Home / Browse projects / Belagavi, Karnataka / KRRISH VRINDAVAN
KRRISH VRINDAVAN
RG-KA-87015 · RERA PRM/KA/RERA/1249/447/PR/241225/008356 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
KRRISH VRINDAVAN is a Mixed Development project by GOPALRAO TUKARAM KUKDOLKAR in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/241225/008356 on 24 Dec 2025. Possession is promised by 9 Sep 2027. 0 of the 36 units on this registration are recorded sold or booked, and 3 of 15 construction stages are filed complete.
At a glance
Project
- NameKRRISH VRINDAVAN
- TypeMixed Development
- Location
- Belagavi
- PincodeNot stated
- RERA no.PRM/KA/RERA/1249/447/PR/241225/008356
- ReraGenie IDRG-KA-87015
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on24 Dec 2025
- Promised completion9 Sep 2027
- Revised completionNone
- Buildings1 building record
- Documents filed93 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KRRISH VRINDAVAN | - | - | - | - | - | 36 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 15 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 85%.
Building: 47% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 60% |
| Retaining wall (All types) | 50% |
| RCC or MS Framed structure | 85% |
| Masonry Construction | 60% |
| Plastering inside , outside & Ceiling | 30% |
| Joinery: Doors, Windows, Ventilators etc | 30% |
| Basic work of Water supply, Sanitary and Electrification | 20% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 10% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 60% |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 80% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 80% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 60% |
| Basement | Yes | 50% |
| Terrace | Yes | 20% |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| GOPALRAO TUKARAM KUKDOLKAR | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 6.95 cr | Rs 37,191 |
| On-site expenditure-Salaries of workers | - | Rs 29.65 lakh |
| On-site expenditure-Consultants Fees | - | Rs 8,540 |
| On-site expenditure-Site Overhead | - | Rs 20,000 |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | - | Rs 14,391 |
| Payment of taxes | - | Rs 6,367 |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GOPALRAO TUKARAM KUKDOLKAR |
| Engineer | VINAY JANARDHAN BEHERE |
| Chartered Accountant | TEJAS MEHTA |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed93
As listed on the registration, under the names the promoter filed them with; the newest 80 of 93 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/241225/008356 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: KV Form - 4 Chartered Accountant (FY 2026-27 Q2).pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate Q2 FY 2026-27.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate Q2 FY 2026-27.pdf | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: ARCHITECT CERTIFICATE - Q4 FY 2025-26.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENGINEER CERTIFICATE - Q4 FY 2025-26.pdf | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf | 14 Jan 2026 |
| Form-6File: Form-6 New.pdf | 5 Dec 2025 |
