ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / KISHAN 26

Valid until 3 Dec 2026 Residential/Group Housing project

KISHAN 26

By HIYA DEVELOPERS

RG-GJ-40667 · RERA PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN327AA10227/EX1/111225/031226 · Last updated on GujRERA portal: 31 Jul 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Dec 2026Possession promisedmoved 12 months from the original
9 of 9Construction stages doneevery applicable stage filed complete
1 of 26Units unsoldnot recorded sold or booked
Jump to the 34 documents Report an error

KISHAN 26 is a Residential/Group Housing project by HIYA DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN327AA10227/EX1/111225/031226 on 24 Mar 2023. Possession is promised by 3 Dec 2026. The completion date has moved by 12 months from the original filing. 25 of the 26 units on this registration are recorded sold or booked, and 9 of 9 construction stages are filed complete.

At a glance

Project

  • NameKISHAN 26
  • TypeResidential/Group Housing
  • Location
    • Kishan 26
    • RS No 555
    • BehindPushpam Home
    • Village Bill
    • Bill Atladara Road
    • Vadodara
    • BIL
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN327AA10227/EX1/111225/031226
  • ReraGenie IDRG-GJ-40667

Builder

  • NameHIYA DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusValid until 3 Dec 2026
  • Registered on24 Mar 2023
  • Promised completion3 Dec 2026
  • Revised completionRevised to 3 Dec 2026 (originally 4 Dec 2025)
  • Buildings1 building record
  • Documents filed34 files

Current status

96%25 of 26 units booked
57.1%Of the estimated cost spent so far

Figures as on 31 Jul 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---26026

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 9 construction stages are filed complete.

A: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area728 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.16 cr
Cost incurredRs 2.38 cr
Spent of the estimate57.12%
BuildingWingEstimatedIncurred
ANARs 4.16 crRs 2.38 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCharmi Hardik Pandya
EngineerTARANG KARSHANBHAI GALANI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN327AA10227/EX1/111225/031226Applied Nov 2025; approved Dec 2025

Documents filed34

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Vadodara Municipal Corporation/RN327AA10227/EX1/111225/031226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)31 Jul 2026
Engineer's certificate annexure31 Jul 2026
Accountant's certificate (Form 3)31 Jul 2026
Architect's certificate (Form 1)30 Jul 2026
Site photograph, A30 Jul 2026
RERA registration certificate24 Mar 2023
Extension certificate-
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Proforma sale deed-
Project photograph-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

96%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep KISHAN 26 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near BIL2,900+ in Vadodara

2 kmKISHAN 26Other 233Dot size: filed unitsN

Filed coordinates, straight-line distance. 233 registered projects within 2 km.

Builder: HIYA DEVELOPERS

HIYA DEVELOPERS has 1 registration on GujRERA, including KISHAN 26. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if KISHAN 26 is delayed beyond 3 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of KISHAN 26?

The registered promoter entity is HIYA DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in KISHAN 26?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KISHAN 26?

The professionals named in the filing: Architect: Charmi Hardik Pandya; Engineer: TARANG KARSHANBHAI GALANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KISHAN 26?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KISHAN 26. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KISHAN 26 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.