Home / Browse projects / Belagavi, Karnataka / MARIGOLD
MARIGOLD
By SHIRGURKAR REAALTYY PRIVATE LIMITED
RG-KA-42340 · RERA PRM/KA/RERA/1249/447/PR/050525/007711 · Last updated on RERA Karnataka portal: 26 Jan 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
MARIGOLD is a Residential/Group Housing project by SHIRGURKAR REAALTYY PRIVATE LIMITED in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/050525/007711 on 5 May 2025. Possession is promised by 31 Dec 2027. 1 of the 23 units on this registration are recorded sold or booked, and 3 of 14 construction stages are filed complete.
At a glance
Project
- NameMARIGOLD
- TypeResidential/Group Housing
- Location
- Belagavi
- PincodeNot stated
- RERA no.PRM/KA/RERA/1249/447/PR/050525/007711
- ReraGenie IDRG-KA-42340
Builder
- NameSHIRGURKAR REAALTYY PRIVATE LIMITED
- Entity typeCompany
- CINU45100KA2005PTC035492
- GSTIN29AABCH5184L1Z4
- Authorized SignatorySUMIT NITIN SHIRGURKAR
- DirectorNITIN ARVIND SHIRGURKAR
- DirectorsNITIN SHRIGURKAR, AMITA NITIN SHRIGURKAR, SUNIT NITIN SHIRGURKAR
- Project HeadSUMIT SHIRGURKARK
- Other registrations2 more →
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on5 May 2025
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed135 files
Current status
Figures as on 26 Jan 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MARIGOLD | - | - | - | 23 | 0 | 23 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 26 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 14 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 50%.
Building: 29% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 50% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 35% |
| Masonry Construction | 5% |
| Plastering inside , outside & Ceiling | 5% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 5% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 2% |
| Railing and Grill fixing | 2% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 26 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 25% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | 75% |
| Terrace | Yes | 0% |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership21
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SHIVAJI B SUTAR | - | - |
| ANAND SADANAND SUTAR | - | - |
| VIJAY SADANAND SUTAR | - | - |
| MEERA ATUL SUTAR | - | - |
| VEENA SATISH KAMMAR | - | - |
| NANDA DNYANESHWAR SUTAR | - | - |
| MOHAN BHARMA SUTAR | - | - |
| ANAND SADANAND SUTAR | - | - |
| MEERA SUTAR | - | - |
| MOHAN B SUTAR | - | - |
| NANDA SUTAR | - | - |
| SHIVAJI SUTAR | - | - |
| VEENA KAMMAR | - | - |
| VIJAY SUTAR | - | - |
| ANAND SUTAR | - | - |
| MEERA SUTAR | - | - |
| MOHAR SUTAR | - | - |
| NANDA SUTAR | - | - |
| SHIVAJI SUTAR | - | - |
| VEENA KAMMAR | - | - |
| VIJAY SUTAR | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 2.51 cr | Rs 9.68 lakh |
| Interest on borrowings | Rs 30.00 lakh | - |
| administrative cost | Rs 15.00 lakh | - |
| On-site expenditure-Consultants Fees | Rs 4.00 lakh | Rs 21,470 |
| Taxes, cess and levy | Rs 3,527 | Rs 20,388 |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NITIN SHIRGURKAR |
| Engineer | VINAY BEHERE |
| Chartered Accountant | RAJENDRA MUNDADA |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed135
As listed on the registration, under the names the promoter filed them with; the newest 80 of 135 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/050525/007711 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: QU 3 FORM 4 25-26.pdf | 26 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: QU 3 FORM 5 25-26.pdf | 26 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: QU 3 FORM 6 25-26.pdf | 26 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 26 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 26 Jan 2026 |
| Source of fund with supporting documentsFile: Source of fund with supporting documents.pdf | 22 Feb 2025 |
| about quarterly report of the previous projectFile: Quarter details about previous project.pdf | 22 Feb 2025 |