| land cost calculation sheetFile: Declaration of land valuve calculation_page-0001.pdf | 5 Dec 2025 |
| 1.1 ANNUAL AUDIT REPORTFile: 1 ANN UAL REPORT RERA - KRRISH GOKUL PROJECT.pdf | 13 Nov 2025 |
| 1.2 SOURCES OF FUNDFile: 2 SOURCE OF FUND.pdf | 13 Nov 2025 |
| 2.1 ECFile: 1 EC.pdf | 13 Nov 2025 |
| 3.1 & 2 SINGLE PLOT LAYOUT PLAN WITH ORDER COPYFile: 1 APPROVED LAYOUT.pdf | 13 Nov 2025 |
| 3.3 COMMENCEMENT CERTIFICATEFile: 3 COMMENCEMENT CERTIFICATE.pdf | 13 Nov 2025 |
| 3.4 VILLAGE/CTS MAPFile: 4 CTS MAP.pdf | 13 Nov 2025 |
| 3.5 NOC UNDER SECTION 14 OF THE KTCP ACTFile: 5 NA.pdf | 13 Nov 2025 |
| 4.1 DETAILS OF EXTENT OF DEVELOPMENTFile: 1 DETAILS OF EXTENT.pdf | 13 Nov 2025 |
| 4.2 NOC OF WATER SUPPLYFile: 2 WATER AFFIDAVIT.pdf | 13 Nov 2025 |
| 4.3 GUIDANCE CERTIFICATEFile: 3 GUIDANCE VALUE.pdf | 13 Nov 2025 |
| 1.1 ANNUAL AUDIT REPORT OF PREVIOUS PROJECTFile: 1 ANNUAL AUDIT REPORT K J.pdf | 9 Oct 2025 |
| 1.2 SOURCES OF FUNDFile: 2 OWN FUND.pdf | 9 Oct 2025 |
| 2.1 ECFile: 1 EC.pdf | 9 Oct 2025 |
| 3.1 APPROVED ORIGINAL SINGLE PLOT LAYOUT PLANFile: 1 NA.pdf | 9 Oct 2025 |
| 3.2 APPROVED ORIGINAL SINGLE PLOT LAYOUT PLAN ORDERFile: 2 NA.pdf | 9 Oct 2025 |
| 3.3 ADLR CERTIFIED SURVEY SKETCHFile: 3 CTS MAP.pdf | 9 Oct 2025 |
| 3.4 COMMENCEMENT CERTIFICATEFile: 4 COMMENCEMENT CERTIFICATE.pdf | 9 Oct 2025 |
| 3.5 DEMARCATION OF PROPOSED LANDFile: 5 CDP PLAN.pdf | 9 Oct 2025 |
| 3.6 NOC UNDER SECTION 14 OF KTCPFile: 6 NA.pdf | 9 Oct 2025 |
| 4.1 DETAILS OF EXTENT OF DEVELOPEMENTFile: 1 DETAILS OF EXTENT.pdf | 9 Oct 2025 |
| 4.2 HESCOM NOCFile: 2 HESCOM NOC ALONGWITH FEE RECEIPT.pdf | 9 Oct 2025 |
| 4.3 WATER NOCFile: 3 WATER NOC.pdf | 9 Oct 2025 |
| 4.4 LAND CALCULATION SHEET AS PER THE GUIDANCE VALUEFile: 4 GUIDANCE VALUE.pdf | 9 Oct 2025 |
| 1.1 ANNUAL AUDIT REPORTFile: 1 ANNUAL AUDIT REPORT K J.pdf | 6 Sep 2025 |
| 1.2 OWN FUNDFile: 2 OWN FUND.pdf | 6 Sep 2025 |
| 2.1 DEED OF SALEFile: 1 DEED OF SALE.pdf | 6 Sep 2025 |
| 2.2 ECFile: 2 NIL ENCUMBRANCE.pdf | 6 Sep 2025 |
| 2.3 FORM BFile: 3 FORM B.pdf | 6 Sep 2025 |
| 3.1 SINGLE PLOT LAYOUT PLANFile: 1 NA.pdf | 6 Sep 2025 |
| 3.2 SINGLE PLOT LAYOUT PLAN ORDERFile: 1 NA.pdf | 6 Sep 2025 |
| 3.3 BUILDING LICENSEFile: 3 BUILDING LICENSE FROM LOCAL ATHORITY.pdf | 6 Sep 2025 |
| 3.4 ADLR SURVEY SKETCHFile: 4 ADLR CERTIFIED SURVEY SKETCH.pdf | 6 Sep 2025 |
| 3.5 LOCATION DETAILS OF THE PROJECTFile: 5 LOCATION DETAILS OF THE PROJECT.pdf | 6 Sep 2025 |
| 3.6 APPROVED BUILDING PLANFile: 6 APPROVED BUILDING PLAN.pdf | 6 Sep 2025 |
| 3.7 ORIGINAL SANCTIONED DRAWINGFile: 7 ORIGINAL SANCTIONED DRAWING, FLOOR PLAN & ELEVATION.pdf | 6 Sep 2025 |
| 3.8 COMMENEMENT CERTIFICATEFile: 8 COMMENCEMENT CERTIFICATE.pdf | 6 Sep 2025 |
| 3.9 MASTER PLAN COPYFile: 9 CDP PLAN.pdf | 6 Sep 2025 |
| 3.10 VILLAGE MAPFile: 10 CTS MAP.pdf | 6 Sep 2025 |
| 3.11 KSPCB NOCFile: 11 KSPCB NOC.pdf | 6 Sep 2025 |
| 3.12 KTCPFile: 12 CDP MAP.pdf | 6 Sep 2025 |
| 4.3 ENGINEER LICENSEFile: 3 ENGINEER LICENSE CERTIFICATE.pdf | 6 Sep 2025 |
| 4.4 CA CERTIFICATEFile: 4 CA CERTIFICATE.pdf | 6 Sep 2025 |
| 4.5 FORM 6File: 5 FORM 6.pdf | 6 Sep 2025 |
