JAI SIGNATURE

By JAI SHELTERS , H.A.VENUGOPAL & 10 OTHERS

RG-KA-06750 · RERA PRM/KA/RERA/1251/446/PR/250626/008753 · Last updated on RERA Karnataka portal: 23 Jun 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2028Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 123 documents Report an error

JAI SIGNATURE is a Residential/Group Housing project by JAI SHELTERS , H.A.VENUGOPAL & 10 OTHERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/250626/008753 on 25 Jun 2026. Possession is promised by 15 Mar 2028.

At a glance

Project

  • NameJAI SIGNATURE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560048
  • Pincode560048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/250626/008753
  • ReraGenie IDRG-KA-06750

Builder

  • NameJAI SHELTERS , H.A.VENUGOPAL & 10 OTHERS
  • Entity typeOther ( Association of Persons )
  • GSTIN29AATFJ8096L1Z5
  • Authorized SignatoryM SOMA SEKHAR

Key dates

this monthRegisteredJun 2026PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 Jun 2026
  • Promised completion15 Mar 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed123 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---50050

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership12

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,124 sq m
Named landowners12
LandownerVillageDistrict
JAI SHELTERS MAG M SOMASEKHAR--
H.A. VENUGOPAL--
RACHANA REDDY--
POKURI SRIKANTH--
PARAMESHWARAPPA E--
E. BHUJANGAM NAIDU--
NADIR ZEESHAN--
DEEPIKA G S,--
J RAVI KUMAR--
N MOHAN NAIDU--
B.DEVAKI,--
B.RANJITH KUMAR--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 34.40 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 30.00 cr-
On-site expenditure-Site OverheadRs 4.40 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectT N S Chakravarthi
EngineerMADAMANCHI SURENDRA NADH
Chartered AccountantCHANDRA MOHAN M

