ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Rural, Karnataka / HOUSE OF SAPIENS

Registration approved No litigation declared Residential/Group Housing project

HOUSE OF SAPIENS

By MA SARADA CONSTRUCTIONS

RG-KA-77679 · RERA PRM/KA/RERA/1250/304/PR/310126/008441 · Last updated on RERA Karnataka portal: 23 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jan 2031Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 86 documents Report an error

HOUSE OF SAPIENS is a Residential/Group Housing project by MA SARADA CONSTRUCTIONS in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/310126/008441 on 31 Jan 2026. Possession is promised by 28 Jan 2031.

At a glance

Project

  • NameHOUSE OF SAPIENS
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 562114
  • Pincode562114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/310126/008441
  • ReraGenie IDRG-KA-77679

Builder

  • NameMA SARADA CONSTRUCTIONS
  • Entity typePartnership Firm
  • GSTIN29AAXFM0492K1ZG
  • Authorized SignatoryChandhapura Nagaraja Manjunatha
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredJan 2026PromisedJan 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on31 Jan 2026
  • Promised completion28 Jan 2031
  • Revised completionNone
  • Buildings3 building records
  • Documents filed86 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---68068
Tower B (Wing 1)---1320132
Tower B (Wing 2)---1140114

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 23 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities41

As on 23 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesYes-
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesYes-
Staircases and Lift lobbies, corridor, lobbies, corridorYes-

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,907 sq m
Named landowners2
LandownerVillageDistrict
Krishnappa--
Rajagopala A--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 175.75 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 159.25 cr-
Interest on borrowingsRs 10.00 cr-
Administrative CostsRs 4.50 cr-
On-site expenditure-Consultants FeesRs 2.00 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPramod Vasudev Shiggavi
EngineerChanakya N
Chartered AccountantH D Ramakrishna

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed86

As listed on the registration, under the names the promoter filed them with; the newest 80 of 86 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/310126/008441 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
MR 10 (2007-2008) HOSFile: 1 MR 10 (2007-2008) HOS.pdf23 Jan 2026
Title DeedFile: 2 Title Deed.pdf23 Jan 2026
EC 01-04-2004 to Till dateFile: 3 EC 01-04-2004 to Till date.pdf23 Jan 2026
Legal ReportFile: 4 Legal Report.pdf23 Jan 2026
6, 7 Aminities Detail and Common area detailsFile: 6, 7 Aminities Detail and Common area details.pdf23 Jan 2026
Declaration Of Water Borewell and Bore well reportFile: 8 Declaration Of Water Borewell and Bore well report.pdf23 Jan 2026
Abstract EstimationFile: 9 Abstract Estimation.pdf23 Jan 2026
Clarification Regarding NO Sales -HOSFile: Clarification Regarding NO Sales -HOS.pdf23 Jan 2026
Clarification Unsecured Loand_HOSFile: Clarification Unsecured Loand_HOS.pdf23 Jan 2026
Query 1 21-01-2026 (1)File: Query 1 21-01-2026 (1).pdf23 Jan 2026
Area Statment - House of SapiensFile: Area Statment - House of Sapiens.pdf23 Jan 2026
RTC, survey 76/1-
Mutation, survey 76/1-
Encumbrance Certificate, survey 76/1-
Conversion/Alienation Order, survey 76/1-
JDA, survey 76/1-
Khatha, survey 76/1-
Registration CertificateFile: Ma Sarada Constructions Form C Certificate.pdf-
GST CertificateFile: Ma Sarada Constructions GST Certificate.pdf-
Partnership DeedFile: Ma Sarada Constructions Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: House Of Sapiens Form 1 CA Certi.pdf-
Certificate issued by Architect Form 2File: House of Sapiens Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: House Of Sapiens Engineer certificate 1.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: House of Sapiens Non-Litigation.pdf-
Balance Sheet 2024 - 2025File: Ma Sarada Constructions BS with schedules FY 24-25.pdf-
Balance Sheet 2023 - 2024File: Ma Sarada Constructions Balance sheet with schedules FY 23-24.pdf-
Balance Sheet 2022 - 2023File: Ma Sarada Constructions Balance Sheet with Schedules FY 23-24.pdf-
Audited Profit and Loss Statement 2024 - 2025File: Ma Sarada Constructions Profit & Loss FY 24-25.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Ma Sarada Constructions Profit & Loss FY 23-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Ma Sarada Constructions Profit & Loss 22-23.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: Ma Sarada Constructions ITR FY 2024-2025.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: Ma Sarada Constructions ITR FY 2023-24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Ma Sarada Constructions ITR FY 2022-23.pdf-
Ma Sarada Constructions Commencement Certificate-
Ma Sarada Constructions Approved Building Plan-
Ma Sarada Constructions Section & elevation-
House of Sapiens Structural Stability Certificate-
House Of Sapiens Project Specification-
Brochure NA-
House Of Sapiens Relinqishment deed-
House of Sapiens Agreement of Sale-
House of Sapiens Allotment Letter-
House of Sapiens Form B-
House of Sapiens Sec 3 1 Voliation-
House of Sapiens Joint Affidavit-
Ma Sarada Constructions BESCOM Noc Signed-
Ma Sarada Constructions Water NOC Signed-
Ma Sarada Constructions KSPCB Noc-
Ma Sarada Constructions SEIAA Noc-
Ma Sarada Constructions Fire NOC-
Ma Sarada Constructions Airport Noc-
Ma Sarada Constructions BSNL Noc-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Ma Sarada Constructions 1st 2nd 3rd floor Plan-
Ma Sarada Constructions 4th to 17 th & Lower Pent House Floor Plan-
Ma Sarada Constructions DP Plan Approval Letter-
Ma Sarada Constructions DP Plan-
Ma Sarada Constructions Upeer Pent house plan-
Ma Sarada Constructions Site Floor Plan-
Ma Sarada Constructions Upper Lower Basement floor-
House of Sapiens STP Drawing-
House Of Sapiens Akarbandh-
Ma Sarada Constructions GPA-
House Of Sapiens Hissa Phody-
House of Sapiens MR T9-
ADLR Survey Sketch House of Sapiens-
House of Sapiens No mortgage-
House of Sapiens CDP Map-
House of Sapiens Village Map-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
UPAVAN, Phase II7/1, 7/9, 7/10, 5/3, 5/4, 5/5 KATHA No. 150200103200620936 , H.Hosahalli Village, Jigani Hobli, Anekal Taluk, Bangalore urban district , AnekalOngoingApr 2027Not due yet
UPAVANIcon Layout, Sy 7/11 and 7/12, , Hoshalli, Hennagara Road, Jigani Hobli , AnekalCompleted-No date filed

How this compares with Bengaluru Rural

20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep HOUSE OF SAPIENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmHOUSE OF SAPIENSOther 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: MA SARADA CONSTRUCTIONS

MA SARADA CONSTRUCTIONS has 2 registrations on RERA Karnataka, including HOUSE OF SAPIENS and UPAVAN, Phase II. Its filings declare 2 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if HOUSE OF SAPIENS is delayed beyond 28 Jan 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HOUSE OF SAPIENS?

The registered promoter entity is MA SARADA CONSTRUCTIONS, a partnership firm as per the filing. Its GSTIN 29AAXFM0492K1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HOUSE OF SAPIENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HOUSE OF SAPIENS?

The professionals named in the filing: Architect: Pramod Vasudev Shiggavi; Engineer: Chanakya N; Chartered Accountant: H D Ramakrishna. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HOUSE OF SAPIENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HOUSE OF SAPIENS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HOUSE OF SAPIENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.