Home / Browse projects / Bengaluru Urban, Karnataka / MIDORI
MIDORI
RG-KA-23671 · RERA PRM/KA/RERA/1251/308/PR/160525/007753 · Last updated on RERA Karnataka portal: 12 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
MIDORI is a Residential/Group Housing project by TATTVAM VENTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/160525/007753 on 16 May 2025. Possession is promised by 30 Nov 2028. 20 of the 117 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.
At a glance
Project
- NameMIDORI
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 562125
- Pincode562125
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/160525/007753
- ReraGenie IDRG-KA-23671
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on16 May 2025
- Promised completion30 Nov 2028
- Revised completionNone
- Buildings11 building records
- Documents filed283 files
Current status
Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BLOCK-A | - | - | - | 4 | 0 | 4 |
| BLOCK-B | - | - | - | 8 | 0 | 8 |
| BLOCK-C | - | - | - | 12 | 0 | 12 |
| BLOCK-D | - | - | - | 12 | 0 | 12 |
| BLOCK-E | - | - | - | 4 | 0 | 4 |
| BLOCK-F | - | - | - | 16 | 0 | 16 |
| BLOCK-G | - | - | - | 12 | 0 | 12 |
| BLOCK-H | - | - | - | 16 | 0 | 16 |
| BLOCK-I | - | - | - | 16 | 0 | 16 |
| BLOCK-J | - | - | - | 16 | 0 | 16 |
| BLOCK-K | - | - | - | 1 | 0 | 1 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 99%.
Building: 24% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 99% |
| Foundation footing work | 70% |
| Upto Plinth Level | 70% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 35% |
| Retaining wall (All types) | 80% |
| Podium Slab | 35% |
| RCC or MS Framed structure | 25% |
| Masonry Construction | 10% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership24
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| TATTVAM VENTURES | - | - |
| TATTVAM VENTURES | - | - |
| PSA Shankar | - | - |
| PS Anand Ram | - | - |
| Royale Developers | - | - |
| Satish PremKumar | - | - |
| PSA Shankar | - | - |
| Satish PremKumar | - | - |
| Satish PremKumar | - | - |
| TATTVAM VENTURES1 | - | - |
| TATTVAM VENTURES | - | - |
| Royale Developers | - | - |
| TATTVAM VENTURES | - | - |
| Royale Developers | - | - |
| TATTVAM VENTURES | - | - |
| Royale Properties | - | - |
| Royale Properties | - | - |
| TATTVAM VENTURES | - | - |
| Satish PremKumar | - | - |
| Puttappa and Legal Heirs | - | - |
| T Y Mahesh Kumar | - | - |
| Sunil Satyanarayana | - | - |
| Sunil Satyanarayana | - | - |
| TATTVAM VENTURES | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 85.00 cr | Rs 21.10 cr |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 10.00 cr | Rs 2.10 cr |
| On-site expenditure-Consultants Fees | Rs 5.00 cr | - |
| On-site expenditure-Salaries of workers | Rs 3.75 cr | Rs 40.95 lakh |
| Payment of taxes | Rs 1.00 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | JNANAPRAKASH |
| Engineer | K R Mohan |
| Chartered Accountant | Thilakraj SP |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed283
As listed on the registration, under the names the promoter filed them with; the newest 80 of 283 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/160525/007753 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate- Form 4 New.pdf | 12 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Arictect Certificate.pdf | 12 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf | 12 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 12 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 12 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 12 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 12 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: TATTVAM VENTURES Form -4.pdf | 8 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect-Q1-2026-27.pdf | 8 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate-Q1-2026-27.pdf | 8 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 8 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 8 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 8 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 8 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Certificate Q4(2025-26).pdf | 20 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Certificate Q4(2025-26).pdf | 20 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6-Certificate Q4(2025-26).pdf | 20 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 20 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 20 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 20 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 20 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4-Certificate.pdf | 13 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-6-Certificate.pdf | 13 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-5-Certificate.pdf | 13 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 13 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 13 Jan 2026 |
