ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / MATHAPATHI GRAND FIELD

Registration approved No litigation declared Residential/Group Housing project

MATHAPATHI GRAND FIELD

By MATHAPATHI CONSTRUCTIONS PRIVATE LIMITED

RG-KA-38751 · RERA PRM/KA/RERA/1251/446/PR/191022/005340 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2026Possession promisedmoved 12 months from the original
7 of 15Construction stages donefurthest along: Joinery: Doors, 99%
66 of 126Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 130 documents Report an error

MATHAPATHI GRAND FIELD is a Residential/Group Housing project by MATHAPATHI CONSTRUCTIONS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/191022/005340 on 19 Oct 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 60 of the 126 units on this registration are recorded sold or booked, and 7 of 15 construction stages are filed complete.

At a glance

Project

  • NameMATHAPATHI GRAND FIELD
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/191022/005340
  • ReraGenie IDRG-KA-38751

Builder

  • NameMATHAPATHI CONSTRUCTIONS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45209KA2020PTC138189
  • GSTIN29AANCM7677B1ZY
  • Authorized SignatoryCHETAN MATHAPATHI
  • MdCHETAN MATHAPATHI
  • DirectorsCHETAN MATHAPATHI, Girijadevi Mathapathi, Dr. M.B Mathapathi, Sachin Mathapathi
  • Project HeadCHETAN MATHAPATHI

Key dates

this monthRegisteredOct 2022First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Oct 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed130 files

Current status

48%60 of 126 units booked
1.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MATHAPATHI GRAND FIELD---1260126

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 15 construction stages are filed complete. The stage furthest along is Joinery: Doors, at 99%.

Building: 96% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc99%
Basic work of Water supply, Sanitary and Electrification79%
Dadoing, Skirting, Flooring, Tiles work (All types)99%
Railing and Grill fixing79%
Electrification, Water supply and Sanitary Finishing99%
Painting99%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)90%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work96%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities33

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes60%
Sewage and Drainage SystemYes70%
Water conservation/rain water harvesting/recharge of ground waterYes70%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes19%
Emergency Evacuation servicesYes5%
Internal Roads & FootpathsYes80%
Electricity supply transformer and substationYes30%
Storm water drainsYes100%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes70%
Parks & Tree plantingYes0%
Street LightingYes30%
ElectricityYes86%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes86%
Club HouseYes86%
Community HallYes86%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes86%
Swimming PoolYes86%
GymYes86%
ParksYes86%
Power BackupYes86%
Piped GasNoNot applicable
Water and SanitationYes86%
Air ConditioningNoNot applicable
StaircasesYes95%
LiftsYes95%
Corridor/LobbiesYes90%
Fire escapesYes20%
Common entrance and exit for the building/common portico/foyer/verandahYes97%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,967 sq m
Named landowners1
LandownerVillageDistrict
MATHAPATHI CONSTRUCTIONS PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 64.15 cr
Cost incurredRs 1.00 cr
Spent of the estimate1.56%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 54.15 crRs 1.00 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 4.00 cr-
Administrative costRs 3.00 cr-
On-site expenditure-Consultants FeesRs 1.50 cr-
Payment of taxesRs 1.50 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectK.B.MAHALINGA SWAMY
EngineerK.B.MAHALINGA SWAMY
Chartered AccountantK.S.REDDY AND CO

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/260120/005340Dec 2025 → Dec 2026

