Home / Browse projects / Belagavi, Karnataka / NAIK TOWER

Registration approved No litigation declared Commercial project

NAIK TOWER

By SHIVALAYA CONSTRUCTIONS

RG-KA-17055 · RERA PRM/KA/RERA/1249/447/PR/200526/008666 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2028Possession promisedno revision filed
4 of 15Construction stages donefurthest along: RCC or MS Framed structure, 90%
57 of 57Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 123 documents Report an error

NAIK TOWER is a Commercial project by SHIVALAYA CONSTRUCTIONS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/200526/008666 on 20 May 2026. Possession is promised by 30 Sep 2028. 0 of the 57 units on this registration are recorded sold or booked, and 4 of 15 construction stages are filed complete.

At a glance

Project

  • NameNAIK TOWER
  • TypeCommercial
  • Location
    • Belagavi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1249/447/PR/200526/008666
  • ReraGenie IDRG-KA-17055

Builder

  • NameSHIVALAYA CONSTRUCTIONS
  • Entity typePartnership Firm
  • GSTIN29ADPFS5239R1ZV
  • Authorized SignatoryMr. BALASAHEB APPU NAIK
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2026PromisedSep 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 May 2026
  • Promised completion30 Sep 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed123 files

Current status

0%0 of 57 units booked
7.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NAIK TOWER---05757

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 15 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 90%.

Building: 59% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)60%
RCC or MS Framed structure90%
Masonry Construction80%
Plastering inside , outside & Ceiling70%
Joinery: Doors, Windows, Ventilators etc30%
Basic work of Water supply, Sanitary and Electrification30%
Dadoing, Skirting, Flooring, Tiles work (All types)50%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing50%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work20%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes60%
Sewage and Drainage SystemYes60%
Water conservation/rain water harvesting/recharge of ground waterYes60%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes30%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes60%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes30%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes30%
Air ConditioningNoNot applicable
StaircasesYes75%
LiftsYes60%
Corridor/LobbiesYes60%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes85%
TerraceNoNot applicable
Outer WallYes85%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners4
LandownerVillageDistrict
SHIVALAYA CONSTRUCTIONS--
Mrs. SHYMALA BALASAHEB NAIK--
Mr. SANKET BALASAHEB NAIK--
BALASAHEB APPASAHEB NAIK--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.01 cr
Cost incurredRs 83.19 lakh
Spent of the estimate7.55%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 11.00 crRs 79.68 lakh
On-site expenditure-Consultants FeesRs 1.18 lakhRs 3.51 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. DYANESHWAR AMRUT SAYANEKAR
EngineerEr. KOUSTUBH J JADHAV
Chartered AccountantCA JAYANT D KALPAVRIKSHA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed123

As listed on the registration, under the names the promoter filed them with; the newest 80 of 123 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/200526/008666 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Sep-2026.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: F5 Architect (Q2) Sep-2026.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: F6 Engineer (Q2) Sep-2026.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Jun-2026.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: F5 Architect (Q1) Jun-2026.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: F6 Engineer (Q1) Jun-2026.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Balance sheet and P N L 2024-25 with CA UDIN with scheduleFile: INCOME TAX 1.pdf3 Dec 2025
lates Individual Partners IT ack, schedule, balance sheet and P N LFile: SCAN_20251111_092545066-8-23.pdf3 Dec 2025
notice replyFile: Notice Reply.pdf3 Dec 2025
profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedules and CA UDINFile: ITR 2022-23 FY.pdf8 Sep 2025
profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedules and CA UDINFile: B Sheet.pdf8 Sep 2025
profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedules and CA UDINFile: Computation Income.pdf8 Sep 2025
profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedules and CA UDINFile: ITR 2024-25.pdf8 Sep 2025
profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedules and CA UDINFile: P&L.pdf8 Sep 2025
profit and loss account and balance sheet for 2021-22, 2022-23 & 2023-24 with schedules and CA UDINFile: Declaration of Financial Statement.pdf8 Sep 2025
legal search reportFile: Advocate Search Report.pdf8 Sep 2025
rectify correct land owners in land details section.File: Undertaking Cum Rectification of Notice.pdf8 Sep 2025
ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR Survey Sketch.pdf8 Sep 2025
Area/ No of units of KSPCB noc is not matching with sanction planFile: Declaration of KSPCB NOC Units Naik Tower.pdf8 Sep 2025
Demarcation of proposed land in original Village map certified by the concern authorityFile: Majgaon Village Map.pdf8 Sep 2025
Approved layout planFile: Approved Layout Plan.pdf8 Sep 2025
UNDERTAKING LETTER OF QUERY REPLYFile: Undertaking Cum Rectification of Notice.pdf8 Sep 2025
balance sheet for 2021-22File: B Sheet.pdf24 Jul 2025
profit and loss account for 2021-22File: P&L.pdf24 Jul 2025
Computation Income for 2021-22,File: Computation Income.pdf24 Jul 2025
balance sheet for 2023-24File: B Sheet.pdf24 Jul 2025
profit and loss account for 2023-24File: P&L.pdf24 Jul 2025
Computation Income for 2023-24File: Computation Income.pdf24 Jul 2025
profit and loss account and balance sheet for 2023-24File: ITR 2023-24.pdf24 Jul 2025
final release orderFile: Release Order.pdf24 Jul 2025
Title deed of remaining landowners other then M/s Shivalaya constructionsFile: Title Deed.pdf24 Jul 2025
Title deed of remaining landowners other then M/s Shivalaya constructionsFile: Sale Deed.pdf24 Jul 2025
Title deed of remaining landowners other then M/s Shivalaya constructionsFile: CTS Uthara.pdf24 Jul 2025
ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR Survey Sketch.pdf24 Jul 2025
Area/ No of units of KSPCB noc is not matching with sanction planFile: Declaration of KSPCB NOC Units Naik Tower.pdf24 Jul 2025
Demarcation of proposed land in original Village map certified by the concern authorityFile: Majgaon Village Map.pdf24 Jul 2025
Approved layout planFile: Layout Plan.pdf24 Jul 2025
Upload proprietorship registration certificateFile: Firm Registration.pdf20 May 2025
profit and loss account and balance sheet for 2022-23 with schedules and CA UDINFile: ITR 2022-23.pdf20 May 2025
profit and loss account and balance sheet for 2022-23 with schedules and CA UDINFile: B Sheet.pdf20 May 2025
profit and loss account and balance sheet for 2022-23 with schedules and CA UDINFile: Computation Income.pdf20 May 2025
profit and loss account and balance sheet for 2022-23 with schedules and CA UDINFile: P&L.pdf20 May 2025
profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: ITR 2023-24.pdf20 May 2025
profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: B Sheet.pdf20 May 2025
profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: Computation Income.pdf20 May 2025
profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: P&L.pdf20 May 2025
profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: ITR 2024-25.pdf20 May 2025
defect free EC from 1-4-2010 to till dateFile: ECC-15042025-393499.pdf20 May 2025
Title deed of remaining landowners other then M/s Shivalaya constructionsFile: Title Deed.pdf20 May 2025
ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: Village Map ADLR.pdf20 May 2025
Architects certificate with valid COA numberFile: Architect's Licence Copy_compressed.pdf20 May 2025
Area/ No of units of KSPCB noc is not matching with sanction planFile: Declaration of KSPCB NOC Units Naik Tower.pdf20 May 2025
Demarcation of proposed land in original Village map certified by the concern authorityFile: Anagol Village Map.pdf20 May 2025
Approval/NOC under section 14 of the KTCP ActFile: NA Order Copy.pdf20 May 2025
Engineer certificate in the prescribed formatFile: F6 Engineer (Ongoing Project).pdf20 May 2025
amenities and common area details properly on the project detail page and upload the calculation sheFile: Certified Amenties & Common Area Details.pdf20 May 2025
latest dated self-attested copy of the renewed Engineer license certificateFile: Engineer Licence Copy (1).pdf20 May 2025
project name and project address and upload the STP/Septic Tank, Soak pit, and sewer line drawing ceFile: STP Demarcation Plan.pdf20 May 2025
Approval/NOC under section 14 of the KTCP ActFile: Release Order.pdf20 May 2025
proprietorship registration certificateFile: GST Certificate.pdf20 May 2025
Registration CertificateFile: Firm Registration.pdf-
GST CertificateFile: GST Certificate (1).pdf-
Partnership DeedFile: Partnership Deed Copy.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form-1 CA.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation.pdf-
Commencement Certificate-

How this compares with Belagavi

0%of this project is bookeddistrict median 39%
24%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep NAIK TOWER on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

Builder: SHIVALAYA CONSTRUCTIONS

SHIVALAYA CONSTRUCTIONS has 2 registrations on RERA Karnataka, including LAXMI PARK and NAIK TOWER. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if NAIK TOWER is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of NAIK TOWER?

The registered promoter entity is SHIVALAYA CONSTRUCTIONS, a partnership firm as per the filing. Its GSTIN 29ADPFS5239R1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in NAIK TOWER?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at NAIK TOWER?

The professionals named in the filing: Architect: Ar. DYANESHWAR AMRUT SAYANEKAR; Engineer: Er. KOUSTUBH J JADHAV; Chartered Accountant: CA JAYANT D KALPAVRIKSHA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAIK TOWER?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAIK TOWER. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAIK TOWER to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.