ReraGenieLog inGet a buyer report

Home / Browse projects / Surat, Gujarat / KRISHNA RESIDENCY

Valid until 31 Dec 2028 Plotted Development project

KRISHNA RESIDENCY

By RADHEVILLA CO OPERATIVE HOUSING SOCIETYLIMITED

RG-GJ-34052 · RERA PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/PAA16744/230426/311228 · Last updated on GujRERA portal: 23 Apr 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2028Possession promisedno revision filed
0 of 9Construction stages donefurthest along: Excavation, 0%
196 of 196Units unsoldnot recorded sold or booked
Jump to the 26 documents Report an error

KRISHNA RESIDENCY is a Plotted Development project by RADHEVILLA CO OPERATIVE HOUSING SOCIETYLIMITED in Surat, Gujarat, registered with GujRERA as PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/PAA16744/230426/311228 on 23 Apr 2026. Possession is promised by 31 Dec 2028. 0 of the 196 units on this registration are recorded sold or booked, and 0 of 9 construction stages are filed complete.

At a glance

Project

  • NameKRISHNA RESIDENCY
  • TypePlotted Development
  • Location
    • BLOCK NO - 484
    • MOJE : - BONAND
    • TA-CHORYASI
    • DIST.-SURAT
    • BONAND
    • Surat City
    • Surat
    • 394230
  • Pincode394230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/PAA16744/230426/311228
  • ReraGenie IDRG-GJ-34052

Builder

  • NameRADHEVILLA CO OPERATIVE HOUSING SOCIETYLIMITED
  • Entity typeAOP

Key dates

this monthRegisteredApr 2026PromisedDec 2028

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2028
  • Registered on23 Apr 2026
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed26 files

Current status

0%0 of 196 units booked

Figures as on 23 Apr 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OPEN PLOT (TOTAL 196 UNIT)---00196

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 23 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 9 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

OPEN PLOT (TOTAL 196 UNIT): 0% average across the applicable activities

ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 23 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,812 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPankajkumar Shambhunath Vishvakarma
EngineerSANJAY BIHARILAL PANJWANI

Documents filed26

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/SURAT/SURAT CITY/Surat Urban Development Authority/PAA16744/230426/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate23 Apr 2026
Accountant's certificate (Form 3)10 Apr 2026
Architect's certificate (Form 1)30 Mar 2026
Engineer's certificate (Form 2)30 Mar 2026
Engineer's certificate annexure30 Mar 2026
Site photograph, OPEN PLOT (TOTAL 196 UNIT)30 Mar 2026
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Proforma sale deed-
Project photograph-

How this compares with Surat

0%of this project is bookeddistrict median 39%
15%of Surat projects moved their completion datethis one has not

Computed across the 2,600+ Surat projects on ReraGenie, from their own filings.

Keep KRISHNA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near BONAND2,600+ in Surat

2 kmKRISHNA RESIDENCYOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: RADHEVILLA CO OPERATIVE HOUSING SOCIETYLIMITED

RADHEVILLA CO OPERATIVE HOUSING SOCIETYLIMITED has 1 registration on GujRERA, including KRISHNA RESIDENCY. Read the full track record. See more projects on the Surat district page.

Frequently asked questions

What are my rights if KRISHNA RESIDENCY is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of KRISHNA RESIDENCY?

The registered promoter entity is RADHEVILLA CO OPERATIVE HOUSING SOCIETYLIMITED, an aop as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in KRISHNA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KRISHNA RESIDENCY?

The professionals named in the filing: Architect: Pankajkumar Shambhunath Vishvakarma; Engineer: SANJAY BIHARILAL PANJWANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KRISHNA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KRISHNA RESIDENCY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KRISHNA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.