Home / Browse projects / Bengaluru Urban, Karnataka / MADHURA GARDENS

Registration approved No litigation declared Residential/Group Housing project

MADHURA GARDENS

By Markon Homes

RG-KA-07505 · RERA PRM/KA/RERA/1251/446/PR/290425/007699 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Apr 2030Possession promisedno revision filed
5 of 17Construction stages donefurthest along: RCC or MS Framed structure, 90%
61 of 80Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 117 documents Report an error

MADHURA GARDENS is a Residential/Group Housing project by Markon Homes in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/290425/007699 on 29 Apr 2025. Possession is promised by 30 Apr 2030. 19 of the 80 units on this registration are recorded sold or booked, and 5 of 17 construction stages are filed complete.

At a glance

Project

  • NameMADHURA GARDENS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/290425/007699
  • ReraGenie IDRG-KA-07505

Builder

  • NameMarkon Homes
  • Entity typePartnership Firm
  • GSTIN29ABVFM8224G1ZN
  • Authorized SignatorySrinivasulu Kondamuri

Key dates

this monthRegisteredApr 2025PromisedApr 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on29 Apr 2025
  • Promised completion30 Apr 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed117 files

Current status

24%19 of 80 units booked
14.0%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Madhura Gardens---80080

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 17 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 90%.

Building: 47% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure90%
Masonry Construction90%
Plastering inside , outside & Ceiling70%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing5%
Electrification, Water supply and Sanitary Finishing5%
Painting10%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)10%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work10%
Internal and External work including landscapes as per sanctioned drawings5%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes10%
Sewage and Drainage SystemYes10%
Water conservation/rain water harvesting/recharge of ground waterYes10%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes20%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes5%
Street LightingYes2%
ElectricityYes10%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes80%
Club HouseYes90%
Community HallYes90%
Outdoor Sports facilityYes10%
Indoor Sports facilityYes70%
Swimming PoolYes0%
GymYes50%
ParksYes5%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes10%
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasYes10%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes10%
Common storage spacesNoNot applicable

Land and ownership14

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area22,102 sq m
Named landowners14
LandownerVillageDistrict
S. NAGARAJ REDDY--
N.YESHWANTH,--
N.NISHRUTH--
S.K. JANARDHANA REDDY--
R. RENUKA--
HEMASHREE J--
HEMA CHANDRA.S. J--
S.K. JANARDHANA REDDY--
R. RENUKA--
HEMASHREE J--
HEMA CHANDRA.S. J--
SUVARNA V--
RATHNAMMA,--
M. G. Nataraj--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 102.96 cr
Cost incurredRs 14.39 cr
Spent of the estimate13.98%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 84.96 crRs 11.54 cr
On-site expenditure-Site OverheadRs 6.00 crRs 1.28 lakh
On-site expenditure-Salaries of workersRs 3.50 crRs 26.26 lakh
Principal sum and interest payable to financial institutions-Scheduled BanksRs 3.00 crRs 2.25 cr
Payment of taxesRs 2.00 crRs 27.22 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.50 crRs 4.15 lakh
On-site expenditure-Consultants FeesRs 1.00 crRs 1.40 lakh
Payment of cessRs 50.00 lakh-
Payment of chargesRs 30.00 lakh-
Payment of feesRs 10.00 lakh-
Payment of PremiumsRs 10.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBommu Veera Narendranath Reddy
EngineerYALLA MALLIKARJUNA
Chartered AccountantHemadri K

