Maaz Residency

By RJM DEVELOPERS

RG-GJ-72371 · RERA PR/GJ/GANDHINAGAR/KALOL (G)/Kalol(G) Municipality/RAA15394/230625/311227 · Last updated on GujRERA portal: 27 May 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2028Possession promisedno revision filed
18 of 54Construction stages doneacross 6 buildings; furthest along: Internal walls, 90%
11 of 24Units unsoldnot recorded sold or booked
Jump to the 35 documents Report an error

Maaz Residency is a Residential/Group Housing project by RJM DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL (G)/Kalol(G) Municipality/RAA15394/230625/311227 on 23 Jun 2025. Possession is promised by 30 Apr 2028. 13 of the 24 units on this registration are recorded sold or booked, and 18 of 54 construction stages are filed complete.

At a glance

Project

  • NameMaaz Residency
  • TypeResidential/Group Housing
  • Location
    • Nr. S. Raj Homes
    • B/h. Al Fatima Residency
    • B/h. Rehmat Residency
    • Kalol
    • Kalol (G)
    • Gandhinagar
    • 382721
  • Pincode382721
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL (G)/Kalol(G) Municipality/RAA15394/230625/311227
  • ReraGenie IDRG-GJ-72371

Builder

  • NameRJM DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2025PromisedApr 2028

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2028
  • Registered on23 Jun 2025
  • Promised completion30 Apr 2028
  • Revised completionNone
  • Buildings6 building records
  • Documents filed35 files

Current status

54%13 of 24 units booked
93.3%Of the estimated cost spent so far

Figures as on 27 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A01 (Type)---101
A (Type)---101
B01 (Type)---10010
B (Type)---10010
C01 (Type)---101
C (Type)---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Internal walls, at 90%.

A01 (Type)71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%
A (Type)71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%
B01 (Type)71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%
B (Type)71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%
C01 (Type)71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%
C (Type)71%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats20%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing75%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%

Progress on shared amenities19

As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes70%
Water supplyYes50%
Sewerage (chamber, lines, septic tank, STP)Yes80%
Storm water drainsYes50%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,639 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 2.42 cr
Cost incurredRs 2.26 cr
Spent of the estimate93.29%
BuildingWingEstimatedIncurred
B (Type)NARs 1.01 crRs 95.00 lakh
B01 (Type)NARs 1.01 crRs 95.00 lakh
C (Type)NARs 10.13 lakhRs 9.00 lakh
C01 (Type)NARs 10.13 lakhRs 9.00 lakh
A (Type)NARs 9.69 lakhRs 9.00 lakh
A01 (Type)NARs 9.69 lakhRs 9.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhaumikkumar Chandravadanbhai Donga
EngineerNITINKUMAR PATEL

Documents filed35

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL (G)/Kalol(G) Municipality/RAA15394/230625/311227 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)27 May 2026
Engineer's certificate (Form 2)21 May 2026
Engineer's certificate annexure21 May 2026
Architect's certificate (Form 1)20 May 2026
Site photograph, A01 (Type)20 May 2026
Site photograph, A01 (Type)20 May 2026
Site photograph, A (Type)20 May 2026
Site photograph, A (Type)20 May 2026
Site photograph, B01 (Type)20 May 2026
Site photograph, B01 (Type)20 May 2026
Site photograph, B (Type)20 May 2026
Site photograph, B (Type)20 May 2026
Site photograph, C01 (Type)20 May 2026
Site photograph, C (Type)20 May 2026
RERA registration certificate23 Jun 2025
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-

How this compares with Gandhinagar

54%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Maaz Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kalol1,600+ in Gandhinagar

2 kmMaaz ResidencyOther 55Dot size: filed unitsN

Filed coordinates, straight-line distance. 55 registered projects within 2 km.

Builder: RJM DEVELOPERS

RJM DEVELOPERS has 1 registration on GujRERA, including Maaz Residency. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Maaz Residency is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Maaz Residency?

The registered promoter entity is RJM DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Maaz Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Maaz Residency?

The professionals named in the filing: Architect: Bhaumikkumar Chandravadanbhai Donga; Engineer: NITINKUMAR PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Maaz Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Maaz Residency. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Maaz Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.