ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / MARUTI AKRIDA

Registration approved No litigation declared Residential/Group Housing project

MARUTI AKRIDA

By MARUTI VENTURES

RG-KA-47549 · RERA PRM/KA/RERA/1251/308/PR/210825/008019 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2027Possession promisedno revision filed
4 of 18Construction stages donefurthest along: Plastering inside, 95%
259 of 322Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 132 documents Report an error

MARUTI AKRIDA is a Residential/Group Housing project by MARUTI VENTURES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/210825/008019 on 21 Aug 2025. Possession is promised by 30 Jun 2027. 63 of the 322 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete.

At a glance

Project

  • NameMARUTI AKRIDA
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/210825/008019
  • ReraGenie IDRG-KA-47549

Builder

  • NameMARUTI VENTURES
  • Entity typePartnership Firm
  • GSTIN29ABEFM6872H1ZS
  • Authorized SignatoryLEKKALA CHAKRAPANI

Key dates

this monthRegisteredAug 2025PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Aug 2025
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed132 files

Current status

20%63 of 322 units booked
43.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER-A---1400140
B---1330133
C---49049

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 18 construction stages are filed complete. The stage furthest along is Plastering inside, at 95%.

Building: 48% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)92%
Retaining wall (All types)100%
RCC or MS Framed structure93%
Masonry Construction60%
Plastering inside , outside & Ceiling95%
Joinery: Doors, Windows, Ventilators etc25%
Basic work of Water supply, Sanitary and Electrification25%
Dadoing, Skirting, Flooring, Tiles work (All types)5%
Railing and Grill fixing20%
Electrification, Water supply and Sanitary Finishing0%
Painting10%
Fire prevention and fire fighting fitting and fixture with network20%
Weather Proof work(tile,concrete)5%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work7%
Internal and External work including landscapes as per sanctioned drawings2%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes30%
Sewage and Drainage SystemYes15%
Water conservation/rain water harvesting/recharge of ground waterYes55%
Energy managementYes0%
Fire protection and fire safety requirementsYes25%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes10%
Internal Roads & FootpathsYes30%
Electricity supply transformer and substationYes10%
Storm water drainsYes25%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes70%
Parks & Tree plantingYes0%
Street LightingYes35%
ElectricityYes5%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes50%
Club HouseYes50%
Community HallYes50%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes10%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningYes0%
StaircasesYes70%
LiftsYes5%
Corridor/LobbiesYes55%
Fire escapesYes25%
Common entrance and exit for the building/common portico/foyer/verandahYes20%
BasementYes25%
TerraceYes35%
Outer WallYes55%
Open parking areasYes10%
Provision for lodging of management staff and security staffYes25%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,580 sq m
Named landowners4
LandownerVillageDistrict
JAGANATHA N--
P DHANUNJAYA REDDY--
P DHANUNJAYA REDDY--
P DHANUNJAYA REDDY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 131.20 cr
Cost incurredRs 56.65 cr
Spent of the estimate43.18%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 112.79 crRs 45.78 cr
On-site expenditure-Salaries of workersRs 6.15 crRs 3.79 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 5.63 crRs 2.86 cr
On-site expenditure-Site OverheadRs 3.15 crRs 2.36 cr
On-site expenditure-Consultants FeesRs 1.36 crRs 1.28 cr
Payment of cessRs 1.13 crRs 10.00 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 98.51 lakhRs 47.09 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAMESH BABU JAYA PRAKASH
EngineerRAMESHA D B
Chartered AccountantKopalli Mallikarjuna

