Home / Browse projects / Gandhinagar, Gujarat / KANTAM GREENS

Valid until 30 Jun 2025 Residential/Group Housing project

KANTAM GREENS

By KANTAM INFRASTRUCTURE

RG-GJ-60585 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA05708/150719 · Last updated on GujRERA portal: 24 Aug 2023

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Jun 2025Possession promisedno revision filed
7 of 7Construction stages doneevery applicable stage filed complete
17 of 100Units unsoldnot recorded sold or booked
Jump to the 49 documents Report an error

KANTAM GREENS is a Residential/Group Housing project by KANTAM INFRASTRUCTURE in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA05708/150719 on 15 Jul 2019. Possession is promised by 30 Jun 2025. 83 of the 100 units on this registration are recorded sold or booked, and 7 of 7 construction stages are filed complete.

At a glance

Project

  • NameKANTAM GREENS
  • TypeResidential/Group Housing
  • Location
    • KANTAM GREENS
    • OPP. JAGJIVAN SOCIETY
    • NR. OM RESIDENCY
    • ARSODIA
    • KALOL EAST
    • Arsodiya
    • Kalol
    • Gandhinagar
    • 382721
  • Pincode382721
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA05708/150719
  • ReraGenie IDRG-GJ-60585

Builder

  • NameKANTAM INFRASTRUCTURE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJul 2019PromisedJun 2025

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2025
  • Registered on15 Jul 2019
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed49 files

Current status

83%83 of 100 units booked
98.9%Of the estimated cost spent so far

Figures as on 24 Aug 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tenament---1000100

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 24 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 7 construction stages are filed complete.

Tenament: 100% average across the applicable activities

ActivityProgress
ExcavationNot applicable
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 24 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)NoNot applicable
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,545 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.00 cr
Cost incurredRs 8.90 cr
Spent of the estimate98.92%
BuildingWingEstimatedIncurred
TenamentNARs 9.00 crRs 8.90 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHAUMIKKUMAR C. DONGA
EngineerNISHIL M SHAH

Documents filed49

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA05708/150719 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)24 Aug 2023
Engineer's certificate (Form 2)24 Aug 2023
Engineer's certificate annexure24 Aug 2023
Accountant's certificate (Form 3)24 Aug 2023
Site photograph, Tenament24 Aug 2023
Site photograph, Tenament24 Aug 2023
Site photograph, Tenament24 Aug 2023
Site photograph, Tenament24 Aug 2023
Site photograph, Tenament24 Aug 2023
Site photograph, Tenament24 Aug 2023
Site photograph, Tenament24 Aug 2023
Site photograph, Tenament24 Aug 2023
Site photograph, Tenament24 Aug 2023
RERA registration certificate15 Jul 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

83%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep KANTAM GREENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Arsodiya1,600+ in Gandhinagar

2 kmKANTAM GREENSOther 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: KANTAM INFRASTRUCTURE

KANTAM INFRASTRUCTURE has 1 registration on GujRERA, including KANTAM GREENS. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if KANTAM GREENS is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of KANTAM GREENS?

The registered promoter entity is KANTAM INFRASTRUCTURE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in KANTAM GREENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at KANTAM GREENS?

The professionals named in the filing: Architect: BHAUMIKKUMAR C. DONGA; Engineer: NISHIL M SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KANTAM GREENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KANTAM GREENS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KANTAM GREENS to a free account