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed117

As listed on the registration, under the names the promoter filed them with; the newest 80 of 117 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/290425/007699 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_MG_Q2_CA.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5_MG_Q2_Architect.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6_Q2_ Engineer.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4_Q1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5_Q1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6_Q1.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form4_Q4_CA_MG.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form -5_Architect_Q4_MG.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4 MG Form 6 Engineer Certificate.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_Q3.pdf19 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form5_Architect_Q3_MG.pdf19 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q3 MG Form 6 Engineer Certificate.pdf19 Feb 2026
P&L 2023-24 w/UDINFile: PL_FY 2023-24.pdf24 Apr 2025
BS 2023-24 w/UDINFile: BS FY 2023-24.pdf24 Apr 2025
P&L 2022-23 w/UDINFile: PL_FY 2022-23.pdf24 Apr 2025
BS 2022-23 w/UDINFile: BS FY 2022-23.pdf24 Apr 2025
CA letter for FY 2021-22, NIL returnsFile: FY_21_22.pdf24 Apr 2025
Title deed for 47/1 - Family partitionFile: 47_1_47_2_Partion_Deed.pdf24 Apr 2025
Title deed for 47/1 - Release deedFile: Rel_Deed_Nagaraj_47_1.pdf24 Apr 2025
Title deed for 47/2 - Release deedFile: SY_47_2_Rel_Deed2_SKJ.pdf24 Apr 2025
Title deed for 47/25 - exchange deedFile: Exchange_Deed_janardhan.pdf24 Apr 2025
Title deed for 49/4File: 49_4_Ratnamma.pdf24 Apr 2025
Title deed for 49/5File: 49_4_Suvarna.pdf24 Apr 2025
Title deed for 49/6File: 49_4_Nataraj.pdf24 Apr 2025
MR in favour of 47/2 full extent 1 Acre 4 guntasFile: MRH9_22_23.pdf24 Apr 2025
Conversion order For Survey Number 49/4File: Sy No 49-4.pdf24 Apr 2025
JDA between land owner and promoter For Survey Number 49/5File: 49_5_Ratnama_ JDA_Comp.pdf24 Apr 2025
Engineer certificate self attestedFile: Form 3_Engineer_Certificate_MG.pdf24 Apr 2025
Amenities calculation sheetFile: Madhura Gardens Amenities and Common areas calculation sheet.pdf24 Apr 2025
self-attested copy of the Engineer license certificate.File: Eng_certificate_attested.pdf24 Apr 2025
Brief estimated cost of constructionFile: MG_Brief_Estimation_Construction.pdf24 Apr 2025
STP design drawing certified by the EngineerFile: MG_STP_Drawing.pdf24 Apr 2025
Land cost calculation sheetFile: Landcost_MG_Self_Atested.pdf24 Apr 2025
Proforma of the Allotment letterFile: Allotment_Letter_MG.pdf24 Apr 2025
Updated Form-B affidavit with start & End dateFile: FormB_Affidavit_24042025.pdf24 Apr 2025
BESCOM NOC self attestedFile: BESCOM_NOC_SelfAtested.pdf24 Apr 2025
BWSSB NOC self attestedFile: BWSSB_NOC_SelfAtested.pdf24 Apr 2025
Source of Funds - AU bank loanFile: Markon Homes _Loan_Sanction_Letter.pdf24 Apr 2025
Source of Funds - Partners contributionFile: BS FY 2023-24.pdf24 Apr 2025
RTC, survey 47/1-
Mutation, survey 47/1-
Encumbrance Certificate, survey 47/1-
Conversion/Alienation Order, survey 47/1-
JDA, survey 47/1-
Khatha, survey 47/1-
RTC, survey 47/2-
Mutation, survey 47/2-
Encumbrance Certificate, survey 47/2-
Conversion/Alienation Order, survey 47/2-
JDA, survey 47/2-
Khatha, survey 47/2-
RTC, survey 47/25-
Mutation, survey 47/25-
Encumbrance Certificate, survey 47/25-
Conversion/Alienation Order, survey 47/25-
JDA, survey 47/25-
Khatha, survey 47/25-
RTC, survey 49/4-
Mutation, survey 49/4-
Encumbrance Certificate, survey 49/4-
Conversion/Alienation Order, survey 49/4-
JDA, survey 49/4-
Khatha, survey 49/4-
RTC, survey 49/5-
Mutation, survey 49/5-
Encumbrance Certificate, survey 49/5-
Conversion/Alienation Order, survey 49/5-
JDA, survey 49/5-
Khatha, survey 49/5-
RTC, survey 49/6-
Mutation, survey 49/6-
Encumbrance Certificate, survey 49/6-
Conversion/Alienation Order, survey 49/6-
JDA, survey 49/6-
Khatha, survey 49/6-
Registration CertificateFile: MarkonHomes_Firm_Registration_Certificate.pdf-
GST CertificateFile: MarkonHomes_GST certificate.pdf-
Partnership DeedFile: MarkonHomes_Firm_Registration_Compress.pdf-
Partner Details-
Partner Details-

How this compares with Bengaluru Urban

24%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MADHURA GARDENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMADHURA GARDENSOther 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: Markon Homes

Markon Homes has 1 registration on RERA Karnataka, including MADHURA GARDENS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MADHURA GARDENS is delayed beyond 30 Apr 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MADHURA GARDENS?

The registered promoter entity is Markon Homes, a partnership firm as per the filing. Its GSTIN 29ABVFM8224G1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MADHURA GARDENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at MADHURA GARDENS?

The professionals named in the filing: Architect: Bommu Veera Narendranath Reddy; Engineer: YALLA MALLIKARJUNA; Chartered Accountant: Hemadri K. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MADHURA GARDENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MADHURA GARDENS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MADHURA GARDENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.