Home / Browse projects / Belagavi, Karnataka / MUKAMBIKA
MUKAMBIKA
RG-KA-39278 · RERA PRM/KA/RERA/1249/447/PR/200515/003400 · Last updated on RERA Karnataka portal: 5 Mar 2020
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
MUKAMBIKA is a Residential/Group Housing project by Sachin Zanvar in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/200515/003400 on 15 May 2020. Possession is promised by 30 Mar 2023. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameMUKAMBIKA
- TypeResidential/Group Housing
- Location
- Belagavi
- PincodeNot stated
- RERA no.PRM/KA/RERA/1249/447/PR/200515/003400
- ReraGenie IDRG-KA-39278
Builder
- NameSachin Zanvar
- Entity typePartnership Firm
- Authorized SignatorySACHIN ZANVAR
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 May 2020
- Promised completion30 Mar 2023
- Revised completionRevised to 30 Mar 2023 (originally 30 Jun 2022)
- Buildings1 building record
- Documents filed73 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MUKAMBIKA | - | - | - | 14 | 0 | 14 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 5 Mar 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
As on 5 Mar 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed73
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/200515/003400 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| BANK STATEMENTFile: BANK STATMENT 1.pdf | 5 Mar 2020 |
| VENDORS DETAILSFile: Vendor details.pdf | 5 Mar 2020 |
| NOCFile: NOC.pdf | 5 Mar 2020 |
| Affidivat Sec 3 (1)File: affidavit.pdf | 17 Feb 2020 |
| Firm certificateFile: firm certificate.pdf | 11 Feb 2020 |
| Bank statementFile: bank statment 2.pdf | 11 Feb 2020 |
| Account front page for passbookFile: bank statment 1.pdf | 11 Feb 2020 |
| payment detaailsFile: payment.pdf | 11 Feb 2020 |
| Project ground floor planFile: PRESSENTATION PLAN GF (22.10.2019).pdf | 11 Feb 2020 |
| Project typical floor plansFile: PRESSENTATION PLAN TF (22.10.2019).pdf | 11 Feb 2020 |
| regarding, balancee sheet and for Profit and Loss statment, its a new firmFile: Scan 25-Jan-2020 (2) (1).pdf | 11 Feb 2020 |
| ORDER COPY | - |
| APPROVED DRAWING | - |
| LAYOUT COPY | - |
| agreement of sale-MUKAMBIKA | - |
| agreement of sale-MUKAMBIKA | - |
| SALE DEED_compressed | - |
| APPROVED DRAWING | - |
| APPROVED DRAWING | - |
| agreement of sale-MUKAMBIKA | - |
| APPROVED DRAWING | - |
| PROJECT SPECIFICATIONS | - |
| EC MERGED | - |
| FORM B_compressed | - |
| CTS NO 900 | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| LAYOUT MAP | - |
| APPROVED DRAWING | - |
| NA COPY | - |
| Unnamed document | - |
| Balance Sheet 2018 - 2019File: Scan 25-Jan-2020.pdf | - |
| Balance Sheet 2017 - 2018File: Scan 25-Jan-2020.pdf | - |
| Balance Sheet 2016 - 2017File: Scan 25-Jan-2020.pdf | - |
| Audited Profit and Loss Statement 2018 - 2019File: Scan 25-Jan-2020 (2).pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: Scan 25-Jan-2020 (2).pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: Scan 25-Jan-2020 (2).pdf | - |
| Director's Report 2018 - 2019File: Scan 25-Jan-2020 (2).pdf | - |
| Director's Report 2017 - 2018File: Scan 25-Jan-2020 (2).pdf | - |
| Director's Report 2016 - 2017File: Scan 25-Jan-2020 (2).pdf | - |
| Cash Flow Statement 2018 - 2019File: Scan 25-Jan-2020 (2).pdf | - |
| Cash Flow Statement 2017 - 2018File: Scan 25-Jan-2020 (2).pdf | - |
| Auditor's Report 2018 - 2019File: Scan 25-Jan-2020 (2).pdf | - |
| Auditor's Report 2017 - 2018File: Scan 25-Jan-2020 (2).pdf | - |
| Auditor's Report 2016 - 2017File: Scan 25-Jan-2020 (2).pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: Scan 25-Jan-2020 (2).pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: Scan 25-Jan-2020 (2).pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: Scan 25-Jan-2020 (2).pdf | - |
| FORM B_compressed | - |
| Prospectus/BrochureFile: MUKAMBIKA (1).docx | - |
| Advertisement Copy 1File: MUKAMBIKA (1).docx | - |
| Tower Excel SheetFile: PRM_KA_RERA_1249_447_PR_200515_003400 (1).xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep MUKAMBIKA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Swarna Griha - 4 Phase 1
Felicity Adobe LLP
SkyCity Homes
M/s. Vishal Infra Built Ltd.
Shree Sant Babamaharaj Complex
Ratuja Developers
Pinnacle
Lotus Landmakrs (I) Pvt Ltd
JYOTICHANDRA
G P DEVELOPERS
SHIVNERI Apartment
SHIVNERI CONSTRUCTIONS
See every Belagavi project, with the district possession charts
Builder: Sachin Zanvar
Sachin Zanvar has 1 registration on RERA Karnataka, including MUKAMBIKA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if MUKAMBIKA is delayed beyond 30 Mar 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MUKAMBIKA?
The registered promoter entity is Sachin Zanvar, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MUKAMBIKA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
What should I check before booking in MUKAMBIKA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback