Home / Browse projects / Belagavi, Karnataka / JAMBAGI SQUARE

Registration approved Mixed Development project

JAMBAGI SQUARE

By Dr Varsha Laxman Jambagi

RG-KA-26482 · RERA PRM/KA/RERA/1249/447/PR/220221/004716 · Last updated on RERA Karnataka portal: 16 Feb 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 68 documents Report an error

JAMBAGI SQUARE is a Mixed Development project by Dr Varsha Laxman Jambagi in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/220221/004716 on 21 Feb 2022. Possession is promised by 31 Dec 2023.

At a glance

Project

  • NameJAMBAGI SQUARE
  • TypeMixed Development
  • Location
    • Belagavi
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1249/447/PR/220221/004716
  • ReraGenie IDRG-KA-26482

Builder

  • NameDr Varsha Laxman Jambagi

Key dates

this monthRegisteredFeb 2022PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Feb 2022
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed68 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Jambagi Square-----11

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 16 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 16 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area392 sq m
Named landowners1
LandownerVillageDistrict
Dr. Varsha Laxman Jambagi--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.20 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectD A Saynekar
EngineerSAGAR HUDDAR

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed68

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/220221/004716 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Proforma of Agreement of saleFile: Proforma of Agreement of sale.pdf16 Feb 2022
demarcation of STP/soak pit in site planFile: permission plan with demarcatio of STP-soak PIT (2).pdf16 Feb 2022
Water NOCFile: Water NOC.pdf8 Feb 2022
Pollution NOCFile: Pollution control board noc jambagi square .pdf8 Feb 2022
HESCOM NOCFile: NOC HESCOM Jambagi square .pdf8 Feb 2022
Fire NOCFile: Fire NOC.pdf8 Feb 2022
Affidavit for NOC for water supply, Fire and power supplyFile: Affidavit for NOC.pdf24 Aug 2021
BALANCE SHEET 2019-20 WITH CA UDINFile: BALANCE SHEET 2019-20 WITH CA UDIN.pdf23 Jul 2021
P AND L 2019-20 WITH CA UDINFile: P AND L 2019-20 WITH CA UDIN.pdf23 Jul 2021
ABOUT ONGOING PROJECT DETAILSFile: ABOUT ONGOING STATUS OF THE PROJECT.pdf23 Jul 2021
BANK ACCOUNT DETAILS AS PER CIRCULAR ISSUED BY BANKFile: RERA ACCOUNT OF THE PROJECT.jpeg23 Jul 2021
AFFIDAVIT FOR BANK ACCOUNTFile: BANK ACCOUNT AFFIDAVIT.pdf8 Jul 2021
LETTER FROM BANKFile: BANK LETTER.jpeg8 Jul 2021
About CA UDINFile: ABOUT CA UDIN.pdf8 Jul 2021
BANK ACCOUNT AFFIDAVITFile: BANK ACCOUNT AFFIDAVIT.pdf17 Jun 2021
ABOUT CA UDIN FOR 2019-20File: ABOUT CA UDIN.pdf17 Jun 2021
WATER NOCFile: NOC.pdf17 Jun 2021
Commencement certificate-
Permission plan of Jambagi square-
Permission plan of Jambagi square-
yet to be finalized-
yet to be finalized-
Sale Deed 1-
Permission plan of Jambagi square-
Permission plan of Jambagi square-
yet to be finalized-
yet to be finalized-
General Specifications-
NEC For 30 Years of Dr Varsha Jambagi-
Affidavate-
CTS EXTRACT-
Saleded-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Permission plan of Jambagi square-
Permission plan of Jambagi square-
Unnamed document-
Balance Sheet 2019 - 2020File: yet to be finalized.pdf-
Balance Sheet 2018 - 2019File: Balance sheet 2019-20.pdf-
Balance Sheet 2017 - 2018File: Balance Sheet 2018-19.pdf-
Audited Profit and Loss Statement 2019 - 2020File: yet to be finalized.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P and L 2019-20.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P and L 2018-19.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR Acknowledgement 20-21.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR Acknowledgement 19-20.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR Acknowledgement 18-19.pdf-
Affidavate B form-
Tower Excel SheetFile: PRMKARERA1249447PR220221004716.xlsx-
Occupancy CertificateFile: CC.pdf-
Completion certificate issued by the competent authorityFile: CC.pdf-
Registered Agreement of SaleFile: Jambagi Square ATS_compressed.pdf-
Registered conveyance deed for an individual unitFile: Jambagi Square Sale deed_compressed.pdf-

How this compares with Belagavi

24%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep JAMBAGI SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

2 kmJAMBAGI SQUAREOther 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: Dr Varsha Laxman Jambagi

Dr Varsha Laxman Jambagi has 1 registration on RERA Karnataka, including JAMBAGI SQUARE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if JAMBAGI SQUARE is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JAMBAGI SQUARE?

The registered promoter entity is Dr Varsha Laxman Jambagi. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JAMBAGI SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JAMBAGI SQUARE?

The professionals named in the filing: Architect: D A Saynekar; Engineer: SAGAR HUDDAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAMBAGI SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAMBAGI SQUARE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAMBAGI SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.