Registration approved Residential/Group Housing project

JYOTI ABHISHEK RESIDENCY

By BHASKAR RAMGOUNDA PATIL

RG-KA-74367 · RERA PRM/KA/RERA/1249/367/PR/200117/003184 · Last updated on RERA Karnataka portal: 7 Jan 2020

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2023Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 38 documents Report an error

JYOTI ABHISHEK RESIDENCY is a Residential/Group Housing project by BHASKAR RAMGOUNDA PATIL in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/367/PR/200117/003184 on 17 Jan 2020. Possession is promised by 31 Dec 2023. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameJYOTI ABHISHEK RESIDENCY
  • TypeResidential/Group Housing
  • Location
    • Chikkodi
    • Belagavi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1249/367/PR/200117/003184
  • ReraGenie IDRG-KA-74367

Builder

  • NameBHASKAR RAMGOUNDA PATIL
  • Declared earlier projects2 →

Key dates

this monthRegisteredJan 2020First promiseMar 2023Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Jan 2020
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Mar 2023)
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Jyoti Abhishek Residency---10010

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 7 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 7 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,208 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 1.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGEETHANJALI SHINE
EngineerSUNIL A DESAI

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2023 → Dec 2023

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/367/PR/200117/003184 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
COPY OF RENTAL AGREEMENTFile: Nippani RERA Document.pdf7 Jan 2020
Local address Prof - Electricity BillFile: Bhaskar Patil Local Bank.jpg28 Dec 2019
Local Bank Account -Bugate Alur -Bank of IndiaFile: Bhaskar Patil Local Bank.jpg28 Dec 2019
buildingplamerged-
buildingplamerged-
buildingplamerged-
Allotment Letter-
Allotment Letter-
Sale deed-
Building Permission-
Allotment Letter-
BUILDING LICENSE-mergedfinal-
Project Specifications -
ECPAPER-
3(1)-
BHASKAR PATIL KHATA BOOK-
Plot No 26-
NA order-
SEARCH REPORT-
Balance Sheet 2018 - 2019File: Balance sheet 2018.pdf-
Balance Sheet 2017 - 2018File: Balance sheet 2017.pdf-
Balance Sheet 2016 - 2017File: Balance sheet 2016.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit and Loss 2018.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit and Loss 2017.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit and Loss 2016.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR acknowledgement 2018-19.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR acknowledgement 2017-18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR acknowledgement 2016-17.pdf-
Form B Affidavit-
Tower Excel SheetFile: PRM_KA_RERA_1249_367_PR_200117_003184.xlsx-
Loan raised documentFile: Houseno1merged.pdf-
Occupancy CertificateFile: Completion Certificate -1.pdf-
Architect certificate for having completed the work(in format no 5)File: ENGINEERFORMNO06.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: ArchitectCertificateFormNo05.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit.pdf-
Architect Certificate Form 5File: ArchitectCertificateFormNo05.pdf-
Occupancy Certifcate Payment challanFile: Occupancy Challan.pdf-
Release letter from Shree Beereshwar Co_Operative Credit society Nippani BranchFile: Houseno1merged.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
SILVER OAK PHASE 1-OngoingJun 2022Not delivered
KIRAN HEIGHTS-OngoingJan 2022Not delivered

How this compares with Belagavi

24%of Belagavi projects moved their completion datethis one moved by 9 months
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep JYOTI ABHISHEK RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

Builder: BHASKAR RAMGOUNDA PATIL

BHASKAR RAMGOUNDA PATIL has 1 registration on RERA Karnataka, including JYOTI ABHISHEK RESIDENCY. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if JYOTI ABHISHEK RESIDENCY is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JYOTI ABHISHEK RESIDENCY?

The registered promoter entity is BHASKAR RAMGOUNDA PATIL. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JYOTI ABHISHEK RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JYOTI ABHISHEK RESIDENCY?

The professionals named in the filing: Architect: GEETHANJALI SHINE; Engineer: SUNIL A DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JYOTI ABHISHEK RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JYOTI ABHISHEK RESIDENCY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JYOTI ABHISHEK RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.