| 4.6 STRUCTURAL STABILITY CERTIFICATEFile: 6 STRUCTURAL STABILITY CERTIFICATE WITH VALID LICENSE HOLDER SIGN.pdf | 6 Sep 2025 |
| 4.7 HESCOMFile: 7 HESCOM NC.pdf | 6 Sep 2025 |
| 4.7 WATER NOCFile: 7 1 WATER NOC.pdf | 6 Sep 2025 |
| 4.9 BRIEF ESTIMATIONFile: 9 BRIEF ESTIMATION WITH LICENSED ENGG SIGN.pdf | 6 Sep 2025 |
| 4.10 GUIDANCE VALUE SHEETFile: 10 GUIDANCE VALUE.pdf | 6 Sep 2025 |
| 4.11 STP DRAWINGFile: 11 STP DRAWING.pdf | 6 Sep 2025 |
| Registration CertificateFile: REGISTRATION UDYAM.pdf | - |
| GST CertificateFile: GST Certificate.pdf | - |
| Certificate issued by CA Form 1File: FORM 1 CA CERTIFICATE.pdf | - |
| Certificate issued by Architect Form 2File: FORM 2 ARCHITECT CERTIFICATE_compressed.pdf | - |
| Certificate issued by Engineer Form 3File: Form-6 New.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: AFFIDAVIT_compressed.pdf | - |
| Balance Sheet 2023 - 2024File: BALANCE SHEET AY 24-25.pdf | - |
| Balance Sheet 2022 - 2023File: BALANCE SHEET AY 23-24.pdf | - |
| Balance Sheet 2021 - 2022File: BALANCE SHEET AY 22-23.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: PROFIT & LOSS 24-25.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: PROFIT & LOSS 23-24.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: PROFIT & LOSS 22-23.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ITR AY 2024-25.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: PROFIT & LOSS 23-24.pdf | - |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| KRRISH ROYAL | CTS NO. 333/A, 333/B & 332 A, ROY ROAD, TILAKWADI, BELAGAVI | Completed | - | No date filed |
| KRRISH JEEVAN | CTS NO. 185, GURUWAR PETH, TILAKWADI, BELAGAVI | Completed | - | No date filed |
| KRRISH GOKUL | CTS NO. 92, MANGALWAR PETH, TILAKWADI, BELAGAVI | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep KRRISH VRINDAVAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Swarna Griha - 4 Phase 1
Felicity Adobe LLP
SkyCity Homes
M/s. Vishal Infra Built Ltd.
Shree Sant Babamaharaj Complex
Ratuja Developers
Pinnacle
Lotus Landmakrs (I) Pvt Ltd
JYOTICHANDRA
G P DEVELOPERS
SHIVNERI Apartment
SHIVNERI CONSTRUCTIONS
See every Belagavi project, with the district possession charts
Builder: GOPALRAO TUKARAM KUKDOLKAR
GOPALRAO TUKARAM KUKDOLKAR has 3 registrations on RERA Karnataka, including KRRISH JEEVAN and KRRISH VIHAR. Its filings declare 7 earlier projects, 7 of them declared completed. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if KRRISH VRINDAVAN is delayed beyond 9 Sep 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of KRRISH VRINDAVAN?
The registered promoter entity is GOPALRAO TUKARAM KUKDOLKAR, a proprietorship as per the filing. Its GSTIN 29AJJPK1495M1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in KRRISH VRINDAVAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at KRRISH VRINDAVAN?
The professionals named in the filing: Architect: GOPALRAO TUKARAM KUKDOLKAR; Engineer: VINAY JANARDHAN BEHERE; Chartered Accountant: TEJAS MEHTA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KRRISH VRINDAVAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback