Home / Browse projects / Davangere, Karnataka / Nallur Shantharam Retreat
Nallur Shantharam Retreat
By Nainika Infrastructure Pvt Ltd
RG-KA-72534 · RERA PRM/KA/RERA/1258/404/PR/271123/006443 · Last updated on RERA Karnataka portal: 10 Feb 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Nallur Shantharam Retreat is a Residential/Group Housing project by Nainika Infrastructure Pvt Ltd in Davangere, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1258/404/PR/271123/006443 on 27 Nov 2023. Possession is promised by 31 Dec 2026. 6 of the 30 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.
At a glance
Project
- NameNallur Shantharam Retreat
- TypeResidential/Group Housing
- Location
- Davanagere
- Davangere
- 577004
- Pincode577004
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1258/404/PR/271123/006443
- ReraGenie IDRG-KA-72534
Builder
- NameNainika Infrastructure Pvt Ltd
- Entity typeCompany
- CINU45201KA2021PTC153915
- GSTIN29AAHCN9052H1Z2
- Authorized SignatoryMahesh DM
- MdMahesh DM
- DirectorsMahesh DM, Archana KS, Srinivas BV, Ashwini Srinivas
- Project HeadMahesh DM
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on27 Nov 2023
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed68 files
Current status
Figures as on 10 Feb 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NALLUR SHANTHARAM RETREAT | - | - | - | 30 | 0 | 30 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 10 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 16 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 100% |
Progress on shared amenities40
As on 10 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 100% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 100% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | No | Not applicable |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| S Raghavendra | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 3.76 cr | Rs 3.76 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Srimathi J Adiga |
| Engineer | Vishnu Kumar |
| Chartered Accountant | Narayana Rao M |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed68
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1258/404/PR/271123/006443 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA CA FORM 4 dec 2025 NSR.pdf | 10 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5, Q3,2025-26,Nallur Shantaram Retreat.pdf | 10 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Nallur Shantaram Retreat 31-12-2025.pdf | 10 Feb 2026 |
| Form-B AffidavitFile: 1 Form-B Affidavit.pdf | 27 Nov 2023 |
| Non Litigation affidavitFile: 2 Non Litigation affidavit.pdf | 27 Nov 2023 |
| JDA AffidavitFile: 3 JDA Affidavit.pdf | 27 Nov 2023 |
| Sec 3(1) AffidavitFile: 4 Sec 3(1) Affidavit.pdf | 27 Nov 2023 |
| Clarification on Single Layout Plot and OrderFile: 5 Clarification on Single Layout Plot and Order.pdf | 27 Nov 2023 |
| Clarification on Village MapFile: 6 Clarification on Village Map.pdf | 27 Nov 2023 |
| Building License or Commencement letterFile: 7 Building License or Commencement letter.pdf | 27 Nov 2023 |
| Registration CertificateFile: Registration Certificate.PDF | - |
| Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: Form-2 Architect Certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Form-3 Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Non-Litigation Affidavit.pdf | - |
| Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf | - |
| Balance Sheet 2021 - 2022File: Nainika Financials 2021-22.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Nainika Financials 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: Nainika Financials 2021-22.pdf | - |
| Building License | - |
| KEB NOC with Fee Receipt | - |
| Water NOC | - |
| Approved plan, Sanction letter,Building License, Area Statement, | - |
| Approved plan, Sanction letter,Building License, Area Statement, | - |
| Approved plan, Sanction letter,Building License, Area Statement, | - |
| Project Specification | - |
| Project Specification | - |
| Stability Certificate | - |
| JDA and GPA | - |
| Land Documents | - |
| Proforma Agreement of Sale Retreat | - |
| Proforma Allotment Letter Retreat | - |
| Brochure | - |
| Form-B Affidavit | - |
| Sec 3(1) Affidavit | - |
| JDA Affidavit | - |
| KEB NOC with Fee Receipt | - |
| Water NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| Fire NOC with Fee paid receipt | - |
| Unnamed document | - |
| KSPCB NOC with fee paid receipt | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Location demarcation | - |
| ESTIMATION COPY | - |
| Area statement | - |
| STP Demarcation | - |
| 15KLD STP DETAILS NALLUR PROJECT-Model | - |
| Archana IT Return 2021-22 | - |
| Mahesh IT Return 2021-22 | - |
| CDP Master Extract | - |
| Nallur SR Value | - |
| Occupancy CertificateFile: E Swathu 1st to 5th floor.pdf | - |
| Completion certificate issued by the competent authorityFile: E Swathu 1st to 5th floor.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Davangere
Computed across the 41 Davangere projects on ReraGenie, from their own filings.
Keep Nallur Shantharam Retreat on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Davangere41 in Davangere
Filed coordinates, straight-line distance. 7 registered projects within 2 km.
SHIVAGANGA ENCLAVE
SHIVAGANGA CONTRACTORS LLP
A M SHANVIKA
A M BUILDERS
SS SANKALP
SS BUILDERS AND PROMOTERS
Silversky Shamada
Silversky Homes LLP
AM VIRUPAKSHAPPA EXOTICA
AM Builders and Developers
PARK TERRACES
SHUBAM CONSTRUCTION
See every Davangere project, with the district possession charts
Builder: Nainika Infrastructure Pvt Ltd
Nainika Infrastructure Pvt Ltd has 1 registration on RERA Karnataka, including Nallur Shantharam Retreat. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Davangere district page.
Frequently asked questions
What are my rights if Nallur Shantharam Retreat is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Nallur Shantharam Retreat?
The registered promoter entity is Nainika Infrastructure Pvt Ltd, a company as per the filing. Its CIN U45201KA2021PTC153915 and GSTIN 29AAHCN9052H1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Nallur Shantharam Retreat?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Nallur Shantharam Retreat?
The professionals named in the filing: Architect: Srimathi J Adiga; Engineer: Vishnu Kumar; Chartered Accountant: Narayana Rao M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Nallur Shantharam Retreat?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback