Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2026Possession promisedno revision filed
4 of 17Construction stages donefurthest along: Electrification, 97%
0 of 68Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 221 documents Report an error

KRK URBAN VILLE is a Residential/Group Housing project by KRK HOUSING PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/311022/005387 on 31 Oct 2022. Possession is promised by 30 Aug 2026. 156 of the 68 units on this registration are recorded sold or booked, and 4 of 17 construction stages are filed complete.

At a glance

Project

  • NameKRK URBAN VILLE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/311022/005387
  • ReraGenie IDRG-KA-11730

Builder

  • NameKRK HOUSING PRIVATE LIMITED
  • Entity typeCompany
  • CINU70109KA2022PTC159671
  • GSTIN29AAJCK4379G1Z1
  • Authorized SignatoryK. RAGHUNATH
  • DirectorsK. RAGHUNATH, K.RAGHUNATH, KANYA RAGHUNATH
  • Project HeadK.RAGHUNATH

Key dates

this monthRegisteredOct 2022PromisedAug 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on31 Oct 2022
  • Promised completion30 Aug 2026
  • Revised completionNone
  • Buildings67 building records
  • Documents filed221 files

Current status

229%156 of 68 units booked
85.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tulip 1---404
Tulip 2---404
Tulip 3---404
Tulip 4---404
Tulip 5---404
Tulip 6---404
Tulip 7---404
Tulip 8---404
Tulip 9---404
Tulip 10---404
Tulip 11---404
Tulip 12---404
Lily 1---404
Lily 2---404
Lily 3---404
Lily 4---404
Lily 5---404
Lily 6---404
Lily 7---404
Lily 8---404
Lily 9---404
Lily 10---404
Lily 11---404
Lily 12---404
Tulip 13---404
Tulip 14---404
Tulip 15---404
Tulip 16---404
Tulip 17---404
Tulip 18---404
Tulip 19---404
Tulip 20---404
Tulip 21---404
Tulip 22---404
Tulip 23---404
Tulip 24---404
Lily 13---404
Lily 14---404
Lily 15---404
Lily 16---404
Lily 17---404
Lily 18---404
Lily 19---404
Lily 20---404
Lily 21---404
Lily 22---404
Lily 23---404
Tulip 25---404
Tulip 26---404
Tulip 27---404
Tulip 28---404
Tulip 29---404
Tulip 30---404
Tulip 31---404
Tulip 32---404
Tulip 33---404
Tulip 34---404
Lily 24---404
Lily 25---404
Lily 26---404
Lily 27---404
Lily 28---404
Lily 29---404
Lily 30---404
Lily 31---404
Lily 32---404
Lily 33---404

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 17 construction stages are filed complete. The stage furthest along is Electrification, at 97%.

Building: 85% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)80%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction85%
Plastering inside , outside & Ceiling80%
Joinery: Doors, Windows, Ventilators etc80%
Basic work of Water supply, Sanitary and Electrification70%
Dadoing, Skirting, Flooring, Tiles work (All types)60%
Railing and Grill fixing50%
Electrification, Water supply and Sanitary Finishing97%
Painting95%
Fire prevention and fire fighting fitting and fixture with network95%
Weather Proof work(tile,concrete)85%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work85%
Internal and External work including landscapes as per sanctioned drawings85%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes95%
Water conservation/rain water harvesting/recharge of ground waterYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes90%
Solid waste management and disposalYes90%
Emergency Evacuation servicesYes90%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes90%
Storm water drainsYes90%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes90%
Parks & Tree plantingYes100%
Street LightingYes90%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes95%
Club HouseYes95%
Community HallNoNot applicable
Outdoor Sports facilityYes90%
Indoor Sports facilityYes90%
Swimming PoolYes90%
GymYes90%
ParksYes100%
Power BackupYes95%
Piped GasNoNot applicable
Water and SanitationYes95%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesYes95%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes100%
Outer WallNoNot applicable
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes95%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,860 sq m
Named landowners1
LandownerVillageDistrict
K. RAGHUNATH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 62.90 cr
Cost incurredRs 53.47 cr
Spent of the estimate85.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 42.00 crRs 35.70 cr
Administrative costRs 13.00 crRs 11.05 cr
Payment of taxesRs 7.50 crRs 6.38 cr
On-site expenditure-Consultants FeesRs 40.00 lakhRs 34.00 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARSHA. K
EngineerS LAKSHMIKANTHA
Chartered AccountantSuresh Babu N

