Home / Browse projects / Bengaluru Urban, Karnataka / Miraya Woods by UKN

Registration approved No litigation declared Residential/Group Housing project

Miraya Woods by UKN

By WATERLINE HOTELS PRIVATE LIMITED

RG-KA-58360 · RERA PRM/KA/RERA/1251/446/PR/180424/006797 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Oct 2029Possession promisedno revision filed
2 of 17Construction stages donefurthest along: Retaining wall (All types), 95%
46 of 72Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 94 documents Report an error

Miraya Woods by UKN is a Residential/Group Housing project by WATERLINE HOTELS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180424/006797 on 18 Apr 2024. Possession is promised by 31 Oct 2029. 26 of the 72 units on this registration are recorded sold or booked, and 2 of 17 construction stages are filed complete.

At a glance

Project

  • NameMiraya Woods by UKN
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560066
  • Pincode560066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/180424/006797
  • ReraGenie IDRG-KA-58360

Builder

  • NameWATERLINE HOTELS PRIVATE LIMITED
  • Entity typeCompany
  • CINU55101KA2008PTC045815
  • GSTIN29AAACW8059N1ZI
  • Authorized SignatorySUDHIR KUMAR MISHRA
  • Chief Executive OfficerKUSH DORAB MEDHORA
  • DirectorsGAUTAM U NAMBISAN, KUSH DORAB MEDHORA
  • Project HeadRajesh Kanna

Key dates

this monthRegisteredApr 2024PromisedOct 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Apr 2024
  • Promised completion31 Oct 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed94 files

Current status

36%26 of 72 units booked
43.9%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-----72

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 17 construction stages are filed complete. The stage furthest along is Retaining wall (All types), at 95%.

Building: 35% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level50%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)50%
Retaining wall (All types)95%
RCC or MS Framed structure95%
Masonry Construction85%
Plastering inside , outside & Ceiling25%
Joinery: Doors, Windows, Ventilators etc1%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)1%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting1%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesYes0%

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,017 sq m
Named landowners4
LandownerVillageDistrict
WATERLINE HOTELS PVT LTD--
GAUTAM U NAMBISAN--
VEERABHADRAPPA SANGAPPA & COMPANY--
Nanda Kumar Rao--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 62.92 cr
Cost incurredRs 27.59 cr
Spent of the estimate43.85%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 44.00 crRs 21.68 cr
On-site expenditure-Site OverheadRs 10.46 crRs 5.10 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 8.02 crRs 81.36 lakh
Payment of cessRs 44.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIJAY AND ANJALI YAGNIK ARCHITECTS
EngineerBase Engineering Services Mr. Suhas M
Chartered AccountantChitragudaiah U

