Home / Browse projects / Bengaluru Urban, Karnataka / NATURA ATAVI II

Registration approved No litigation declared Residential/Group Housing project

NATURA ATAVI II

By CACHET PROJECTS LLP

RG-KA-67772 · RERA PRM/KA/RERA/1251/308/PR/200123/005642 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2030Possession promisedno revision filed
10 of 16Construction stages donefurthest along: Painting, 98%
18 of 96Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 170 documents Report an error

NATURA ATAVI II is a Residential/Group Housing project by CACHET PROJECTS LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/200123/005642 on 20 Jan 2023. Possession is promised by 31 Dec 2030. 78 of the 96 units on this registration are recorded sold or booked, and 10 of 16 construction stages are filed complete.

At a glance

Project

  • NameNATURA ATAVI II
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562107
  • Pincode562107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/200123/005642
  • ReraGenie IDRG-KA-67772

Builder

  • NameCACHET PROJECTS LLP
  • Entity typePartnership Firm
  • GSTIN29AAKFC5202A1ZY
  • Authorized SignatoryMr.B Chiranjeevi
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2023PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jan 2023
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed170 files

Current status

81%78 of 96 units booked
7.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NATURA ATAVI II---96096

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 16 construction stages are filed complete. The stage furthest along is Painting, at 98%.

Building: 98% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing96%
Electrification, Water supply and Sanitary Finishing96%
Painting98%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)95%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work95%
Internal and External work including landscapes as per sanctioned drawings96%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes98%
Sewage and Drainage SystemYes95%
Water conservation/rain water harvesting/recharge of ground waterYes98%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes98%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes95%
Electricity supply transformer and substationYes95%
Storm water drainsYes100%
Use of renewable energyYes95%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes98%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes100%
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes100%
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership7

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area26,911 sq m
Named landowners7
LandownerVillageDistrict
Hosur Ramaiah--
Venkatesh--
Pillamma--
Ramesh--
Chandrappa--
Venkatesh--
B R Murthy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 87.10 cr
Cost incurredRs 6.06 cr
Spent of the estimate6.96%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 75.00 crRs 5.30 cr
Admin and Marketing CostRs 6.76 cr-
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 4.80 crRs 38.54 lakh
On-site expenditure-Consultants FeesRs 53.77 lakhRs 37.39 lakh
Payment of taxes-Rs 78,553

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectFWD ARCHITECTS
EngineerCRATIS DESIGNERS PVT LTD
Chartered AccountantNIRANJAN REDDY and ASSOCIATES

