ReraGenieLog inGet a buyer report

Home / Browse projects / Belagavi, Karnataka / KRRISH ROYAL

Registration approved Mixed Development project

KRRISH ROYAL

By GOPALRAO

RG-KA-85832 · RERA PRM/KA/RERA/1249/447/PR/191015/002921

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Apr 2023Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 77 documents Report an error

KRRISH ROYAL is a Mixed Development project by GOPALRAO in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/191015/002921 on 15 Oct 2019. Possession is promised by 9 Apr 2023. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameKRRISH ROYAL
  • TypeMixed Development
  • Location
    • Belagavi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1249/447/PR/191015/002921
  • ReraGenie IDRG-KA-85832

Builder

  • NameGOPALRAO
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2019First promiseJul 2022Revised toApr 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Oct 2019
  • Promised completion9 Apr 2023
  • Revised completionRevised to 9 Apr 2023 (originally 9 Jul 2022)
  • Buildings1 building record
  • Documents filed77 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
KRRISH ROYAL-----40

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,254 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 10.54 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGOPALRAO T. KUKDOLKAR
EngineerVINAY BEHERE

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJul 2022 → Apr 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed77

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/191015/002921 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificate-
Copy of Building Permission Plan-
Sanctioned layout building plan-
SALE DEED DRAFT RERA-
New Agreement Draft Copy-
Sale deed-
Copy of Building Permission Plan-
Area Development plan of Project Area-
letter-
KRRISH ROYAL BROUCHER-
all NOC(2)-
Project Specification-
Encumbrance Certificate(1)-
AFFIDAVIT-
CTS Extract-
Scan20-
Mother deed-
Scan20-
Scan20-
Scan20-
Scan20-
Fire Noc-
Scan20-
Scan20-
Scan20-
KSPCB-
Scan20-
Scan20-
Scan20-
Unnamed document-
Scan20-
Scan20-
Scan20-
Scan20-
Scan20-
Scan20-
Stability Certificate-
section-
Scan20-
Scan20-
Scan20-
Legal Opinion-
Balance Sheet 2017 - 2018File: Balance sheet 2018.pdf-
Balance Sheet 2016 - 2017File: Balance Sheet 2017.pdf-
Balance Sheet 2015 - 2016File: Balance sheet 2016.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Audited Profit loss Statement 2018.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Audited Profit loss Statement 2017.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Audited Profit loss statement 2016.pdf-
Director's Report 2017 - 2018File: Auditor's Report 2018.pdf-
Director's Report 2016 - 2017File: Auditor's Report 2017.pdf-
Director's Report 2015 - 2016File: Auditor's Report 2016.pdf-
Cash Flow Statement 2017 - 2018File: Cash Ffow 2018.pdf-
Cash Flow Statement 2016 - 2017File: Cash flow 2017.pdf-
Auditor's Report 2017 - 2018File: Auditor's Report 2018.pdf-
Auditor's Report 2016 - 2017File: Auditor's Report 2017.pdf-
Auditor's Report 2015 - 2016File: Auditor's Report 2016.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR 2018.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR 2017.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 2016.pdf-
Declaration Form B-
Prospectus/BrochureFile: KRRISH ROYAL BROUCHER.pdf-
Advertisement Copy 1File: ADD KRRISH ROYAL.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1249_447_PR_191015_002921 (5).xlsx-
Change in inventory/specification detailsFile: INVENTORY LIST.pdf-
Stability CertificateFile: Stability Certificate.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: Development Charges.pdf-
Consent for operation issued by KSPCBFile: KSPCB.pdf-
Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: Handing Over Certificate Krrish Royal.pdf-
Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: Hescom Krrish royal.pdf-
Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: water supply and drainage line.pdf-
Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: YES.pdf-
Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: YES.pdf-
Details of undivided share of land handed over to the association of allotteesFile: YES.pdf-
Architect certificate for having completed the work(in format no 5)File: Architect Certificate Completion Krrish royal.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: CA form completion krrish royal.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: affidavit krrish royal.pdf-
occupancy certifiateFile: Occupancy certificate.pdf-

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
KRRISH VIHAR-Completed-No date filed
KRRISH PRIDE-Completed-No date filed
KRRISH NEST 'B' WING-Completed-No date filed
KRRISH NEST 'A' WING-Completed-No date filed

How this compares with Belagavi

24%of Belagavi projects moved their completion datethis one moved by 9 months
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep KRRISH ROYAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

Builder: GOPALRAO

GOPALRAO has 1 registration on RERA Karnataka, including KRRISH ROYAL. Its filings declare 4 earlier projects, 4 of them declared completed. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if KRRISH ROYAL is delayed beyond 9 Apr 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of KRRISH ROYAL?

The registered promoter entity is GOPALRAO. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in KRRISH ROYAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KRRISH ROYAL?

The professionals named in the filing: Architect: GOPALRAO T. KUKDOLKAR; Engineer: VINAY BEHERE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRRISH ROYAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRRISH ROYAL. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRRISH ROYAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.