ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Navavedam's SunCrest

Registration approved No litigation declared Residential/Group Housing project

Navavedam's SunCrest

By Navavedam Ventures Pvt Ltd

RG-KA-57889 · RERA PRM/KA/RERA/1251/446/PR/250924/007067 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2027Possession promisedno revision filed
1 of 18Construction stages donefurthest along: Foundation footing work, 80%
0Complaints at RERA Karnatakaon this registration
Jump to the 185 documents Report an error

Navavedam's SunCrest is a Residential/Group Housing project by Navavedam Ventures Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/250924/007067 on 25 Sep 2024. Possession is promised by 14 Jun 2027.

At a glance

Project

  • NameNavavedam's SunCrest
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/250924/007067
  • ReraGenie IDRG-KA-57889

Builder

  • NameNavavedam Ventures Pvt Ltd
  • Entity typeOther ( Private Limited )
  • CINU70109KA2021PTC151314
  • GSTIN29AAHCN7814K1ZX
  • Authorized SignatoryKishore Kumar Gattu
  • Managing DirectorKISHORTE KUMAR GATTU
  • DirectorKISHORE KUMAR GATTU
  • Project HeadAmal Rajan

Key dates

this monthRegisteredSep 2024PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 Sep 2024
  • Promised completion14 Jun 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed185 files

Current status

3.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Row Villas---52052

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 18 construction stages are filed complete. The stage furthest along is Foundation footing work, at 80%.

Building: 13% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work80%
Retaining wall (All types)60%
Plinth level Beam0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
RCC or MS Framed structure0%
Masonry construction: Bricks, Concrete blocks etc0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Painting0%
Elevation work0%
Internal and External work including landscapes as per santioned drawings0%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Internal Roads & FootpathsYes0%
Sewage and Drainage SystemYes0%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes0%
Air Conditioning And incerntionNoNot applicable
StaircasesYes5%
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorYes0%
Fire escapesYes0%
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,801 sq m
Named landowners4
LandownerVillageDistrict
Venkatalakshmamma--
Venkatalakshmamma--
Venkatalakshmamma--
Venkatalakshmamma--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 50.72 cr
Cost incurredRs 1.92 cr
Spent of the estimate3.79%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 25.90 crRs 76.54 lakh
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 16.95 crRs 67.01 lakh
Payment of feesRs 2.59 cr-
On-site expenditure-Salaries of workersRs 2.16 crRs 29.40 lakh
Payment of taxesRs 1.29 crRs 6.22 lakh
On-site expenditure-Consultants FeesRs 1.00 crRs 6.05 lakh
Payment of cessRs 25.90 lakh-
Payment of chargesRs 25.90 lakh-
On-site expenditure-Site OverheadRs 12.95 lakhRs 6.90 lakh
Payment of PremiumsRs 10.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 7.77 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitect Rushikesh.H
EngineerManoj P
Chartered AccountantM Gopi Krishna & Associates