| Sy No 6-4 Sale Deed to TVFile: Sy No 6-4 Sale Deed to TV.pdf | 15 May 2025 |
| Sy No 6-4 Sale Deed 2 Guntas To TVFile: Sy No 6-4 Sale Deed 2 Guntas To TV.pdf | 15 May 2025 |
| Sy No 6-4 RD - GPA to TVFile: Sy No 6-4 RD - GPA to TV.pdf | 15 May 2025 |
| Sy No 6-4 RD - JDA to TVFile: Sy No 6-4 RD - JDA to TV.pdf | 15 May 2025 |
| EC 3/5File: 3-5 ec.pdf | 8 May 2025 |
| EC 4/1File: 4-1 ec.pdf | 8 May 2025 |
| EC 4/2File: 4-2 ec.pdf | 8 May 2025 |
| EC 5/2File: 5-2 ec.pdf | 8 May 2025 |
| EC 5/3File: 5-3 ec.pdf | 8 May 2025 |
| EC 5/4File: 5-4 ec.pdf | 8 May 2025 |
| EC 5/5File: 5-5 ec.pdf | 8 May 2025 |
| EC 5/6File: 5-6 ec.pdf | 8 May 2025 |
| EC 6/1File: 6-1 ec.pdf | 8 May 2025 |
| EC 6/3File: 6-3 ec.pdf | 8 May 2025 |
| EC 6/5File: 6-5 ec.pdf | 8 May 2025 |
| EC 6/6File: 6-6 ec.pdf | 8 May 2025 |
| EC 6/7File: 6-7 ec.pdf | 8 May 2025 |
| EC 8/1File: 8-1 ec.pdf | 8 May 2025 |
| EC 8/2File: 8-2 ec.pdf | 8 May 2025 |
| EC 8/3File: 8-3 ec.pdf | 8 May 2025 |
| EC 7File: sy no 7 ec.pdf | 8 May 2025 |
| EC 3/6File: 3-6 EC_merged.pdf | 8 May 2025 |
| EC 6/2File: 6-2 ec.pdf | 8 May 2025 |
| EC 6/4File: 6-4 ec.pdf | 8 May 2025 |
| EC 9/4File: 9-4 ec.pdf | 8 May 2025 |
| Project specificationFile: Midori Project Specifications.pdf | 8 May 2025 |
| Allotment letterFile: Allotment Letter Proforma.pdf | 8 May 2025 |
| Agreement for SaleFile: Agreement for Sale Proforma.pdf | 8 May 2025 |
| STP designFile: STP Design.pdf | 8 May 2025 |
| Land cost calculationFile: Midori Land cost details self attested.pdf | 8 May 2025 |
| Borewell 1File: Borewell 1.jpg | 8 May 2025 |
| Borewell 2File: Borewell 2.jpg | 8 May 2025 |
| Water Panchayath NOCFile: Midori Panchayath Water NOC.pdf | 8 May 2025 |
| Structural safety adopted for the proposed buildingFile: certificate of structural safety.pdf | 8 May 2025 |
| Advocate ReportFile: Advocate Search Report.pdf | 8 May 2025 |
| Title Deed 4/1File: 4-1 PSA Sale Deed doc 1189-12-13.pdf | 8 May 2025 |
| Title Deed 4/2File: 4-2 anand sd 600-12-13.pdf | 8 May 2025 |
| Title Deed 5/2File: 5_2 Sale Deed.pdf | 8 May 2025 |
| Title Deed 5/3File: 5_3 sd d0c 5620-11-12.pdf | 8 May 2025 |
| Title Deed 5/4File: 5-4 psa sd 2572-12-13.pdf | 8 May 2025 |
| Title Deed 5/5 and 5/6File: 5_5 5_6 Satish sale deed.pdf | 8 May 2025 |
| Title Deed 6/3File: 6-3 Sale Deed.pdf | 8 May 2025 |
| Title Deed 6/6File: 6-6 to RP.pdf | 8 May 2025 |
| Title Deed 6/7File: 6-7 Title to RP.pdf | 8 May 2025 |
| Title Deed 6/9File: 6-9 Satish sale deed 6-9.pdf | 8 May 2025 |
| Title Deed 7File: 7 sd 2337-07-08.pdf | 8 May 2025 |
| Title Deed 8/1File: 8_1 masesh sale deed.pdf | 8 May 2025 |
| Title Deed 8/2File: 8_2 Sunil sale deed.pdf | 8 May 2025 |
| Title Deed 8/3File: 8_3 sunil sale deed no 2.pdf | 8 May 2025 |
| TATTVAM VENTURES Title Deed 6/2 4 GuntasFile: 6-2 4G Sale Deed.pdf | 8 May 2025 |
| TATTVAM VENTURES Title Deed 6/2 1 GuntasFile: 6-2 1G Sale Deed.pdf | 8 May 2025 |
| Form B Affidavit UpdatedFile: Form B UPDATED.pdf | 8 May 2025 |
| Common Area and Amenities CertifiedFile: Amenities and Common Area.pdf | 8 May 2025 |
| Sy No 6-4 Sale Deed to TVFile: Sy No 6-4 Sale Deed to TV.pdf | 8 May 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| WOODSVALE | Sy No. 9/1,2,3,4, 10/1,2,3,4, 11,15/1,2,3, 16/1A1B,16/2,17/1,17/2, 18,19/1,2,20/2,3,4,21/1,2,3,5,22/1,24/1, 4,6,9,25/1,2,3,4,26/1,2,27/1A,1B,1C,, 31/1,2,34/1,2,3,5,6,35/2,53/1A,1B,1C,4,5 , Ittanguru Village, Sarjapur Hobli | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep MIDORI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 28 registered projects within 2 km.
Nambiar District 25 Phase 3
Nambiar EnsembleResidential Projects LLP
Meridian Park Phase II @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase I @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase III @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Nambiar District 25 Phase 2
Nambiar EnsembleResidential Projects LLP
SEVEN SARJAPUR
FORTUNE PRIMERO LLP
See every Bengaluru Urban project, with the district possession charts
Builder: TATTVAM VENTURES
TATTVAM VENTURES has 2 registrations on RERA Karnataka, including MIDORI and WOODSVALE. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if MIDORI is delayed beyond 30 Nov 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MIDORI?
The registered promoter entity is TATTVAM VENTURES, a partnership firm as per the filing. Its GSTIN 29AAQFT1885Q1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MIDORI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at MIDORI?
The professionals named in the filing: Architect: JNANAPRAKASH; Engineer: K R Mohan; Chartered Accountant: Thilakraj SP. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MIDORI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.