| source of fund with supporting documentsFile: Source of fund with supporting documents.pdf | 4 Feb 2025 |
| about Total site area in approved plan and in order copyFile: about total built up area in order copy and plan.pdf | 4 Feb 2025 |
| about commencement certificateFile: about commencment.pdf | 4 Feb 2025 |
| Source of fund with supporting documentsFile: Source of fund with supporting documents.pdf | 14 Jan 2025 |
| submission confirmation of annual audit of previous projectFile: Submission Confirmation Annual audit for Nishigandha.pdf | 14 Jan 2025 |
| katha extract in the names of all owner as othersFile: KHATA IN THE NAME OF ALL OWNER AS OTHERS.jpeg | 14 Jan 2025 |
| order for Water NOC with DDFile: Marigold Water NOC ref letter with DD.pdf | 14 Jan 2025 |
| about commencement certificateFile: about commencment.pdf | 14 Jan 2025 |
| original sanctioned drawings, floor plan, sectional drawings and elevationsFile: modified drawing hindu nagar (1).pdf | 14 Jan 2025 |
| Total site area is not matching in approved plan and in order copyFile: about plot area in plan and approved letter.pdf | 14 Jan 2025 |
| about total built up area in order copy and planFile: about total built up area in order copy and plan.pdf | 14 Jan 2025 |
| Permission order copyFile: building license.pdf | 14 Jan 2025 |
| Permission drawingFile: modified drawing hindu nagar (1).pdf | 14 Jan 2025 |
| source of fund with supporting documentsFile: Source of fund with supporting documents.pdf | 10 Dec 2024 |
| CTS extract of 779 i.e. khata issued by the City Survey office reflects name of all ownersFile: CTS Extract 779 - 17-06-2023_compressed.pdf | 10 Dec 2024 |
| CTS extract of 780 i.e. khata issued by the City Survey office reflects name of all ownersFile: CTS No 780_compressed.pdf | 10 Dec 2024 |
| CTS extract of 781 i.e. khata issued by the City Survey office reflects name of all ownersFile: CTS No 781.pdf | 10 Dec 2024 |
| ADLR of CTS Certified the Boundary of the Proposed land- survey skectFile: ADLR certified survey skecth.jpeg | 10 Dec 2024 |
| modified approved planFile: modified drawing hindu nagar.pdf | 10 Dec 2024 |
| modified permission letterFile: Modified Permission Letter Hindu Nagar.pdf | 10 Dec 2024 |
| Original sanctioned drawings, floor plan, sectional drawings and elevations bearing QR codeFile: modified drawing hindu nagar.pdf | 10 Dec 2024 |
| CTS Map (Village Map)File: ADLR certified survey skecth.jpeg | 10 Dec 2024 |
| Approval/NOC under section 14 of the KTCP ActFile: Approval-NOC Section 14.pdf | 10 Dec 2024 |
| Form 6 at the time of regsitrationFile: Form 6 at the time of registration.pdf | 10 Dec 2024 |
| CDPFile: CDP.jpg | 10 Dec 2024 |
| master plan demarcation of project land areaFile: master plan demarcation of project land.jpg | 10 Dec 2024 |
| about source of fund with supporting documentsFile: Source of fund with supporting documents.pdf | 23 Oct 2024 |
| about borrowing details not mentioned in CA Form 1 certificateFile: about borrowing in financial statement.pdf | 23 Oct 2024 |
| self attested membership certificate of CAFile: self atteste membership certificate of CA.pdf | 23 Oct 2024 |
| annual audit of previous project NishigandhaFile: rera form no 7 Nishigandh.pdf | 23 Oct 2024 |
| ADLR survey sketch certifying boundary of the project landFile: ADLR certified survey skecth.jpeg | 23 Oct 2024 |
| original digital signed sanctioned drawings, floor plan, sectional drawings and elevations.File: modified drawing hindu nagar.pdf | 23 Oct 2024 |
| original building permission letterFile: Modified Permission Letter Hindu Nagar.pdf | 23 Oct 2024 |
| Village Map certified by concern department about boundaries of the project landFile: ADLR certified survey skecth.jpeg | 23 Oct 2024 |
| about change of land useFile: about Conversion Order.pdf | 23 Oct 2024 |
| about project status as new launch and not ongoingFile: ABOUT ONGOING STATUS OF THE PROJECT.pdf | 23 Oct 2024 |
| Defect liability in AOS as notifiedFile: Format of Agreement of sale.pdf | 23 Oct 2024 |
| about water NOCFile: about water NOC.pdf | 23 Oct 2024 |