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed132

As listed on the registration, under the names the promoter filed them with; the newest 80 of 132 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/210825/008019 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q2-26-27 MV Akrida form-4.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Q2-26-27 MV Akrida form -5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2-26-27 MV Akrida form-6-1.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Labour and Education Department15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q-1 26-27 MV AKRIDA-Form-4.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Q1-26-27 MV Akrida form -5.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q1-26-27 MV Akrida form-6.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Labour and Education Department14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4_Q4_Maruti Ventures _Akirda_FY 2025-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Q4-25-26 MV Akrida form -5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4-25-26 MV Akrida form-6.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Labour and Education Department15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Maruti venture _KRERA_Form4_compressed.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Q3-25-26 MV Akrida form -5.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q3-25-26 MV Akrida form-6.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 Fire and Safety13 Jan 2026
Q3 2025-26 Labour and Education Department13 Jan 2026
Q3 2025-26 Airport Authority of India13 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department13 Jan 2026
stability certificateFile: Stebility certificate.jpg14 Aug 2025
project estimation detailsFile: Estimation Cost.pdf14 Aug 2025
Proforma of agreement (AFS)File: Maruti Akrida Agreement of Sale Proforma updated.pdf14 Aug 2025
Proforma Allotment letterFile: Maruti Akrida AllotmentLetter Revised (1).pdf14 Aug 2025
section 3(1) affidavitFile: Section 3(1)Affidavit (1).pdf14 Aug 2025
Land cost calculation sheetFile: Guidance value.pdf14 Aug 2025
STP design drawingFile: STP (2).pdf14 Aug 2025
134/2 EC LatestFile: EC 134-2.pdf5 Aug 2025
134/2 Mutation RecordFile: 1342 MR (2).pdf5 Aug 2025
134/2 Title DeedFile: 134-2 Sale Deed.pdf5 Aug 2025
416/3 EC LatestFile: EC 416-3.pdf5 Aug 2025
416/3 Mutation RecordFile: 4163 MR.pdf5 Aug 2025
416/3 Title DeedFile: Sale Deed 416-3.pdf5 Aug 2025
416/4 EC LatestFile: EC 416-4.pdf5 Aug 2025
416/4 Mutation RecordFile: 416-4 MR.pdf5 Aug 2025
416/4 Title DeedFile: Sale Deed 416-4.pdf5 Aug 2025
416/7 EC LatestFile: EC 416-7.pdf5 Aug 2025
416/7 Mutation RecordFile: 416-7 MR.pdf5 Aug 2025
416/7 Title DeedFile: Sale Deed 416-7.pdf5 Aug 2025
Section 3(1)File: AFFIDAVIT CUM DECLARATION (2).pdf5 Aug 2025
FIRE NOCFile: MARUTI VENTURES FIRE NOC.pdf5 Aug 2025
GUIdence Value of Land CostFile: Guidance value MV.pdf5 Aug 2025
STP MVFile: STP MV.pdf5 Aug 2025
structural Stability certificateFile: MV Akrida Structural stability certificate.pdf5 Aug 2025
Specifications documentFile: MV specifications.pdf5 Aug 2025
Engineer Estimation DeclarationFile: Maruti Ventures Akrida Form 3 (3).pdf5 Aug 2025
134/2 KathaFile: katha 134 2_0001.pdf5 Aug 2025
416/3 KathaFile: katha 416 3_0001.pdf5 Aug 2025
416/4 KathaFile: katha 416 4_0001.pdf5 Aug 2025
416/7 KathaFile: katha 416 7_0001.pdf5 Aug 2025
Engineer CertificateFile: RAMESH DB Engineer Certificate.jpeg5 Aug 2025
RTC, survey 134/2-
Mutation, survey 134/2-
Encumbrance Certificate, survey 134/2-
Conversion/Alienation Order, survey 134/2-
JDA, survey 134/2-
Khatha, survey 134/2-
RTC, survey 416/3-
Mutation, survey 416/3-
Encumbrance Certificate, survey 416/3-
Conversion/Alienation Order, survey 416/3-
JDA, survey 416/3-
Khatha, survey 416/3-
RTC, survey 416/4-

How this compares with Bengaluru Urban

20%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MARUTI AKRIDA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMARUTI AKRIDAOther 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: MARUTI VENTURES

MARUTI VENTURES has 1 registration on RERA Karnataka, including MARUTI AKRIDA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MARUTI AKRIDA is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MARUTI AKRIDA?

The registered promoter entity is MARUTI VENTURES, a partnership firm as per the filing. Its GSTIN 29ABEFM6872H1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MARUTI AKRIDA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MARUTI AKRIDA?

The professionals named in the filing: Architect: RAMESH BABU JAYA PRAKASH; Engineer: RAMESHA D B; Chartered Accountant: Kopalli Mallikarjuna. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARUTI AKRIDA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARUTI AKRIDA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARUTI AKRIDA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.