ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / MarkON Sportz Valley

Registration approved No litigation declared Mixed Development project

MarkON Sportz Valley

By MARKON DEVELOPERS

RG-KA-27478 · RERA PRM/KA/RERA/1251/308/PR/121125/008242 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Oct 2030Possession promisedno revision filed
3 of 17Construction stages donefurthest along: RCC or MS Framed structure, 20%
69 of 73Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 166 documents Report an error

MarkON Sportz Valley is a Mixed Development project by MARKON DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/121125/008242 on 12 Nov 2025. Possession is promised by 31 Oct 2030. 4 of the 73 units on this registration are recorded sold or booked, and 3 of 17 construction stages are filed complete.

At a glance

Project

  • NameMarkON Sportz Valley
  • TypeMixed Development
  • Location
    • Anekal
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/121125/008242
  • ReraGenie IDRG-KA-27478

Builder

  • NameMARKON DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29ABQFM1715P1ZJ
  • Authorized SignatorySrinivasulu Kondamuri

Key dates

this monthRegisteredNov 2025PromisedOct 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on12 Nov 2025
  • Promised completion31 Oct 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed166 files

Current status

5%4 of 73 units booked
4.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block1---73073

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 17 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 20%.

Building: 19% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure20%
Masonry Construction10%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities38

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes10%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes10%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable

Land and ownership14

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,079 sq m
Named landowners14
LandownerVillageDistrict
NIRMALA--
NIRMALA--
NIRMALA--
NIRMALA--
MARKON DEVELOPERS--
MARKON DEVELOPERS--
MARKON DEVELOPERS--
MARKON DEVELOERS--
MARKON DEVELOPERS--
MARKON EVELOPERS--
MARKON DEVELOPERS--
MARKON DEVELOPERS--
MARKON DEVELOPERS--
MARKON DEVELOPERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 84.18 cr
Cost incurredRs 3.83 cr
Spent of the estimate4.55%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 67.18 crRs 2.80 cr
On-site expenditure-Site OverheadRs 5.00 crRs 1.40 lakh
On-site expenditure-Salaries of workersRs 3.50 crRs 8.15 lakh
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 3.00 crRs 62.23 lakh
Payment of taxesRs 2.00 crRs 14.79 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.50 crRs 91,705
On-site expenditure-Consultants FeesRs 1.00 crRs 15.68 lakh
Payment of cessRs 50.00 lakh-
Payment of chargesRs 30.00 lakh-
Payment of feesRs 10.00 lakh-
Payment of PremiumsRs 10.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBommu Veera Narendranath Redd
EngineerYALLA MALLIKARJUNA
Chartered AccountantHemadri K