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed170

As listed on the registration, under the names the promoter filed them with; the newest 80 of 170 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/200123/005642 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form - 4 CA Certificate Natura QU SEP 2026_.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form - 5 Architect Certificate Natura QU SEP 2026.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 6 Engineer Certificate Natura QU SEP 2026.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4- JUNE 26 -NATURA ATAVII II.pdf11 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 -JUNE 26- NATURA ATAVI II.pdf11 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 6 - QU JUNE 26- NATURA ATAVI II.pdf11 Jul 2026
Q1 2026-27 Water supply and sewage board11 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)11 Jul 2026
Q1 2026-27 KPTCL- BESCOM11 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA March 26 Cachet.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect March 26 Cachet.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer March 26 Cachet.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Dec 25.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Dec 25.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Dec 25.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
ATAVI QUARTERLY REPORTSFile: FINAL -Quarterly update Details.pdf17 Jan 2023
ATTAVI FINAL RELEASE ORDERFile: ATTAVI FINAL RELEASE ORDER (2).pdf17 Jan 2023
ATTAVI Apply For CompletionFile: Apply For Completion.pdf17 Jan 2023
60_1 Title deedsFile: 60_1 Title deeds compressed.pdf30 Dec 2022
62_5 title deedFile: 62_5 title deed.pdf30 Dec 2022
62_7001File: 62_7001.pdf30 Dec 2022
63_1 title deedFile: 63_1 title deed.pdf30 Dec 2022
63_2 title deedFile: 63_2 title deed.pdf30 Dec 2022
Agreement For SaleFile: Agreement For Sale.pdf30 Dec 2022
akarbandh mergedFile: akarbandh merged.pdf30 Dec 2022
Allotment Letter DraftFile: Allotment Letter Draft.pdf30 Dec 2022
ASSOCIATION LETTER001File: ASSOCIATION LETTER001.pdf30 Dec 2022
ATAVI_SITE LocationFile: ATAVI_SITE Location.pdf30 Dec 2022
CA Certificate Form_1File: CA Certificate Form_1.pdf30 Dec 2022
Certified Carpet AREAS ATAVIFile: Carpet AREAS ATAVI.pdf30 Dec 2022
CDP MapFile: CDP Map.jpeg30 Dec 2022
Conversion OrderFile: Conversion Order.pdf30 Dec 2022
Development Plan OrderFile: Development Plan Order.pdf30 Dec 2022
Development PLANFile: Development PLAN.pdf30 Dec 2022
EstimateFile: Estimate.pdf30 Dec 2022
Existing Layout planFile: Existing Layout plan.pdf30 Dec 2022
JDAFile: JDA.pdf30 Dec 2022
podi 62_7001File: podi 62_7001.pdf30 Dec 2022
PROJECT SITEFile: PROJECT SITE.pdf30 Dec 2022
Relinuishment deedFile: Relinuishment deed.pdf30 Dec 2022
Sanction PlanFile: Sanction Plan.pdf30 Dec 2022
Section DrawingFile: Section Drawing.pdf30 Dec 2022
sketch all sy nosFile: sketch all sy nos.pdf30 Dec 2022
STP Master plan Sewage Disposal layoutFile: STP Master plan Sewage Disposal layout.pdf30 Dec 2022
Title deed 62_2File: Title deed 62_2.pdf30 Dec 2022
title deedFile: title deed.pdf30 Dec 2022
VILLAGE MAPFile: VILLAGE MAP.pdf30 Dec 2022
RTC, survey 62/1 and 62/7-
Mutation, survey 62/1 and 62/7-
Encumbrance Certificate, survey 62/1 and 62/7-
Conversion/Alienation Order, survey 62/1 and 62/7-
Sale/Title/Gift Deed, survey 62/1 and 62/7-
JDA, survey 62/1 and 62/7-
Khatha, survey 62/1 and 62/7-
RTC, survey 62/2-
Mutation, survey 62/2-
Encumbrance Certificate, survey 62/2-
Conversion/Alienation Order, survey 62/2-
Sale/Title/Gift Deed, survey 62/2-
JDA, survey 62/2-
Khatha, survey 62/2-
RTC, survey 62/5-
Mutation, survey 62/5-
Encumbrance Certificate, survey 62/5-
Conversion/Alienation Order, survey 62/5-
Sale/Title/Gift Deed, survey 62/5-
JDA, survey 62/5-
Khatha, survey 62/5-
RTC, survey 63/1-
Mutation, survey 63/1-
Encumbrance Certificate, survey 63/1-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
ATAVISy no.57,59/3/4, 60/2/4/5/6/7/8/9, 62/3/4, 63/3 situated at S Medhalli Village, Sarjapura Hobli, Anekal Taluk, Bangalore.OngoingDec 2022Not delivered

How this compares with Bengaluru Urban

81%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep NATURA ATAVI II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmNATURA ATAVI IIOther 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: CACHET PROJECTS LLP

CACHET PROJECTS LLP has 2 registrations on RERA Karnataka, including ATAVI and NATURA ATAVI II. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if NATURA ATAVI II is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NATURA ATAVI II?

The registered promoter entity is CACHET PROJECTS LLP, a partnership firm as per the filing. Its GSTIN 29AAKFC5202A1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NATURA ATAVI II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NATURA ATAVI II?

The professionals named in the filing: Architect: FWD ARCHITECTS; Engineer: CRATIS DESIGNERS PVT LTD; Chartered Accountant: NIRANJAN REDDY and ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NATURA ATAVI II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NATURA ATAVI II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NATURA ATAVI II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.