Home / Browse projects / Bengaluru Urban, Karnataka / JEEVAN'S ALLURE

Registration approved No litigation declared Residential/Group Housing project

JEEVAN'S ALLURE

By JEEVAN DEVELOPERS

RG-KA-54704 · RERA PRM/KA/RERA/1251/446/PR/070125/007354 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jul 2027Possession promisedno revision filed
7 of 16Construction stages donefurthest along: Weather Proof work(tile, 80%
103 of 152Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 144 documents Report an error

JEEVAN'S ALLURE is a Residential/Group Housing project by JEEVAN DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/070125/007354 on 7 Jan 2025. Possession is promised by 31 Jul 2027. 49 of the 152 units on this registration are recorded sold or booked, and 7 of 16 construction stages are filed complete.

At a glance

Project

  • NameJEEVAN'S ALLURE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/070125/007354
  • ReraGenie IDRG-KA-54704

Builder

  • NameJEEVAN DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29AANFJ6615K1ZS
  • Authorized SignatoryREPALA SRINIVAS
  • Other registrations1 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredJan 2025PromisedJul 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Jan 2025
  • Promised completion31 Jul 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed144 files

Current status

32%49 of 152 units booked
85.1%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ALLURE---1520152

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 16 construction stages are filed complete. The stage furthest along is Weather Proof work(tile, at 80%.

Building: 75% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc30%
Basic work of Water supply, Sanitary and Electrification75%
Dadoing, Skirting, Flooring, Tiles work (All types)75%
Railing and Grill fixing75%
Electrification, Water supply and Sanitary Finishing30%
Painting60%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)80%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work80%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes50%
Sewage and Drainage SystemYes50%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes30%
Parks & Tree plantingYes0%
Street LightingYes10%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes50%
Corridor/LobbiesYes80%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes70%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership12

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,488 sq m
Named landowners12
LandownerVillageDistrict
N M VENKATESH REDDY--
V PRADEEP--
V PRASHANTH--
V PRATHAP--
N M VENKATESH REDDY--
V PRADEEP--
V PRASHANTH--
V PRATHAP--
N M VENKATESH REDDY--
V PRADEEP--
V PRASHANTH--
V PRATHAP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 41.30 cr
Cost incurredRs 35.14 cr
Spent of the estimate85.09%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 32.00 crRs 29.57 cr
Payment of taxesRs 6.00 crRs 95.61 lakh
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.25 crRs 2.70 cr
On-site expenditure-Site OverheadRs 1.00 crRs 10.81 lakh
On-site expenditure-Consultants FeesRs 55.00 lakhRs 21.20 lakh
On-site expenditure-Salaries of workersRs 25.00 lakhRs 1.50 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 25.00 lakhRs 10.00 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB V NARENDRANATH REDDY
EngineerMADAMANCHI SURENDRA NADH
Chartered AccountantSRIKANTH PAYYAVULA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed144