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed166

As listed on the registration, under the names the promoter filed them with; the newest 80 of 166 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/121125/008242 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Q2_CA.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5_SV_Q2_Architect.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6_SV_Q2_Engineer.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form4_Q1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5_Q1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6_Q1.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form- 4_CA_Q4.pdf27 Jun 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form- 5_Architect_Q4.pdf27 Jun 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form- 6_Engineer_Q4.pdf27 Jun 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_Q3.pdf19 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form -5, Architect certificate_Q3_18FEB2026(DEC2025).pdf19 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer certificate_Q3.pdf19 Feb 2026
FORM B AFFIDAVITFile: Form_B_Affidavit.pdf7 Nov 2025
LAND VALUE CALCULATION SHEETFile: Landcost_Calculation_SV.pdf7 Nov 2025
ALLOTMENT LETTERFile: Allotment_Letter_SV.pdf7 Nov 2025
LATEST EC SHOWING THE BAJAJ HOUSING FINANACE LIMITED MORTGAGEFile: ECC-Bajaj_Housing.pdf7 Nov 2025
GUIDANCE VALUE CERTIFICATE SARJAPUR LANDSFile: Valuation_Certificate_SV.pdf7 Nov 2025
STP drawingFile: STP_Drawing_SV.pdf7 Nov 2025
88/2 Sale deedFile: 88_2 Sale Deed.pdf7 Nov 2025
88/3 Sale deedFile: 88_3_20Guntas Sale Deed.pdf7 Nov 2025
88/4 Sale deedFile: 88_4_09Guntas Sale Deed.pdf7 Nov 2025
89/2 Sale deedFile: 89_2_Saledeed.pdf7 Nov 2025
1)Approved Original Single Plot layout planFile: STRR DP Approval Drawing ( ).pdf30 Oct 2025
2)Approved Original Single Plot layout plan orderFile: STRR DP Work Order ( ).pdf30 Oct 2025
3)ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR_Sketch_Sarjapur_PH1.pdf30 Oct 2025
3)ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey letterFile: ADLR to STRR Return Letter ( ).pdf30 Oct 2025
4)Upload commencement certificate.File: Commencement_SV.pdf30 Oct 2025
5)Demarcation of proposed land in Approved Master plan Certified by the competent authority.File: Sarjapura 88 LU.pdf30 Oct 2025
6)Demarcation of proposed land in original Village map certified by the competent authority.File: Sarjapura 88 RC.pdf30 Oct 2025
Demarcation of proposed land in original Google map certified by the competent authority.File: Sarjapura 88 SR1.pdf30 Oct 2025
8) Upload project specification along with signatureFile: Project_Specifications_SV.pdf30 Oct 2025
9) Kindly upload the Proforma of agreement (AFS) for sale, duly fill all applicable fieldsFile: SA_RERA_SportzValley_Sarjapur.pdf30 Oct 2025
10) Upload Proforma Allotment letter as per the prescribed format duly fill all applicable fieldsFile: Allotment_Letter_SV.pdf30 Oct 2025
11) Kindly upload the SEIAA NOC with all pagesFile: SEIAA NOC.pdf30 Oct 2025
12) Upload brief project estimation with licenced engineer signature.File: Construction_Cost_Estimate_Engineer.pdf30 Oct 2025
13)Kindly upload the STP design drawing certified by the Engineer as per the guidelines.File: STP_Drawing_SV.pdf30 Oct 2025
14)Please upload the Land cost calculation sheet as per the guidance value(Self-attested copy).File: LandCost_Estimation_selfattested_SV.pdf30 Oct 2025
Upload structural stability certificate duly signed by the Structural engineerFile: Sarjapura_Stability_Certificate.pdf30 Oct 2025
RTC, survey 88/2-
Mutation, survey 88/2-
Encumbrance Certificate, survey 88/2-
Conversion/Alienation Order, survey 88/2-
JDA, survey 88/2-
Khatha, survey 88/2-
RTC, survey 88/3-
Mutation, survey 88/3-
Encumbrance Certificate, survey 88/3-
Conversion/Alienation Order, survey 88/3-
JDA, survey 88/3-
Khatha, survey 88/3-
RTC, survey 88/4-
Mutation, survey 88/4-
Encumbrance Certificate, survey 88/4-
Conversion/Alienation Order, survey 88/4-
JDA, survey 88/4-
Khatha, survey 88/4-
RTC, survey 89/2-
Mutation, survey 89/2-
Encumbrance Certificate, survey 89/2-
Conversion/Alienation Order, survey 89/2-
JDA, survey 89/2-
Khatha, survey 89/2-
RTC, survey 90/1-
Mutation, survey 90/1-
Encumbrance Certificate, survey 90/1-
Conversion/Alienation Order, survey 90/1-
Sale/Title/Gift Deed, survey 90/1-
Khatha, survey 90/1-
RTC, survey 90/2-
Mutation, survey 90/2-
Encumbrance Certificate, survey 90/2-
Conversion/Alienation Order, survey 90/2-
Sale/Title/Gift Deed, survey 90/2-
Khatha, survey 90/2-
RTC, survey 90/3-
Mutation, survey 90/3-
Encumbrance Certificate, survey 90/3-
Conversion/Alienation Order, survey 90/3-
Sale/Title/Gift Deed, survey 90/3-
Khatha, survey 90/3-

How this compares with Bengaluru Urban

5%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MarkON Sportz Valley on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMarkON Sportz ValleyOther 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: MARKON DEVELOPERS

MARKON DEVELOPERS has 1 registration on RERA Karnataka, including MarkON Sportz Valley. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MarkON Sportz Valley is delayed beyond 31 Oct 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MarkON Sportz Valley?

The registered promoter entity is MARKON DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29ABQFM1715P1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MarkON Sportz Valley?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MarkON Sportz Valley?

The professionals named in the filing: Architect: Bommu Veera Narendranath Redd; Engineer: YALLA MALLIKARJUNA; Chartered Accountant: Hemadri K. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MarkON Sportz Valley?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MarkON Sportz Valley. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MarkON Sportz Valley to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.