025 |
| JOINT ADLR SURVEY SKETCHFile: (8) Joint ADLR Servy Sketch.pdf | 16 Sep 2025 |
| EACH FLOOR PLANFile: (9) Floor and Section Plan.pdf | 16 Sep 2025 |
| KSPCB NOCFile: (10) Pollution Noc.pdf | 16 Sep 2025 |
| SEIAA NOC CONCENT LETTERFile: (11) Consent letter for SEIAA NOC.pdf | 16 Sep 2025 |
| ENGINEER LICENCEFile: (3) Engg Licence_compressed.pdf | 16 Sep 2025 |
| CA RERA REG CERTIFICATEFile: (4) CA RERA Reg Cert.pdf | 16 Sep 2025 |
| ENGG RERA CERTIFICATEFile: (4) Eng Rera Rera Cert.pdf | 16 Sep 2025 |
| ENGINEER FORM NO 6File: (5) Engg Form No 6.pdf | 16 Sep 2025 |
| STABILITY CERTIFICATEFile: (6) Stabilty Cert Shrijay.pdf | 16 Sep 2025 |
| STRUCTRAL ENGG LICENCEFile: (6) Structural Engg Licence.pdf | 16 Sep 2025 |
| PROJECT SPECIFICATIONFile: (7) Project Specification.pdf | 16 Sep 2025 |
| PROFORMA SALES AGREEEMENTFile: (8) Proforma Sale Agreement.pdf | 16 Sep 2025 |
| WATER SUPPLY ACKFile: WATER SUPPLY ACK.pdf | 16 Sep 2025 |
| WATER SUPPLY AFFIDAVITFile: Affdivate for WATER NOC.pdf | 16 Sep 2025 |
| PROJECT ESTIMTION ENGG SIGNFile: (11) Project Estimation Engg Sign.pdf | 16 Sep 2025 |
| LAND COST DETAILSFile: (13) Land cost Selft Attested.pdf | 16 Sep 2025 |
| STP DESIGN DRAWINGFile: (14) STP Design Drwaing.pdf | 16 Sep 2025 |
| Registration CertificateFile: Partnership Reg Cert.pdf | - |
| GST CertificateFile: gst certificate.pdf | - |
| Partnership DeedFile: Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: CA REG CERTIFICATE MOD.pdf | - |
| Certificate issued by Architect Form 2File: Arch RERA Reg Cert.pdf | - |
| Certificate issued by Engineer Form 3File: Eng Rera Rera Cert.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: (5) NO LETIGATION AFFIDIVATE.pdf | - |
| Balance Sheet 2023 - 2024File: Nav Bal Sheet 31-3-24.pdf | - |
| Balance Sheet 2022 - 2023File: Nav Bal Sheet 31-3-23.pdf | - |
| Balance Sheet 2021 - 2022File: Nav Bal Sheet 31-3-22.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: Nav PnL 31-3-22.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: Nav PnL 31-3-23.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Nav PnL 31-3-24.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: Nav IT Ret 31-3-22.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: Nav IT Ret 31-3-23.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: Nav It Ret 31-3-24.pdf | - |
| Approval Certificate (3) | - |
| Approved Drawing | - |
| NAVCHAITANYA ELITE-SECTIONS-Model | - |
| Stabilty Cert Shrijay | - |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| NAVCHAITANYA RESIDENCY | CTS NO.318/1, DATTA GALLI, SONAR GALLI CORNER, M.VADGAON, BELAGAVI | Completed | - | No date filed |
| BHANDARE RESIDENCY | CTS NO.450 CCB NO.558/A DATTA GALLI, M.VADGAON, BELAGAVI | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep NAVCHAITNYA ELITE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Swarna Griha - 4 Phase 1
Felicity Adobe LLP
SkyCity Homes
M/s. Vishal Infra Built Ltd.
Shree Sant Babamaharaj Complex
Ratuja Developers
Pinnacle
Lotus Landmakrs (I) Pvt Ltd
JYOTICHANDRA
G P DEVELOPERS
SHIVNERI Apartment
SHIVNERI CONSTRUCTIONS
See every Belagavi project, with the district possession charts
Builder: NAVCHAITANYA DEVELOPERS
NAVCHAITANYA DEVELOPERS has 3 registrations on RERA Karnataka, including NAVCHAITANYA RESIDENCY and BHANDARE RESIDENCY. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if NAVCHAITNYA ELITE is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of NAVCHAITNYA ELITE?
The registered promoter entity is NAVCHAITANYA DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AAOFN5131D1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in NAVCHAITNYA ELITE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at NAVCHAITNYA ELITE?
The professionals named in the filing: Architect: ARUN NETAJI KURADE; Engineer: SHRIJAY GOPALKRISHNA KALGHATGI; Chartered Accountant: VIJAY R CHAPPAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in NAVCHAITNYA ELITE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.