ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / MIDORI

Registration approved No litigation declared Residential/Group Housing project

MIDORI

By TATTVAM VENTURES

RG-KA-23671 · RERA PRM/KA/RERA/1251/308/PR/160525/007753 · Last updated on RERA Karnataka portal: 12 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2028Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 99%
97 of 117Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 283 documents Report an error

MIDORI is a Residential/Group Housing project by TATTVAM VENTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/160525/007753 on 16 May 2025. Possession is promised by 30 Nov 2028. 20 of the 117 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameMIDORI
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/160525/007753
  • ReraGenie IDRG-KA-23671

Builder

  • NameTATTVAM VENTURES
  • Entity typePartnership Firm
  • GSTIN29AAQFT1885Q1ZX
  • Authorized SignatoryY A HARI KISHORE
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2025PromisedNov 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 May 2025
  • Promised completion30 Nov 2028
  • Revised completionNone
  • Buildings11 building records
  • Documents filed283 files

Current status

17%20 of 117 units booked
22.5%Of the estimated cost spent so far

Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK-A---404
BLOCK-B---808
BLOCK-C---12012
BLOCK-D---12012
BLOCK-E---404
BLOCK-F---16016
BLOCK-G---12012
BLOCK-H---16016
BLOCK-I---16016
BLOCK-J---16016
BLOCK-K---101

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 99%.

Building: 24% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work99%
Foundation footing work70%
Upto Plinth Level70%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)35%
Retaining wall (All types)80%
Podium Slab35%
RCC or MS Framed structure25%
Masonry Construction10%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership24

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area21,979 sq m
Named landowners24
LandownerVillageDistrict
TATTVAM VENTURES--
TATTVAM VENTURES--
PSA Shankar--
PS Anand Ram--
Royale Developers--
Satish PremKumar--
PSA Shankar--
Satish PremKumar--
Satish PremKumar--
TATTVAM VENTURES1--
TATTVAM VENTURES--
Royale Developers--
TATTVAM VENTURES--
Royale Developers--
TATTVAM VENTURES--
Royale Properties--
Royale Properties--
TATTVAM VENTURES--
Satish PremKumar--
Puttappa and Legal Heirs--
T Y Mahesh Kumar--
Sunil Satyanarayana--
Sunil Satyanarayana--
TATTVAM VENTURES--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 104.75 cr
Cost incurredRs 23.61 cr
Spent of the estimate22.54%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 85.00 crRs 21.10 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 10.00 crRs 2.10 cr
On-site expenditure-Consultants FeesRs 5.00 cr-
On-site expenditure-Salaries of workersRs 3.75 crRs 40.95 lakh
Payment of taxesRs 1.00 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJNANAPRAKASH
EngineerK R Mohan
Chartered AccountantThilakraj SP

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed283

As listed on the registration, under the names the promoter filed them with; the newest 80 of 283 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/160525/007753 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate- Form 4 New.pdf12 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Arictect Certificate.pdf12 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf12 Oct 2026
Q2 2026-27 Water supply and sewage board12 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)12 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)12 Oct 2026
Q2 2026-27 KPTCL- BESCOM12 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: TATTVAM VENTURES Form -4.pdf8 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect-Q1-2026-27.pdf8 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate-Q1-2026-27.pdf8 Jul 2026
Q1 2026-27 Water supply and sewage board8 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)8 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)8 Jul 2026
Q1 2026-27 KPTCL- BESCOM8 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Certificate Q4(2025-26).pdf20 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Certificate Q4(2025-26).pdf20 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6-Certificate Q4(2025-26).pdf20 Apr 2026
Q4 2025-26 Water supply and sewage board20 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)20 Apr 2026
Q4 2025-26 KPTCL- BESCOM20 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4-Certificate.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-6-Certificate.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-5-Certificate.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Jan 2026
Sy No 6-4 Sale Deed to TVFile: Sy No 6-4 Sale Deed to TV.pdf15 May 2025
Sy No 6-4 Sale Deed 2 Guntas To TVFile: Sy No 6-4 Sale Deed 2 Guntas To TV.pdf15 May 2025
Sy No 6-4 RD - GPA to TVFile: Sy No 6-4 RD - GPA to TV.pdf15 May 2025
Sy No 6-4 RD - JDA to TVFile: Sy No 6-4 RD - JDA to TV.pdf15 May 2025
EC 3/5File: 3-5 ec.pdf8 May 2025
EC 4/1File: 4-1 ec.pdf8 May 2025
EC 4/2File: 4-2 ec.pdf8 May 2025
EC 5/2File: 5-2 ec.pdf8 May 2025
EC 5/3File: 5-3 ec.pdf8 May 2025
EC 5/4File: 5-4 ec.pdf8 May 2025
EC 5/5File: 5-5 ec.pdf8 May 2025
EC 5/6File: 5-6 ec.pdf8 May 2025
EC 6/1File: 6-1 ec.pdf8 May 2025
EC 6/3File: 6-3 ec.pdf8 May 2025
EC 6/5File: 6-5 ec.pdf8 May 2025
EC 6/6File: 6-6 ec.pdf8 May 2025
EC 6/7File: 6-7 ec.pdf8 May 2025
EC 8/1File: 8-1 ec.pdf8 May 2025
EC 8/2File: 8-2 ec.pdf8 May 2025
EC 8/3File: 8-3 ec.pdf8 May 2025
EC 7File: sy no 7 ec.pdf8 May 2025
EC 3/6File: 3-6 EC_merged.pdf8 May 2025
EC 6/2File: 6-2 ec.pdf8 May 2025
EC 6/4File: 6-4 ec.pdf8 May 2025
EC 9/4File: 9-4 ec.pdf8 May 2025
Project specificationFile: Midori Project Specifications.pdf8 May 2025
Allotment letterFile: Allotment Letter Proforma.pdf8 May 2025
Agreement for SaleFile: Agreement for Sale Proforma.pdf8 May 2025
STP designFile: STP Design.pdf8 May 2025
Land cost calculationFile: Midori Land cost details self attested.pdf8 May 2025
Borewell 1File: Borewell 1.jpg8 May 2025
Borewell 2File: Borewell 2.jpg8 May 2025
Water Panchayath NOCFile: Midori Panchayath Water NOC.pdf8 May 2025
Structural safety adopted for the proposed buildingFile: certificate of structural safety.pdf8 May 2025
Advocate ReportFile: Advocate Search Report.pdf8 May 2025
Title Deed 4/1File: 4-1 PSA Sale Deed doc 1189-12-13.pdf8 May 2025
Title Deed 4/2File: 4-2 anand sd 600-12-13.pdf8 May 2025
Title Deed 5/2File: 5_2 Sale Deed.pdf8 May 2025
Title Deed 5/3File: 5_3 sd d0c 5620-11-12.pdf8 May 2025
Title Deed 5/4File: 5-4 psa sd 2572-12-13.pdf8 May 2025
Title Deed 5/5 and 5/6File: 5_5 5_6 Satish sale deed.pdf8 May 2025
Title Deed 6/3File: 6-3 Sale Deed.pdf8 May 2025
Title Deed 6/6File: 6-6 to RP.pdf8 May 2025
Title Deed 6/7File: 6-7 Title to RP.pdf8 May 2025
Title Deed 6/9File: 6-9 Satish sale deed 6-9.pdf8 May 2025
Title Deed 7File: 7 sd 2337-07-08.pdf8 May 2025
Title Deed 8/1File: 8_1 masesh sale deed.pdf8 May 2025
Title Deed 8/2File: 8_2 Sunil sale deed.pdf8 May 2025
Title Deed 8/3File: 8_3 sunil sale deed no 2.pdf8 May 2025
TATTVAM VENTURES Title Deed 6/2 4 GuntasFile: 6-2 4G Sale Deed.pdf8 May 2025
TATTVAM VENTURES Title Deed 6/2 1 GuntasFile: 6-2 1G Sale Deed.pdf8 May 2025
Form B Affidavit UpdatedFile: Form B UPDATED.pdf8 May 2025
Common Area and Amenities CertifiedFile: Amenities and Common Area.pdf8 May 2025
Sy No 6-4 Sale Deed to TVFile: Sy No 6-4 Sale Deed to TV.pdf8 May 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
WOODSVALESy No. 9/1,2,3,4, 10/1,2,3,4, 11,15/1,2,3, 16/1A1B,16/2,17/1,17/2, 18,19/1,2,20/2,3,4,21/1,2,3,5,22/1,24/1, 4,6,9,25/1,2,3,4,26/1,2,27/1A,1B,1C,, 31/1,2,34/1,2,3,5,6,35/2,53/1A,1B,1C,4,5 , Ittanguru Village, Sarjapur HobliCompleted-No date filed

How this compares with Bengaluru Urban

17%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MIDORI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMIDORIOther 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 28 registered projects within 2 km.

Builder: TATTVAM VENTURES

TATTVAM VENTURES has 2 registrations on RERA Karnataka, including MIDORI and WOODSVALE. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MIDORI is delayed beyond 30 Nov 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MIDORI?

The registered promoter entity is TATTVAM VENTURES, a partnership firm as per the filing. Its GSTIN 29AAQFT1885Q1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MIDORI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MIDORI?

The professionals named in the filing: Architect: JNANAPRAKASH; Engineer: K R Mohan; Chartered Accountant: Thilakraj SP. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MIDORI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MIDORI. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MIDORI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.