Home / Browse projects / Vadodara, Gujarat / KRISHNA MERIDIAN
KRISHNA MERIDIAN
RG-GJ-65266 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA02380/EX1/160320 · Last updated on GujRERA portal: 20 Sep 2021
Source: official GujRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- Nothing verified clear yet
Saved.
KRISHNA MERIDIAN is a Mixed Development project by KRISHNA INFRASTRUCTURE in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA02380/EX1/160320 on 16 Apr 2018. Possession is promised by 31 Mar 2021. The completion date has moved by 12 months from the original filing. 116 of the 149 units on this registration are recorded sold or booked, and 48 of 48 construction stages are filed complete.
At a glance
Project
- NameKRISHNA MERIDIAN
- TypeMixed Development
- Location
- KRISHNA MERIDIAN
- BESIDE SIDDHESHWAR KRISHNA
- NR. IIRA INTERNATIONAL SCHOOL
- 30 MTR CANAL ROAD
- BHAYALI
- Bhayali
- Vadodara
- 391410
- Pincode391410
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA02380/EX1/160320
- ReraGenie IDRG-GJ-65266
Builder
- NameKRISHNA INFRASTRUCTURE
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Mar 2021
- Registered on16 Apr 2018
- Promised completion31 Mar 2021
- Revised completionRevised to 31 Mar 2021 (originally 31 Mar 2020)
- Buildings6 building records
- Documents filed43 files
Current status
Figures as on 20 Sep 2021, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower A | - | - | - | 20 | 0 | 20 |
| Tower B | - | - | - | 20 | 0 | 20 |
| Tower C | - | - | - | 20 | 0 | 20 |
| Tower D | - | - | - | 20 | 0 | 20 |
| Tower E | - | - | - | 20 | 0 | 20 |
| Tower F | - | - | - | 0 | 49 | 49 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building6
As on 20 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
48 of 48 construction stages are filed complete across 6 buildings.
Tower A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Tower F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 20 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | Yes | 100% |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tower A | NA | Rs 1.94 cr | Rs 1.69 cr |
| Tower B | NA | Rs 1.94 cr | Rs 1.69 cr |
| Tower C | NA | Rs 1.94 cr | Rs 1.69 cr |
| Tower D | NA | Rs 1.94 cr | Rs 1.69 cr |
| Tower E | NA | Rs 1.94 cr | Rs 1.69 cr |
| Tower F | NA | Rs 1.94 cr | Rs 1.69 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARPIT PATEL |
| Engineer | ZARNA ASSOCIATES |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed43
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA02380/EX1/160320 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 20 Sep 2021 |
| Engineer's certificate (Form 2) | 20 Sep 2021 |
| Engineer's certificate annexure | 20 Sep 2021 |
| Accountant's certificate (Form 3) | 20 Sep 2021 |
| Site photograph, Tower A | 20 Sep 2021 |
| Site photograph, Tower B | 20 Sep 2021 |
| Site photograph, Tower C | 20 Sep 2021 |
| Site photograph, Tower D | 20 Sep 2021 |
| Site photograph, Tower E | 20 Sep 2021 |
| Site photograph, Tower F | 20 Sep 2021 |
| RERA registration certificate | 16 Apr 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep KRISHNA MERIDIAN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bhayali2,900+ in Vadodara
Filed coordinates, straight-line distance. 307 registered projects within 2 km.
SAMANVAY STATUS 2
Status Realty
PMAY BILL 532 EWS-II FP 38
VADODARA URBAN DEVELOPMENT AUTHORITY
THE MARK
SHREE GANESH DEVLOPERS
ANANTA SAVERA SWAGATAM
S S INFRA
PMAY BHAYLI 392 EWS-II FP 114
VADODARA URBAN DEVELOPMENT AUTHORITY
PMAY BHAYLI 360 EWS-I FP 100
VADODARA URBAN DEVELOPMENT AUTHORITY
See every Vadodara project, with the district possession charts
Builder: KRISHNA INFRASTRUCTURE
KRISHNA INFRASTRUCTURE has 2 registrations on GujRERA, including KRISHNA MERIDIAN and CROWN-140. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if KRISHNA MERIDIAN is delayed beyond 31 Mar 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of KRISHNA MERIDIAN?
The registered promoter entity is KRISHNA INFRASTRUCTURE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in KRISHNA MERIDIAN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at KRISHNA MERIDIAN?
The professionals named in the filing: Architect: ARPIT PATEL; Engineer: ZARNA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KRISHNA MERIDIAN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.