| about FARFile: about FAR.pdf | 23 Oct 2024 |
| about plot area in the letter and in the planFile: about plot area in plan and approved letter.pdf | 23 Oct 2024 |
| KhataFile: Form No 2 Hindu Nagar.jpeg | 23 Oct 2024 |
| self attested PANFile: SRPL Pan Seal with Sign.pdf | 20 Sep 2024 |
| About borrowing details as per financial statementFile: about borrowing in financial statement.pdf | 20 Sep 2024 |
| Company registration numberFile: Certificate of Firm.pdf | 20 Sep 2024 |
| EC from 20/9/2022 to till date For CTS Number 779 , 781 & 780File: ECC-24082024- marigold (1).pdf | 20 Sep 2024 |
| about renewed JDA between Landowner and promoterFile: about renewal of JDA.pdf | 20 Sep 2024 |
| Form 2 of KhataFile: Form No 2 Hindu Nagar.jpeg | 20 Sep 2024 |
| Title deed of current land owner CTS 781File: Shalan ramesh patil sale deed cts no 781.pdf | 20 Sep 2024 |
| Advocate search reportFile: Legal Opinion - Marigold Hindu Nagar.pdf | 20 Sep 2024 |
| Notarized Form B-AffidavitFile: form b (2).pdf | 20 Sep 2024 |
| about single plot layout order and planFile: about Single plot layout order and plan.pdf | 20 Sep 2024 |
| Building license from local authority with QR CodeFile: Marigold Permission Letter.pdf | 20 Sep 2024 |
| approved building plan with QR CodeFile: Marigold Permission Drawing.pdf | 20 Sep 2024 |
| Phase wise Development phase demarcation drawingFile: about phase wise development.pdf | 20 Sep 2024 |
| about COA Architect certificateFile: about COA.pdf | 20 Sep 2024 |
| about Car parking order allotmentFile: about car parking.pdf | 20 Sep 2024 |
| sewer line drawing certifiedFile: MARIGOLD - SEWER LINE LAYOUT FOR RERA.pdf | 20 Sep 2024 |
| self attested HESCOM NOCFile: Hescom NOC Marigold Self Attested-.pdf | 20 Sep 2024 |
| about land cost calculationsFile: Land cost calculations.pdf | 20 Sep 2024 |
| Format of agreement as notifiedFile: Format of Agreement of sale.pdf | 20 Sep 2024 |
| about water NOCFile: about water NOC.pdf | 20 Sep 2024 |
| Registration CertificateFile: Certificate of Firm.pdf | - |
| Memorandum of AssociationFile: Altered Memorandum of Association.pdf | - |
| Article of AssociationFile: Altered Articles of Association.pdf | - |
| GST Certificate | - |
| Organization StructureFile: Certificate - Change of Object Clause.pdf | - |
| Certificate issued by CA Form 1File: Form 1-CA.pdf | - |
| Certificate issued by Architect Form 2File: Form -2, Architect _Marigold_.pdf | - |
| Certificate issued by Engineer Form 3File: Form - 3, Engineer _Marigold_.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: No litigation - Affidavit.pdf | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| NISHIGANDH | CTS NO. 2178, OLD PLOT NO. 137(PART), R S NO. 14/1/2 , CORPORATION NO. 712/4E, S V ROAD , ANGOL | Ongoing | Dec 2025 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep MARIGOLD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Swarna Griha - 4 Phase 1
Felicity Adobe LLP
SkyCity Homes
M/s. Vishal Infra Built Ltd.
Shree Sant Babamaharaj Complex
Ratuja Developers
Pinnacle
Lotus Landmakrs (I) Pvt Ltd
JYOTICHANDRA
G P DEVELOPERS
SHIVNERI Apartment
SHIVNERI CONSTRUCTIONS
See every Belagavi project, with the district possession charts
Builder: SHIRGURKAR REAALTYY PRIVATE LIMITED
SHIRGURKAR REAALTYY PRIVATE LIMITED has 3 registrations on RERA Karnataka, including MARIGOLD and NISHIGANDHA. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if MARIGOLD is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of MARIGOLD?
The registered promoter entity is SHIRGURKAR REAALTYY PRIVATE LIMITED, a company as per the filing. Its CIN U45100KA2005PTC035492 and GSTIN 29AABCH5184L1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in MARIGOLD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at MARIGOLD?
The professionals named in the filing: Architect: NITIN SHIRGURKAR; Engineer: VINAY BEHERE; Chartered Accountant: RAJENDRA MUNDADA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MARIGOLD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.