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed185

As listed on the registration, under the names the promoter filed them with; the newest 80 of 185 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/250924/007067 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 1 RERA CA signed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: NAVAVEDAMForm5ArchitectsCertificate 4 2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6.pdf15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Renewed Approved Building planFile: scan0188_compressed.pdf26 Jul 2026
Renewed Approved Building planFile: scan0189_compressed_1.pdf26 Jul 2026
Renewed Approved Building planFile: scan0190_compressed.pdf26 Jul 2026
Renewed Approved Building planFile: scan0191compressed.pdf26 Jul 2026
Renewed Approved Building plan order letterFile: Commencement Certificate (2).pdf26 Jul 2026
Kindly upload the sold and unsold units details and allottees list clearly duly mentioning the projFile: RERA enclosed letter.pdf26 Jul 2026
Kindly upload elaborated structural stability certificate clearly stating the number of floors consiFile: Engineer Certificate (1).pdf26 Jul 2026
Kindly upload elaborated structural stability certificate clearly stating the number of floors consiFile: Provisional Structural Stability Certifiacte.pdf26 Jul 2026
Kindlyupload revised NOC's for increased loads.File: NOC regarding RERA.pdf26 Jul 2026
Promoter need to upload details of new land added.File: RERA change (1).pdf26 Jul 2026
TITLE DEED INFAVOUR OF JDA LAND OWNER VENKATA LAKSHMAMMAFile: 2024-08-15_110921_kishor1_compressed.pdf20 Aug 2024
SINGLE LAYOUT ORDERFile: Single layout order.pdf14 Aug 2024
PROJECT SPECIFICATIONFile: Specification.pdf14 Aug 2024
STRUCTURAL SAFETY ADOPTED FOR THE PROPOSED BUILDINGFile: Structural safety.pdf14 Aug 2024
KSPCB NOC WITH FEES RECEIPTFile: KSPCB NOC with fees receipt.pdf14 Aug 2024
JDA SY NO 73 6File: JDA Sy No 73 6.pdf14 Aug 2024
PROJECT AMINITIESFile: Aminities.pdf14 Aug 2024
PROJECT CARPET AREA CALCULATIONSFile: carpet area calculation.pdf14 Aug 2024
CDP MAPFile: CDP navavedam.pdf14 Aug 2024
BRIEF ESTIMATED COST OF CONSTRUCIONSFile: img20240803_12175389.pdf14 Aug 2024
CLARIFICATION ON RTCFile: Affidavit for Sale permission.pdf14 Aug 2024
STP DESINGFile: STP-NAVAVEDAM-35 KLD-1.pdf14 Aug 2024
Order CopyFile: inam oblition order-Printout.pdf4 Jul 2024
Clarification on Order copyFile: IHC Order note.pdf4 Jul 2024
ClarificationFile: LRFBE CR 13 (1).pdf4 Jul 2024
Form BFile: FORM B Singed Copy.pdf4 Jul 2024
Non litigation affidavitFile: Affidivit Singed.pdf4 Jul 2024
Singal Plan Order copyFile: scan0441.pdf4 Jul 2024
Certified carpet area calculationFile: AREA CALCULATION CERTIFICATE.pdf4 Jul 2024
Village MapFile: Village Map.jpeg4 Jul 2024
KSPCB CFEFile: Naveveda20240703_14074046.pdf4 Jul 2024
building licenseFile: Commencement Letter.pdf4 Jul 2024
Floor PlansFile: Plan -1 of 4.pdf4 Jul 2024
Floor PlansFile: Plan -2 of 4.pdf4 Jul 2024
Floor PlansFile: Plan -3 of 4.pdf4 Jul 2024
Floor PlansFile: Plan -4 of 4.pdf4 Jul 2024
ElevationsFile: Soul Street by Navavedam-Rear View-TYPE A&B.jpg4 Jul 2024
ZR CopyFile: zr2031-final.pdf4 Jul 2024
Area DetailsFile: NV_BUILT UP AREA CALCULATIONS+RERA_25-05-2024 (1).xlsx4 Jul 2024
Engineer licenseFile: Engineer Certificate.pdf4 Jul 2024
Comman Area DetailsFile: NV_BUILT UP AREA CALCULATIONS+RERA_25-05-2024 (1).xlsx4 Jul 2024
Engineer CertificateFile: FORM 3 SIGNED COPY (3).pdf4 Jul 2024
STPFile: 20240419_NV_STP DEMARKATION PLAN.pdf4 Jul 2024
Agreement of Sale PerformaFile: Agreement of Sale Proforma_Updated (1).pdf4 Jul 2024
FacilitiesFile: Facilities.pdf4 Jul 2024
Land CostFile: Land cost.pdf4 Jul 2024
AffidivitFile: Affidivit Singed.pdf4 Jul 2024
JDFile: JDA Sy No 73-6_compressed_compressed (1).pdf4 Jul 2024
KhataFile: Khata copy.pdf4 Jul 2024
AgreementFile: Agreement of Sale Proforma_Updated (1) (1).pdf4 Jul 2024
Bank AffidavitFile: BANK Affidavit.pdf29 May 2024
CA certificateFile: Certificate by Chartered accountant.pdf29 May 2024
Kishore Adhar Card Director 1File: kishore adhar self.pdf29 May 2024
KIshore Pan Drector 1File: kishore pan self.pdf29 May 2024
Rajani Adharcard Director 2File: RAJANI ADHAR_compressed.pdf29 May 2024
Rajani PAN Director 2File: RAJANI PAN_compressed.pdf29 May 2024
CA CertificateFile: COP Signed.pdf29 May 2024
BANK Loan applicationFile: 2024-04-25 19-21 (1).pdf29 May 2024
Networth Valu KishoreFile: KISHORE NETWOR.pdf29 May 2024
EC from 01.04.2008 to till date for Sy.no.73/6 with transaction detailsFile: ECC-25042024-593642.pdf29 May 2024
Relinquishment DeedFile: Relinquishment Deed.pdf29 May 2024
Uploaded Khata extent 7642.74 Sqm and JDA extent 2.04.08 A-G , approved plan extent 7801 sqm, henceFile: Khata copy.pdf29 May 2024
`B’ Kharab confirmation order issued by Revenue Dept. for Sy no.73/6 Ext: 0-04.08 guntas.File: B Kharab Note.pdf29 May 2024
Approved Project plan Sy no.73/6 Ext: 2-00 A-G and mentioned project detail Sy No.73/6 only,File: IHC Order note.pdf29 May 2024
Notarized Non litigationFile: Affidivit.pdf29 May 2024
Form BFile: FORM B (1).pdf29 May 2024
Guidance ValuFile: Guidence Value.pdf29 May 2024
Total Area Covers Area, Open AreaFile: NV_BUILT UP AREA CALCULATIONS+RERA_25-04-2024 (1).xlsx29 May 2024
Breakup of types of unitsFile: NV_BUILT UP AREA CALCULATIONS+RERA_25-04-2024 (1).xlsx29 May 2024
Single plot lay outFile: Single plan approval.pdf29 May 2024
Single plot Layout approval orderFile: sigal plot approval order copy.pdf29 May 2024
CDP MAPFile: CDP Map.pdf29 May 2024
SECTION DrawningsFile: Plan -1 of 4.pdf29 May 2024
Section DrawningsFile: Plan -2 of 4.pdf29 May 2024
Section DrawningFile: Plan -3 of 4.pdf29 May 2024

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Navavedam's SunCrest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmNavavedam's SunCrestOther 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Navavedam Ventures Pvt Ltd

Navavedam Ventures Pvt Ltd has 1 registration on RERA Karnataka, including Navavedam's SunCrest. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Navavedam's SunCrest is delayed beyond 14 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Navavedam's SunCrest?

The registered promoter entity is Navavedam Ventures Pvt Ltd, an other ( private limited ) as per the filing. Its CIN U70109KA2021PTC151314 and GSTIN 29AAHCN7814K1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Navavedam's SunCrest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Navavedam's SunCrest?

The professionals named in the filing: Architect: Architect Rushikesh.H; Engineer: Manoj P; Chartered Accountant: M Gopi Krishna & Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Navavedam's SunCrest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Navavedam's SunCrest. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Navavedam's SunCrest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.