ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / IMPERIAL SKY

Valid until 31 Dec 2025 Mixed Development project

IMPERIAL SKY

By RADHE BUILDCON

RG-GJ-72155 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MN145AA10045/A1M/290124/311225 · Last updated on GujRERA portal: 1 Aug 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2025Possession promisedno revision filed
18 of 18Construction stages doneacross 2 buildings; every applicable stage filed complete
28 of 97Units unsoldnot recorded sold or booked
Jump to the 29 documents Report an error

IMPERIAL SKY is a Mixed Development project by RADHE BUILDCON in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MN145AA10045/A1M/290124/311225 on 3 Aug 2022. Possession is promised by 31 Dec 2025. 69 of the 97 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameIMPERIAL SKY
  • TypeMixed Development
  • Location
    • IMPERIAL SKY
    • NR SHREE RANG UPVAN BUNGLOWS
    • PDPU ROAD
    • RAISAN
    • RAYSAN
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MN145AA10045/A1M/290124/311225
  • ReraGenie IDRG-GJ-72155

Builder

  • NameRADHE BUILDCON
  • Entity typePARTNERSHIP FIRM
  • Other registrations3 more →
  • Past their filed date3

Key dates

this monthRegisteredAug 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2025
  • Registered on3 Aug 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed29 files

Current status

71%69 of 97 units booked
71.2%Of the estimated cost spent so far

Figures as on 1 Aug 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---44044
A---48553

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 1 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete across 2 buildings.

B100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 1 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationYes100%
Use of renewable energyYes100%
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,025 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 18.12 cr
Cost incurredRs 12.91 cr
Spent of the estimate71.23%
BuildingWingEstimatedIncurred
ANARs 9.06 crRs 6.20 cr
BNARs 9.06 crRs 6.71 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanket Kailashbhai Vora
EngineerCHIRAGKUMAR PRAGJIBHAI NAKRANI

Documents filed29

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/MN145AA10045/A1M/290124/311225 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)1 Aug 2025
Accountant's certificate (Form 3)1 Aug 2025
Site photograph, B1 Aug 2025
Site photograph, A1 Aug 2025
Engineer's certificate (Form 2)8 Oct 2024
Engineer's certificate annexure8 Oct 2024
RERA registration certificate3 Aug 2022
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

71%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep IMPERIAL SKY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near RAYSAN1,600+ in Gandhinagar

2 kmIMPERIAL SKYOther 200Dot size: filed unitsN

Filed coordinates, straight-line distance. 200 registered projects within 2 km.

Builder: RADHE BUILDCON

RADHE BUILDCON has 4 registrations on GujRERA, including VRAJ SKYLINE and IMPERIAL SKY. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if IMPERIAL SKY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of IMPERIAL SKY?

The registered promoter entity is RADHE BUILDCON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in IMPERIAL SKY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at IMPERIAL SKY?

The professionals named in the filing: Architect: Sanket Kailashbhai Vora; Engineer: CHIRAGKUMAR PRAGJIBHAI NAKRANI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in IMPERIAL SKY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About IMPERIAL SKY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save IMPERIAL SKY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.