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed221

As listed on the registration, under the names the promoter filed them with; the newest 80 of 221 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/311022/005387 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: KRK RERA CA CERT Sep 26.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: KRK ENGINEER Sep 26.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: KRK ENGINEER Sep 26.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
NOC RENEWAL CLARIFICATION AFFIDAVITFile: Noc clarification affidavit.pdf30 Sep 2026
ENGINEER SELF ATTESTED LICENSE COPYFile: UNO ENGR LICENSE CERT SELF ATT.pdf15 Sep 2026
APARTMENT PLANFile: Apartment plan.pdf15 Sep 2026
SOLD UNITS DETAILSFile: sold units details.pdf15 Sep 2026
UNSOLD UNITS DETAILSFile: unsold units details.pdf15 Sep 2026
FORM B AFFIDAVITFile: Form B affidavit KRK.pdf15 Sep 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: KRK RERA CA CERT June 26.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: KRK ENGINEER June 26.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: KRK ENGINEER June 26.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: KRK RERA CA CERT Mar 26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Engineer Certificate KRK Q4.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate KRK Q4.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: KRK RERA CA CERT Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: KRK ENGINEER Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: KRK ENGINEER Dec 25.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Registered GPAFile: GPA_compressed (1).pdf21 Oct 2022
JD AffidavitFile: JD affidavit.pdf21 Oct 2022
Non litigation affidavitFile: No Litigation Affidavit to RERA.pdf21 Oct 2022
balcony area detailsFile: Balcony area mentioned in the project details page not matching with the sanction plan cla21 Oct 2022
cdp map revisedFile: CDP MAP REVISED.pdf21 Oct 2022
total area clarificationFile: Total area mentioned in the Area details page not matching with the sanction plan clarify.21 Oct 2022
bwssb nocFile: BWSSB NOC.pdf21 Oct 2022
kspcb nocFile: KSPCB NOC.pdf21 Oct 2022
bescom nocFile: bescom noc.pdf21 Oct 2022
development planFile: Development plan.PDF21 Oct 2022
elevation planFile: elevation1.pdf21 Oct 2022
elevation plan 1File: elevation2.pdf21 Oct 2022
elevation plan 2File: elevation3.pdf21 Oct 2022
work orderFile: Work order.pdf21 Oct 2022
typicl planFile: Typicl plan.PDF21 Oct 2022
demarked planFile: Demarked plan.pdf21 Oct 2022
KRK OC Phase 1File: KRK-UV-OCCUPANCY CERTIFICATE phase 1.pdf21 Oct 2022
Relinquishment deedFile: RELINQUISHMENT DEED.pdf21 Oct 2022
noc renewal clarification letterFile: renewal clarification letter.pdf21 Oct 2022
stpFile: KRK Urban ville-STP.pdf21 Oct 2022
sanctioned plan demarcationFile: sanctioned plan demacation.pdf21 Oct 2022
CDP MAPFile: CDP Map.PDF21 Oct 2022
TITLE DEEDFile: KRK UV-SY-NO-9&11-2-GIFT DEED-K RAGHUANTH.PDF14 Aug 2022
TITLE DEED 1File: TITLE DEED SY-9-DOCUMENT NO - 6773.pdf14 Aug 2022
TITLE DEED 2File: TITLE DEED SY-11-2-DOCUMENT NO-6774.pdf14 Aug 2022
CLARIFICATIONFile: Revenue clarification.pdf14 Aug 2022
TOTAL AREA CLARIFICATIONFile: Total area mentioned in the Area details page not matching with the sanction plan clarify.14 Aug 2022
cc clarificationFile: CC.pdf14 Aug 2022
cdpFile: CDP Map.pdf14 Aug 2022
take over agreementFile: KRK-Takeover agreement.pdf14 Aug 2022
nocFile: KSPCB NOC.pdf14 Aug 2022
receiptFile: KSPCB NOC Fee receipt.pdf14 Aug 2022
BWSSB NOCFile: BWSSB NOC.pdf14 Aug 2022
BESCOM NOCFile: bescom noc.pdf14 Aug 2022
Guidance valueFile: guidance value certificate_compressed.pdf14 Aug 2022
parking detailsFile: Two wheelers parking details.pdf14 Aug 2022
demark planFile: Demarked plan.pdf14 Aug 2022
clarification letterFile: POINT NO-06 Clarification Letter to RERA.pdf14 Aug 2022
work orderFile: Work order.pdf14 Aug 2022
all plan 1File: 02.PDF14 Aug 2022
all plan 2File: 01.PDF14 Aug 2022
mapFile: Map.pdf14 Aug 2022
elevation plan 1File: elevation1.pdf14 Aug 2022
elevation plan 2File: elevation2.pdf14 Aug 2022
elevation plan 3File: elevation3.pdf14 Aug 2022
typical planFile: Typicl plan.PDF14 Aug 2022
demarcation planFile: sanctioned plan demacation.pdf14 Aug 2022
revised CDP mapFile: CDP MAP REVISED.pdf14 Aug 2022
Clarification letterFile: Balcony area mentioned in the project details page not matching with the sanction plan cla14 Aug 2022
AOS as per RERAFile: Agreement of Sale Proforma as per RERA.pdf21 Jul 2022

How this compares with Bengaluru Urban

229%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep KRK URBAN VILLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmKRK URBAN VILLEOther 83Dot size: filed unitsN

Filed coordinates, straight-line distance. 83 registered projects within 2 km.

Builder: KRK HOUSING PRIVATE LIMITED

KRK HOUSING PRIVATE LIMITED has 1 registration on RERA Karnataka, including KRK URBAN VILLE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if KRK URBAN VILLE is delayed beyond 30 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of KRK URBAN VILLE?

The registered promoter entity is KRK HOUSING PRIVATE LIMITED, a company as per the filing. Its CIN U70109KA2022PTC159671 and GSTIN 29AAJCK4379G1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in KRK URBAN VILLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KRK URBAN VILLE?

The professionals named in the filing: Architect: HARSHA. K; Engineer: S LAKSHMIKANTHA; Chartered Accountant: Suresh Babu N. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRK URBAN VILLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRK URBAN VILLE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRK URBAN VILLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.