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed94

As listed on the registration, under the names the promoter filed them with; the newest 80 of 94 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180424/006797 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate RERA form 4 Miraya q2 27.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Miraya Woods - RERA Certificate (October 10, 2026).pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Eng certificate Rera-mirayawoods.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate Woods Q1 RERA.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Miraya Woods - RERA architect Certificate (July 10, 2026).pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Miraya woods Rera eng Certificate july 2026.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Miraya Woods_Format_Form -4, Chartered Accountant (QU).pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect_Miraya Woods_Q4-2025-26.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Miraya Woods_Engineer Certificate_Q-4-25-26.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Miraya Woods_Format_Form -4, Chartered Accountant Q3 25-26.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 05 RERA - Architect_Miraya Woods_Q3-2025-26.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Miraya Woods_Engineer Certificate_Q-III-25-26.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)12 Jan 2026
Clarification and Affidavit for KSPCB NOCFile: KSPCB_Affidavit.pdf17 Apr 2024
RTC, survey SURVEY NO.67 (P)-
Mutation, survey SURVEY NO.67 (P)-
Encumbrance Certificate, survey SURVEY NO.67 (P)-
Conversion/Alienation Order, survey SURVEY NO.67 (P)-
Sale/Title/Gift Deed, survey SURVEY NO.67 (P)-
Khatha, survey SURVEY NO.67 (P)-
Registration CertificateFile: 1 Annexure Certificate of Incorporation WHPL.PDF-
Organization StructureFile: 11 Annexure Company Organization Structure RERA- updated.pdf-
Certificate issued by CA Form 1File: 56 57 Annexure Form1 CA Certificate - Miraya Woods revised.pdf-
Certificate issued by Architect Form 2File: 59 Rev RERA Certificate - Miraya Woods.pdf-
Certificate issued by Engineer Form 3File: 58 ENG CERTIFICATE MIRAYA WOODS.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: 45 Annexure AFFIDAVIT-NON LITIGATION.pdf-
Certificate from Chartered AccountFile: 56 57 Annexure Form1 CA Certificate - Miraya Woods revised.pdf-
Balance Sheet 2022 - 2023File: 60 Annexure WHPL BS 22-23.pdf-
Balance Sheet 2021 - 2022File: 60 Annexure WHPL BS 2021-22.pdf-
Balance Sheet 2020 - 2021File: 60 Annexure Waterline Hotels Private Limited BS 20-21.pdf-
Audited Profit and Loss Statement 2022 - 2023File: 61 Annexure WHPL P&L 22-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: 61 Annexure WHPL P&L 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: 61 Annexure Waterline Hotels Private Limited P&L 20-21.pdf-
Director's Report 2022 - 2023File: 62 Annexure Directors report - Waterline Hotels.pdf-
Director's Report 2021 - 2022File: 62 annexure Directors Report- Waterline Hotels pvt ltd.pdf-
Director's Report 2020 - 2021File: 62 Annexure Directors Report_WHPL.pdf-
Cash Flow Statement 2022 - 2023File: 63 Annexure WHPL cash flow 22-23.pdf-
Cash Flow Statement 2021 - 2022File: 63 Annexure WHPL Cash Flow 2021-22.pdf-
Auditor's Report 2022 - 2023File: 64 Annexure WHPL Audit Report 22-23.pdf-
Auditor's Report 2021 - 2022File: 64 Annexure WHPL Auditors Report 2021-22.pdf-
Auditor's Report 2020 - 2021File: 64 Annexure Audit Report - WHPL 20-21.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: 65 Annexure ACK459860991281023 AY 2023-24.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: 65 Annexure ACK_AAACW8059N AY 2022-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: 65 Annexure ACK_AAACW8059N_AY 2021-22.pdf-
67 Annexure Commencement Letter dated 13 04 2023 (BDA)-
Blank-
69 94 BWSSB NOC dated 06 09 2023-
70 to 74 76 77 Annexure Approved plan 22 01 2024-
70 to 74 76 77 Annexure Approved plan 22 01 2024-
70 to 74 76 77 Annexure Approved plan 22 01 2024-
70 to 74 76 77 Annexure Approved plan 22 01 2024-
70 to 74 76 77 Annexure Approved plan 22 01 2024-
Annexure 75 Miraya Wood Specifications-
70 to 74 76 77 Annexure Approved plan 22 01 2024-
70 to 74 76 77 Annexure Approved plan 22 01 2024-
78 Annexure structural certificate-
81 Annexure JV Agreement-
82 Annexure Demand letter - Change of Land usage-
84 Annexure Conversion Order dated 03 10 2016(30 guntas) 17 05 2017 (10 guntas)-
85 Annexure Miraya Woods - Title opinion-
Miraya_AOS-
Miraya_AllottmentLetter_Draft-
Blank-
90 Annexure RERA -FORM B-
91 Annexure Notarized Affidavit for 3(1) Voliation-
92 Annexure JD Affidavit Cum Declaration-
Clarification_BESCOM_CC_SINGLEPLOT-
69 94 BWSSB NOC dated 06 09 2023-
Blank-
Blank-

How this compares with Bengaluru Urban

36%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Miraya Woods by UKN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMiraya Woods by UKNOther 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: WATERLINE HOTELS PRIVATE LIMITED

WATERLINE HOTELS PRIVATE LIMITED has 1 registration on RERA Karnataka, including Miraya Woods by UKN. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Miraya Woods by UKN is delayed beyond 31 Oct 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Miraya Woods by UKN?

The registered promoter entity is WATERLINE HOTELS PRIVATE LIMITED, a company as per the filing. Its CIN U55101KA2008PTC045815 and GSTIN 29AAACW8059N1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Miraya Woods by UKN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Miraya Woods by UKN?

The professionals named in the filing: Architect: VIJAY AND ANJALI YAGNIK ARCHITECTS; Engineer: Base Engineering Services Mr. Suhas M; Chartered Accountant: Chitragudaiah U. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Miraya Woods by UKN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Miraya Woods by UKN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Miraya Woods by UKN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.