Reason as filed by the promoterCustomers want modification in interiors

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed130

As listed on the registration, under the names the promoter filed them with; the newest 80 of 130 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/191022/005340 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate_compressed2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form_4 CA Certificate.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form_5 Architect Certificate.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form_6 Engineer Certificate.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate Form_4_compressed.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate Form_5.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate Form_6.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 RERA CERTIFICATE Q3.pdf28 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form_5 Architects Certificate Q3.pdf28 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineers Certificate Q3.pdf28 Jan 2026
Q3 2025-26 Water supply and sewage board28 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)28 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)28 Jan 2026
Q3 2025-26 KPTCL- BESCOM28 Jan 2026
ECFile: EC.pdf13 Jan 2026
EX 1 Architect Certificate For Status Of Work As On DateFile: EX 1 Architect Certificate For Status Of Work As On Date.pdf13 Jan 2026
EX 2 Architect Certificate For Pending Work As On DateFile: EX 2 Architect Certificate For Pending Work As On Date.pdf13 Jan 2026
EX 3 CA Certificate Fund UtilizedFile: EX 3 CA Certificate Fund Utilized.pdf13 Jan 2026
Ext 4 CA Certificate Fund RequiredFile: Ext 4 CA Certificate Fund Required.pdf13 Jan 2026
Ext 5 Engineer Status of the WorkFile: Ext 5 Engineer Status of the Work.pdf13 Jan 2026
Ext 6 Engineer Pending WorkFile: Ext 6 Engineer Pending Work.pdf13 Jan 2026
Ex_7 AffidavitFile: Ex_7 Affidavit.pdf13 Jan 2026
Reason for ExtensionFile: Reason for Extension.pdf13 Jan 2026
Sold and Unsold detailsFile: Sold and Unsold details.pdf13 Jan 2026
NOCs DeclarationFile: NOCs Declaration.pdf13 Jan 2026
Notified Sale Agreement - AOSFile: SALE AGREEMENT RERA FINAL.pdf13 Oct 2022
BWSSB NOCFile: BWSSB NOC.pdf1 Oct 2022
SALE AGREEMENT HIGHLIGHTEDFile: SALE AGREEMENT RERA FINAL.pdf1 Oct 2022
BESCOM NOCFile: BESCOM NOC.pdf1 Oct 2022
CASH FLOW STATEMENTFile: cashflow statement for the year - 2020-21.pdf12 Sep 2022
DIRECTORS REPORTFile: Directors - Board of Directors Report.pdf12 Sep 2022
Balance SheetFile: Balance Sheet.pdf19 Aug 2022
P and LFile: P and L.pdf19 Aug 2022
Auditors ReportFile: Auditors Report.pdf19 Aug 2022
ITRFile: ITR.pdf19 Aug 2022
Katha in the name of Seller Recom PropertiesFile: Katha-RecomProperties.pdf19 Aug 2022
Khatha in the name of MATHAPATHI CONSTRUCTIONS PRIVATE LIMITEDFile: KHATHA - Mathapathi Constructions.pdf19 Aug 2022
Advocate Search ReportFile: Advocate Search Report.pdf19 Aug 2022
RTC 76/3File: Latest RTC 76-3.pdf26 Jul 2022
MutationFile: Mutation - KHATHA.pdf26 Jul 2022
SR Value Certified CopyFile: SR Valuation Certified Copy.pdf26 Jul 2022
Form BFile: Form B.pdf26 Jul 2022
Non Litigation AffidavitFile: Non Litigation Affidavit.pdf26 Jul 2022
BESCOM NOC Fees ReceiptFile: BESCOM FEES PAID RECEIPT.pdf26 Jul 2022
BWSSB NOC Fees ReceiptFile: BWSSB FEES PAID RECEIPT.pdf26 Jul 2022
ENGINEER CERTIFICATEFile: Form 3 - Engineer Certifcate.pdf26 Jul 2022
COMMENCEMENT CERTIFICATEFile: Commencement Certificate.pdf26 Jul 2022
SALE AGREEMENT PROFORMAFile: SALE AGREEMENT RERA FINAL.pdf26 Jul 2022
AFFIDAVITFile: Affidavit.pdf26 Jul 2022
SPECIFICATIONSFile: Specifications.pdf26 Jul 2022
RTC, survey 76/3-
Mutation, survey 76/3-
Encumbrance Certificate, survey 76/3-
Conversion/Alienation Order, survey 76/3-
Sale/Title/Gift Deed, survey 76/3-
Khatha, survey 76/3-
Registration CertificateFile: Certificate of Incorporation.pdf-
Organization StructureFile: Director Details.pdf-
Certificate issued by CA Form 1File: Form 1 - CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 and Form 3 - Engineer and Architect.pdf-
Certificate issued by Engineer Form 3File: Form 3 - Engineer Certifcate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 - CA Certificate.pdf-

How this compares with Bengaluru Urban

48%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MATHAPATHI GRAND FIELD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMATHAPATHI GRAND FIELDOther 75Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: MATHAPATHI CONSTRUCTIONS PRIVATE LIMITED

MATHAPATHI CONSTRUCTIONS PRIVATE LIMITED has 1 registration on RERA Karnataka, including MATHAPATHI GRAND FIELD. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MATHAPATHI GRAND FIELD is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MATHAPATHI GRAND FIELD?

The registered promoter entity is MATHAPATHI CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Its CIN U45209KA2020PTC138189 and GSTIN 29AANCM7677B1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MATHAPATHI GRAND FIELD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MATHAPATHI GRAND FIELD?

The professionals named in the filing: Architect: K.B.MAHALINGA SWAMY; Engineer: K.B.MAHALINGA SWAMY; Chartered Accountant: K.S.REDDY AND CO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MATHAPATHI GRAND FIELD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MATHAPATHI GRAND FIELD. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MATHAPATHI GRAND FIELD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.