Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Manik Prabhu Nagar is a Plotted Development project by Girish K Butali in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/362/PR/290323/005827 on 29 Mar 2023. Possession is promised by 31 Dec 2023.
At a glance
Project
- NameManik Prabhu Nagar
- TypePlotted Development
- Location
- Athni
- Belagavi
- 591248
- Pincode591248
- RERA no.PRM/KA/RERA/1249/362/PR/290323/005827
- ReraGenie IDRG-KA-21714
Builder
- NameGirish K Butali
- Entity typeProprietorship Firm
- GSTIN29AECPB8304A1Z5
- Authorized SignatoryGirish K Butali
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on29 Mar 2023
- Promised completion31 Dec 2023
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed91 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Girish K Butali | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 95.88 lakh | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | Annappa Giramalla Halli |
| Chartered Accountant | Mahesh Tenzing &Co |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed91
As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/362/PR/290323/005827 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| profit and loss 2019-20 along with UDINFile: Profit and Loss FY 19-20.pdf | 27 Feb 2023 |
| profit and loss 2020-21 along with UDINFile: Profit and Loss FY 20-21.pdf | 27 Feb 2023 |
| profit and loss 2021-22 along with UDINFile: Profit and Loss FY 21-22.pdf | 27 Feb 2023 |
| balance sheet 2019-20 along with UDINFile: Balance sheet FY 19-20.pdf | 27 Feb 2023 |
| balance sheet 2020-21 along with UDINFile: Balance sheet FY 20-21.pdf | 27 Feb 2023 |
| balance sheet 2021-22 along with UDINFile: Balance sheet FY 21-22.pdf | 27 Feb 2023 |
| sources of fund clarificationFile: Source of Project.pdf | 27 Feb 2023 |
| Advocate Search ReportFile: Legal Opinion.pdf | 27 Feb 2023 |
| title deed to ByrappaFile: Bhairappa Sale Dead.pdf | 27 Feb 2023 |
| title deed to Byrappa dairyFile: Bhairappa Telasang Dairy.pdf | 27 Feb 2023 |
| Plot wise area Break up of types of PlotFile: Plot wise breakup.pdf | 27 Feb 2023 |
| updated KGP planFile: Kjp 1.pdf | 27 Feb 2023 |
| Architects certificateFile: Architect Report.pdf | 27 Feb 2023 |
| Engineer license + his qualification CertificateFile: Engineer Certificate.pdf | 27 Feb 2023 |
| source of water supply to projectFile: Water NOC.pdf | 27 Feb 2023 |
| preform of Allotment letter in the prescribed formatFile: Allottment Letter.pdf | 27 Feb 2023 |
| Septic tank, Soak pit and sewer line demarcation drawingFile: Section of Septic Tank.pdf | 27 Feb 2023 |
| GST CertificateFile: 1-GST.pdf | 31 Jan 2023 |
| Balance sheet-2019-20File: 2-GKB BS FY 19-20.pdf | 31 Jan 2023 |
| Balance sheet-2020-21File: 2-GKB BS FY 20-21.pdf | 31 Jan 2023 |
| Balance sheet-2021-22File: 2-GKB BS FY 21-22.pdf | 31 Jan 2023 |
| Profit and Loss-2019-20File: 2-GKB PL FY 19-20.pdf | 31 Jan 2023 |
| Profit and Loss-2020-21File: 2-GKB PL FY 20-21.pdf | 31 Jan 2023 |
| Profit and Loss-2021-22File: 2-GKB PL FY 21-22.pdf | 31 Jan 2023 |
| Sale Deed in the name of promoterFile: 6-Sale Dead.pdf | 31 Jan 2023 |
| guidance value obtained from concerned sub registerFile: Marketing Valuation.pdf | 31 Jan 2023 |
| KGP PlanFile: 9-Kjp 1.pdf | 31 Jan 2023 |
| clear and legible layout planFile: 11-Town Planning Map.pdf | 31 Jan 2023 |
| Relinquishment deedFile: 12-Reliquishment Deed.pdf | 31 Jan 2023 |
| village mapFile: 13-Village Map.pdf | 31 Jan 2023 |
| Engineer certificateFile: 14-Certificate By Engineer.pdf | 31 Jan 2023 |
| fee receipt paid towards Power supply NOCFile: 17-Fee Paid Receipt Towards HESCOM NOC.pdf | 31 Jan 2023 |
| Water NOCFile: 18-water NOC.pdf | 31 Jan 2023 |
| signed copy of project specificationFile: 19-Project Specifications.pdf | 31 Jan 2023 |
| Allotment letterFile: 20-Allotment Letter.pdf | 31 Jan 2023 |
| section 3(1) notarized affidavitFile: 21-Affidavit.pdf | 31 Jan 2023 |
| Detailed signed reply by PromoterFile: Details Reply Doc.pdf | 31 Jan 2023 |
| RTC, survey 503/2 | - |
| Mutation, survey 503/2 | - |
| Encumbrance Certificate, survey 503/2 | - |
| Conversion/Alienation Order, survey 503/2 | - |
| Khatha, survey 503/2 | - |
| Certificate issued by CA Form 1File: Form Reg-1 Girish Butali_compressed.pdf | - |
| Certificate issued by Engineer Form 3File: 14-Certificate By Engineer.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: Affidavit.pdf | - |
| Certificate from Chartered AccountFile: Form Reg-1 Girish Butali_compressed.pdf | - |
| Certificate issued by ArchitectFile: Architect Report.pdf | - |
| Balance Sheet 2021 - 2022File: BS-21-22.pdf | - |
| Balance Sheet 2020 - 2021File: BS-20-21.pdf | - |
| Balance Sheet 2019 - 2020File: BS-19-20.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: PL-21-22.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: PL-20-21.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: PL-19-20.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR-21-22_compressed.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR-20-21.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: ITR-22-23_compressed.pdf | - |
| Town Planning Order Copy | - |
| Hescom Noc | - |
| Panchayat Noc | - |
| Town Planning Map | - |
| Town Planning Map | - |
| Project Specifications_compressed | - |
| N A Order Copy_compressed | - |
| Sale Dead | - |
| Proforma of Agreement of Sale updated | - |
| Allotment Letter | - |
| Form B | - |
| Affidavit Cum Declaration | - |
| Affidavit | - |
| Hescom Noc | - |
| Panchayat Noc | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep Manik Prabhu Nagar on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Swarna Griha - 4 Phase 1
Felicity Adobe LLP
SkyCity Homes
M/s. Vishal Infra Built Ltd.
Shree Sant Babamaharaj Complex
Ratuja Developers
Pinnacle
Lotus Landmakrs (I) Pvt Ltd
JYOTICHANDRA
G P DEVELOPERS
SHIVNERI Apartment
SHIVNERI CONSTRUCTIONS
See every Belagavi project, with the district possession charts
Builder: Girish K Butali
Girish K Butali has 1 registration on RERA Karnataka, including Manik Prabhu Nagar. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if Manik Prabhu Nagar is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Manik Prabhu Nagar?
The registered promoter entity is Girish K Butali, a proprietorship firm as per the filing. Its GSTIN 29AECPB8304A1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Manik Prabhu Nagar?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Manik Prabhu Nagar?
The professionals named in the filing: Engineer: Annappa Giramalla Halli; Chartered Accountant: Mahesh Tenzing &Co. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Manik Prabhu Nagar?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback