JP LAVENDER BLOCK-A

By JP Housing Corporation

RG-KA-91709 · RERA PRM/KA/RERA/1250/304/PR/180524/006898 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
15 of 17Construction stages donefurthest along: Elevation work, 30%
43 of 76Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 141 documents Report an error

JP LAVENDER BLOCK-A is a Residential/Group Housing project by JP Housing Corporation in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/180524/006898 on 18 May 2024. Possession is promised by 31 Dec 2026. 33 of the 76 units on this registration are recorded sold or booked, and 15 of 17 construction stages are filed complete.

At a glance

Project

  • NameJP LAVENDER BLOCK-A
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 562114
  • Pincode562114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/180524/006898
  • ReraGenie IDRG-KA-91709

Builder

  • NameJP Housing Corporation
  • Entity typePartnership Firm
  • GSTIN29AAOFJ6743P1ZC
  • Authorized SignatoryJAYAPRASAD H.V
  • Other registrations4 more →

Key dates

this monthRegisteredMay 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 May 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed141 files

Current status

43%33 of 76 units booked
69.5%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---76076

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 17 construction stages are filed complete. The stage furthest along is Elevation work, at 30%.

Building: 90% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work30%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes80%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes80%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes70%
Electricity supply transformer and substationYes90%
Storm water drainsYes80%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes80%
Parks & Tree plantingYes75%
Street LightingYes80%
ElectricityYes80%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes90%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes80%
GymYes90%
ParksNoNot applicable
Power BackupYes40%
Piped GasNoNot applicable
Water and SanitationYes60%
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes80%
Corridor/LobbiesYes80%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes90%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes80%
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,704 sq m
Named landowners3
LandownerVillageDistrict
Chandramma--
Gitamma--
Gitamma--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.29 cr
Cost incurredRs 21.04 cr
Spent of the estimate69.47%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 30.29 crRs 21.04 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSathish Babu
EngineerMANIKONDA LAXMI NARASIMHA RAO
Chartered AccountantVenkatramana P

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed141

As listed on the registration, under the names the promoter filed them with; the newest 80 of 141 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/180524/006898 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4-Q2-2026-27.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM -5-Q2-2026-27.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 -Q2-2026-27.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4-Q1-2026-27.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM -5-Q1-2026-27.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 -Q1-2026-27.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM-4-Q4-2025-26.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM -5-Q4-2025-26.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 -Q4-2025-26.pdf13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM-4-Q3-2025-26.pdf20 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM -5-Q3-2025-26_compressed.pdf20 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 -Q3-2025-26.pdf20 Jan 2026
JP Housing Financials 2022-23File: 1 JP Housing Financials 2022-23.pdf17 May 2024
JP Housing Financials 2021-22File: 2 JP Housing Financials 2021-22.pdf17 May 2024
JP Housing Financials 2020-21File: 3 JP Housing Financials 2020-21.pdf17 May 2024
BANK AFFIDAVIT-BLOCK-AFile: 4 BANK AFFIDAVIT-BLOCK-A.pdf17 May 2024
SOURCES OF FUNDS with supporting docsFile: 5 SOURCES OF FUNDS with supporting docs.pdf17 May 2024
Clarification on previous projectsFile: 6 Clarification on previous projects.pdf17 May 2024
JP Tulips_OCFile: 7 JP Tulips_OC.pdf17 May 2024
CA membership cerficate-Self attestedFile: 15 CA membership cerficate-Self attested.pdf17 May 2024
NETWORTH-JAYAPRASADFile: 16 NETWORTH-JAYAPRASAD.pdf17 May 2024
NETWORTH-LAVANYAFile: 17 NETWORTH-LAVANYA.pdf17 May 2024
PROVISIONAL-2023-24File: 18 PROVISIONAL-2023-24.pdf17 May 2024
JAYAPRASAD-ITR FY-2022-23File: JAYAPRASAD-ITR FY-2022-23.pdf17 May 2024
JAYAPRASAD-ITR FY-2021-22File: JAYAPRASAD-ITR FY-2021-22.pdf17 May 2024
JAYAPRASAD-ITR FY-2020-21File: JAYAPRASAD-ITR FY-2020-21.pdf17 May 2024
LAVANYA-2022-23File: LAVANYA-2022-23.pdf17 May 2024
LAVANYA-2021-22File: LAVANYA-2021-22.pdf17 May 2024
LAVANYA-2020-21File: LAVANYA-2020-21.pdf17 May 2024
Single Plot OrderFile: 1 Single Plot Order.pdf17 May 2024
JP LAVENDER BLOCK-A-AREA STATEMENTFile: 2 JP LAVENDER BLOCK-A-AREA STATEMENT.pdf17 May 2024
VILLAGE MAP DemarcationFile: 3 VILLAGE MAP Demarcation.pdf17 May 2024
Clarification on Commencement CertificateFile: 4 Clarification on Commencement Certificate.pdf17 May 2024
HPA-Zonal Regulations-2031File: 5 HPA-Zonal Regulations-2031.pdf17 May 2024
BUILDING PLAN-2-76 UNITSFile: 6 BUILDING PLAN-2-76 UNITS.pdf17 May 2024
RELINQUSHMENT DEED-2File: 7 RELINQUSHMENT DEED-2.pdf17 May 2024
RTC, survey 288/5-
Mutation, survey 288/5-
Encumbrance Certificate, survey 288/5-
Conversion/Alienation Order, survey 288/5-
Sale/Title/Gift Deed, survey 288/5-
JDA, survey 288/5-
Khatha, survey 288/5-
RTC, survey 288/10-
Mutation, survey 288/10-
Encumbrance Certificate, survey 288/10-
Conversion/Alienation Order, survey 288/10-
Sale/Title/Gift Deed, survey 288/10-
JDA, survey 288/10-
Khatha, survey 288/10-
RTC, survey 288/11-
Mutation, survey 288/11-
Encumbrance Certificate, survey 288/11-
Conversion/Alienation Order, survey 288/11-
Sale/Title/Gift Deed, survey 288/11-
JDA, survey 288/11-
Khatha, survey 288/11-
Registration CertificateFile: Incorporation Certifcate.pdf-
Partnership DeedFile: PARTNERSHIP DEEED.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: FORM-1-CA Cert.pdf-
Certificate issued by Architect Form 2File: FORM-2-Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: FORM-3-Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for Non-Litigation Details- With JDA.pdf-
Certificate from Chartered AccountFile: FORM-1-CA Cert.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet 2022-23.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet 2021-22.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet 2021-22.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Profit and Loss 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit and Loss 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit and Loss 2021-22.pdf-
Cash Flow Statement 2022 - 2023File: Statement of Income 2022-23.pdf-

How this compares with Bengaluru Rural

43%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep JP LAVENDER BLOCK-A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmJP LAVENDER BLOCK-AOther 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: JP Housing Corporation

JP Housing Corporation has 5 registrations on RERA Karnataka, including JP LAVENDER BLOCK-B and JP LAVENDER BLOCK-A. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if JP LAVENDER BLOCK-A is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JP LAVENDER BLOCK-A?

The registered promoter entity is JP Housing Corporation, a partnership firm as per the filing. Its GSTIN 29AAOFJ6743P1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JP LAVENDER BLOCK-A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JP LAVENDER BLOCK-A?

The professionals named in the filing: Architect: Sathish Babu; Engineer: MANIKONDA LAXMI NARASIMHA RAO; Chartered Accountant: Venkatramana P. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JP LAVENDER BLOCK-A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JP LAVENDER BLOCK-A. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JP LAVENDER BLOCK-A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.