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed123

As listed on the registration, under the names the promoter filed them with; the newest 80 of 123 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/250626/008753 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Board ResoulationFile: Board Resoulation_Jai Shelters.pdf23 Jun 2026
Request Letter_K-RERA SecretaryFile: Request Letter_Jai Shelter_Seceratary RERA.pdf23 Jun 2026
Undertaking Cum Declearation by AOP_Jai Shelters & OthersFile: Undertaking Cum Declearation by AOP_Jai Signature.pdf16 Jun 2026
GPA by Jai Shelters & Others for Jai Signature Project_RERAFile: GPA_Jai Signature Project_RERA.pdf16 Jun 2026
Performa Agreement for Sale Draft with the specifications and amenities detailsFile: Performa AOS _Jai Signature.pdf16 Jun 2026
land calculation sheet_Declearation as per the SR Value & Sale deedFile: land calculation sheet_Declearation_Jai Signature.pdf16 Jun 2026
SALE DEEDFile: SALE DEED 2.pdf22 Apr 2026
land cost calculation sheetFile: land cost calculation as per guidance value (1).pdf22 Apr 2026
guidance certificate highlightFile: stamp duty.pdf22 Apr 2026
JD REQUEST LETTERFile: SALE DEED SIGNATURE.pdf22 Apr 2026
guidance value along with guidance certificate highlight the priceFile: Stamp duty .pdf16 Feb 2026
specifications and amenities details in AFSFile: Specifications Jai Shelters.pdf16 Feb 2026
JDA between land owner and promoterFile: doc.pdf16 Feb 2026
updated the specifications and amenities details in AFSFile: Adobe Scan 22 Jan 2026 (2).pdf22 Jan 2026
land cost calculation sheet as per the guidance value along with guidance certificate highlightFile: stamp duty.pdf22 Jan 2026
land cost calculation sheetFile: land cost calculation as per guidance value.pdf22 Jan 2026
sale deedFile: SALE DEED 2.pdf22 Jan 2026
bank affidavit in the prescribed format documentsFile: bank affidavit 1.pdf31 Dec 2025
Profit and Loss Statement and balance sheet 2023-24File: Jai shelters FY 23-24.pdf31 Dec 2025
Profit and Loss Statement and balance sheet 2024-25File: Jai shelters FY 24-25 (1).pdf31 Dec 2025
BANK LETTERFile: BANK LETTER SING.jpg31 Dec 2025
STATEMENTFile: 9175 STATEMNT.pdf31 Dec 2025
STATEMENTFile: 4247 STATEMENT.pdf31 Dec 2025
copy of connected MR showing flow of titles in favour of landowner before conversionFile: MR.jpeg31 Dec 2025
GIFT DEEDFile: GIFT DEED.pdf31 Dec 2025
PRESENT LAND OWNER SALE DEEDFile: PRESENT SALE DEED-compressed.pdf31 Dec 2025
EC from 1-4-2011 to till dateFile: EC (2).pdf31 Dec 2025
Approved Original Single Plot layout planFile: SINGLE LAYOUT PLAN.pdf31 Dec 2025
Master plan CDP RMPFile: HUDI_BBMP-MP.pdf31 Dec 2025
VILLAGE MAPFile: HUDI_BBMP-VM.pdf31 Dec 2025
GOOGLE MAPFile: HUDI_BBMP-GOOGLE.pdf31 Dec 2025
BWSSB NOCFile: BWSSB NOC SIG.pdf31 Dec 2025
BWSSB RECEIPTFile: BWSSB RECEIPT.pdf31 Dec 2025
PCB NOCFile: PCB.pdf31 Dec 2025
BESCOM NOCFile: Jai Shelters Noc BESCOM.pdf31 Dec 2025
BESCOM RECEIPTFile: BESCOM RECEIPT.jpeg31 Dec 2025
structural stability certificateFile: Jai Shelters - Structural Stability Certificate (1).pdf31 Dec 2025
specifications and amenities details in AFSFile: SPECFICATIONS_N.pdf31 Dec 2025
guidance value along with guidance certificateFile: STAMPDUTY VALUE SIG.pdf31 Dec 2025
land cost calculation sheetFile: land cost calculation as per guidance value.pdf31 Dec 2025
sources of funds to complete the projectFile: sourcec of fund.pdf31 Dec 2025
STP DRAWINGSFile: STP (3).pdf31 Dec 2025
RTC, survey 102/2-
Mutation, survey 102/2-
Encumbrance Certificate, survey 102/2-
Conversion/Alienation Order, survey 102/2-
Sale/Title/Gift Deed, survey 102/2-
Khatha, survey 102/2-
Registration CertificateFile: FIRM CERTIFICATE.jpeg-
GST CertificateFile: AA291124059834ZRC27112024.pdf-
Certificate issued by CA Form 1File: Signature.pdf-
Certificate issued by Architect Form 2File: 20251202184922 (1).pdf-
Certificate issued by Engineer Form 3File: Jai Signature - Form 3 02-12-2025.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: affidavit no litigations sig.pdf-
Balance Sheet 2024 - 2025File: jai shelters fy 24-25.pdf-
Balance Sheet 2023 - 2024File: StatementofIncomeAATFJ8096L.pdf-
Balance Sheet 2022 - 2023File: NA RERA 1 (2).pdf-
Audited Profit and Loss Statement 2024 - 2025File: jai shelters fy 24-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: NA RERA 1 (2).pdf-
Audited Profit and Loss Statement 2022 - 2023File: NA RERA 1 (2).pdf-
Income Tax Return Acknowledgement 2024 - 2025File: jai shelters fy 24-25.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Jai SheltersITR V.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: NA RERA 1 (2).pdf-
cc letter-
building lice-
plan-
plan-
SPECFICATIONS_N-
clarification about non production of brochers-
reliquishment deed sig-
Sale Agreement Proforma JAI Signature-
model allotment letter-
affidavit 2-
affidavit 3-
affidavit no litigations sig-
LEGAL REPORT SIG-
Jai Shelters Noc-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep JAI SIGNATURE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmJAI SIGNATUREOther 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: JAI SHELTERS , H.A.VENUGOPAL & 10 OTHERS

JAI SHELTERS , H.A.VENUGOPAL & 10 OTHERS has 1 registration on RERA Karnataka, including JAI SIGNATURE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if JAI SIGNATURE is delayed beyond 15 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of JAI SIGNATURE?

The registered promoter entity is JAI SHELTERS , H.A.VENUGOPAL & 10 OTHERS, an other ( association of persons ) as per the filing. Its GSTIN 29AATFJ8096L1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in JAI SIGNATURE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at JAI SIGNATURE?

The professionals named in the filing: Architect: T N S Chakravarthi; Engineer: MADAMANCHI SURENDRA NADH; Chartered Accountant: CHANDRA MOHAN M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in JAI SIGNATURE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About JAI SIGNATURE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save JAI SIGNATURE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.