As listed on the registration, under the names the promoter filed them with; the newest 80 of 144 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/070125/007354 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 JEEVANS ALLURE Q2_compressed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect_Q2_13OCT2026(SEP2026).pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: HO 1117 Form 6 -14-Oct-2026.pdf15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q1 26-27_compressed.pdf11 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5, Architect_Q1_08JUL2026(JUN2026).pdf11 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: HO 1117 Form 6 -08-July-2026.pdf11 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)11 Jul 2026
Q1 2026-27 KPTCL- BESCOM11 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Q4 25-26 (1).pdf10 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect_Q4_16APR2026(MAR2026)_compressed.pdf10 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Jeevan's Allure Form 06 16-04-2026.pdf10 Jul 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)10 Jul 2026
Q4 2025-26 KPTCL- BESCOM10 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Allure (1).pdf2 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect_Q3_31JAN(DEC2025).pdf2 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Jeevan's Allure - Form 06 - Engineer's Certificate 31-01-2026.pdf2 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)2 Feb 2026
Q3 2025-26 KPTCL- BESCOM2 Feb 2026
Title deeds of current land ownersFile: 1 Title deeds of current land owners.pdf18 Dec 2024
JDA DocumentFile: 1 JDA Document.pdf18 Dec 2024
C O Sy no 121-6File: 1 C O Sy no 121-6.pdf18 Dec 2024
C O Sy no 121-9File: 1 C O Sy no 121-9.pdf18 Dec 2024
C O Sy no 121-11File: 1 C O Sy no 121-11.pdf18 Dec 2024
CDP Map with CLUFile: 3 CDP Map with CLU.pdf18 Dec 2024
zoning regulationFile: 4 zoning regulation.pdf18 Dec 2024
Village mapFile: 5 Village map.pdf18 Dec 2024
ADLR SKETCHFile: 7 ADLR SKETCH.pdf18 Dec 2024
Demand note and Court Stay orderFile: 9 Demand note and Court Stay order.pdf18 Dec 2024
Query Answers 16-12-2024File: Query 16-12-2024.pdf18 Dec 2024
Quarterly Update Details June 24File: 1 Quarterly Update Details June 24.pdf18 Nov 2024
Quarterly Update Details Sep 24File: 1 Quarterly Update Details Sep 24.pdf18 Nov 2024
Balance Sheet 2023-24File: 2 Balance Sheet 2023-24.pdf18 Nov 2024
ITR 2024-25File: 2 ITR 2024-25.pdf18 Nov 2024
Profit and loss 2023-24File: 2 Profit and loss 2023-24.pdf18 Nov 2024
S of F with Supportive documentsFile: 3 S of F with Supportive documents.pdf18 Nov 2024
Title deeds of current land ownersFile: 4 Title deeds of current land owners.pdf18 Nov 2024
CDP Map with CLUFile: 6 CDP Map with CLU.pdf18 Nov 2024
zoning regulationFile: 7 zoning regulation.pdf18 Nov 2024
Village MapFile: 8 Village Map.pdf18 Nov 2024
Demand note and Court Stay orderFile: 11 Demand note and Court Stay order.pdf18 Nov 2024
FORM B AFFIDAVITFile: 10 FORM B AFFIDAVIT.pdf18 Nov 2024
1.the profit and loss account, balance sheet, and ITR for 2020-21, 2021-22 & 2022-23 with scheduleFile: Financials 202021.pdf19 Oct 2024
2.the profit and loss account, balance sheet, and ITR for 2020-21, 2021-22 & 2022-23 with scheduleFile: Financials 202122.pdf19 Oct 2024
3.the profit and loss account, balance sheet, and ITR for 2020-21, 2021-22 & 2022-23 with scheduleFile: Financials 202223.pdf19 Oct 2024
4.title deed of the current land owner as per latest transaction for all 3 snos in the project forFile: Title deed of Current landowner.pdf19 Oct 2024
5.Building Commencement CertificateFile: CC.pdf19 Oct 2024
8.Extract of Master Plan with consent authority seal and signatureFile: BBMP Sanctioned Plan.pdf19 Oct 2024
10.Village map marking the proposed siteFile: Will Be Upload soon.pdf19 Oct 2024
13.NOC issued by BWSSB along with the copy of the fee receipt paid towards the NOC.File: Will Be Upload soon.pdf19 Oct 2024
14. the land calculation sheet. Please upload the Land cost calculation sheet as per the guidance vaFile: Land cost calculation sheet as per the guidance va.pdf19 Oct 2024
16. the proforma of the Allotment letter.File: Allotment Letter Allure RERA.pdf19 Oct 2024
1. GST CertificateFile: GST Certificate - Jeevan Developers.pdf14 Sep 2024
2. Brief estimated cost of construction certified by the EngineerFile: Engineer Certification - allure.pdf14 Sep 2024
3. ADLR Survey SketchFile: ADLR SKETCH.pdf14 Sep 2024
4. Village Map.File: Village Map.pdf14 Sep 2024
5.Certificate of registration of partnership firmFile: CRC.jpeg14 Sep 2024
6.KSPCB NOCFile: PCB NOC ALLURE.pdf14 Sep 2024
7. BWSSB NOCFile: Will Be Upload soon.pdf14 Sep 2024
10.Amenities and Common area detailsFile: AMENITITES DETAILS.pdf14 Sep 2024
12.Latest self attested copy of the Engineer license certificateFile: BBMP - Certificate.pdf14 Sep 2024
13. Building Commencement Certificate.File: CC.pdf14 Sep 2024
14.Land cost calculation sheet as per the guidance valueFile: Land cost Calculation Guidance Value.pdf14 Sep 2024
15.title deed of the current land ownerFile: Title deed of Current landowner.pdf14 Sep 2024
16.connected MR in favuor of landowner before conversionFile: Connected MR.pdf14 Sep 2024
17.partner's KYC with self-attested.File: Partners KYC.pdf14 Sep 2024
18.CA's KYCFile: CA KYC.pdf14 Sep 2024
19.sources of funds to complete the projectFile: Source of Fund.pdf14 Sep 2024
20.project specification certified by the EngineerFile: Specifications.pdf14 Sep 2024
21.STP DRAWINGFile: STP JEEVAN DEVELOPERS.pdf14 Sep 2024
22.Building plan Blue print in readable formatFile: Building Plan.pdf14 Sep 2024
23. Each floor plan and section planFile: Each Floor plan and Section Plan.pdf14 Sep 2024
24. Financials 2020-21File: Financials 2020-21.pdf14 Sep 2024
24. Financials 2021-22File: Financials 2021-22.pdf14 Sep 2024
24. Financials 2022-23File: Financials 2022-23.pdf14 Sep 2024
25.The source of water supply to the projectFile: Bore Point.jpeg14 Sep 2024
26.proforma of the Allotment letter in the prescribed formatFile: Allotment Letter Allure RERA.pdf14 Sep 2024
28.Extract of Master Plan.File: BBMP Sanctioned Plan.pdf14 Sep 2024
RTC, survey 121/6-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
JEEVANS OCTAVE LitigationSY NO 95/3, 95/4,95/5,95/12,95/13 , CHAIITANYA ANANAYA ROAD ,SEEGEHALLI , KADUGODIOngoingJun 2025Not delivered
JEEVAN'S PRISTINESy.No.79/2. Munnekolala Village, Marathahalli BANGALORECompleted-No date filed

How this compares with Bengaluru Urban

32%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep JEEVAN'S ALLURE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmJEEVAN'S ALLUREOther 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: JEEVAN DEVELOPERS

JEEVAN DEVELOPERS has 2 registrations on RERA Karnataka, including JEEVAN'S ALLURE and Jeevans Octave. Its filings declare 3 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if JEEVAN'S ALLURE is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JEEVAN'S ALLURE?

The registered promoter entity is JEEVAN DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AANFJ6615K1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JEEVAN'S ALLURE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JEEVAN'S ALLURE?

The professionals named in the filing: Architect: B V NARENDRANATH REDDY; Engineer: MADAMANCHI SURENDRA NADH; Chartered Accountant: SRIKANTH PAYYAVULA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JEEVAN'S ALLURE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JEEVAN'S ALLURE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JEEVAN'S ALLURE to a free account