ReraGenieLog inGet a buyer report

Home / Browse projects / Belagavi, Karnataka / HANAMANTA KRUPA

Registration approved No litigation declared Residential/Group Housing project

HANAMANTA KRUPA

By VELMAVIRASHRI NIRMITI

RG-KA-57645 · RERA PRM/KA/RERA/1249/447/PR/091025/008152 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Mar 2027Possession promisedno revision filed
6 of 14Construction stages donefurthest along: Plastering inside, 90%
11 of 12Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 116 documents Report an error

HANAMANTA KRUPA is a Residential/Group Housing project by VELMAVIRASHRI NIRMITI in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/091025/008152 on 9 Oct 2025. Possession is promised by 31 Mar 2027. 1 of the 12 units on this registration are recorded sold or booked, and 6 of 14 construction stages are filed complete.

At a glance

Project

  • NameHANAMANTA KRUPA
  • TypeResidential/Group Housing
  • Location
    • Belagavi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1249/447/PR/091025/008152
  • ReraGenie IDRG-KA-57645

Builder

  • NameVELMAVIRASHRI NIRMITI
  • Entity typeProprietorship
  • GSTIN29ACVPM1509K1Z1
  • Authorized SignatoryMr. KULKARNI SUBHASH MADDHURAO

Key dates

this monthRegisteredOct 2025PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Oct 2025
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed116 files

Current status

8%1 of 12 units booked
3.5%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HANAMANTA KRUPA---12012

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 14 construction stages are filed complete. The stage furthest along is Plastering inside, at 90%.

Building: 80% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling90%
Joinery: Doors, Windows, Ventilators etc70%
Basic work of Water supply, Sanitary and Electrification70%
Dadoing, Skirting, Flooring, Tiles work (All types)70%
Railing and Grill fixing70%
Electrification, Water supply and Sanitary Finishing70%
Painting40%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work40%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes60%
Sewage and Drainage SystemYes60%
Water conservation/rain water harvesting/recharge of ground waterYes60%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes40%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes40%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes60%
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsYes50%
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes70%
Outer WallYes90%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners5
LandownerVillageDistrict
Dr. Raja s/o Vithalrao Kulkarni--
Mr. Prahlad s/o Vithalrao Kulkarni--
Smt. Jayalaxmi w/o Mohan Harapanahalli--
Smt. Vidya @ Gouri w/o Ratnakar Kulkarni--
Smt. Shubha w/o Narayan Hattiholi--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 3.81 cr
Cost incurredRs 13.44 lakh
Spent of the estimate3.53%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 3.28 crRs 10.81 lakh
On-site expenditure-Site OverheadRs 49.50 lakhRs 2.63 lakh
On-site expenditure-Consultants FeesRs 3.50 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. SUNIL S AJAGAONKAR
EngineerEr. VINAY JANARDAN BEHRE

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed116

As listed on the registration, under the names the promoter filed them with; the newest 80 of 116 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/091025/008152 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Jun-2026.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: F5 Architect (Q1) Jun-2026.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: F6 Engineer (Q1) Jun-2026.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Mar-2026.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: F5 Architect (QU) Mar-2026.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: F6 Engineer (QU) Mar-2026.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: VELMAVIRASHRI NIRMITI -Rera Certificate.pdf31 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Dec-2025.pdf31 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: F6 Engineer Hanamanta Krupa.pdf31 Mar 2026
Q3 2025-26 Water supply and sewage board31 Mar 2026
Q3 2025-26 KPTCL- BESCOM31 Mar 2026
Approved Original Single Plot layout planFile: Affidavit for Single Plot & Order Copy.pdf12 Sep 2025
Approved Original Single Plot layout plan work orderFile: Affidavit for Single Plot & Order Copy.pdf12 Sep 2025
Approved Original Single Plot layout planFile: CTS Map.pdf12 Sep 2025
Village map certified by the concern officer with demarcation of proposed landFile: Village Map Letter from ADLR.pdf12 Sep 2025
Village map certified by the concern officer with demarcation of proposed landFile: Village Map & ADLR Survey Sketch.pdf3 Jul 2025
Village map certified by the concern officer with demarcation of proposed landFile: Village Map.pdf3 Jul 2025
Profit and loss account and balance sheet for 2021-22 with schedules and CA UDINFile: ITR 2021-22.pdf2 Jun 2025
Profit and loss account and balance sheet for 2021-22 with schedules and CA UDINFile: B Sheet 21-22.pdf2 Jun 2025
Profit and loss account and balance sheet for 2021-22 with schedules and CA UDINFile: P&L 21-22.pdf2 Jun 2025
Profit and loss account and balance sheet for 2021-22 with schedules and CA UDINFile: Schedules 21-22.pdf2 Jun 2025
Profit and loss account and balance sheet for 2022-23 with schedules and CA UDINFile: FY Statement 2022-23.pdf2 Jun 2025
Profit and loss account and balance sheet for 2022-23 with schedules and CA UDINFile: ITR 2022-23.pdf2 Jun 2025
Profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: ITR 2023-24.pdf2 Jun 2025
Profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: B Sheet 23-24.pdf2 Jun 2025
Profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: P&L 23-24.pdf2 Jun 2025
Profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: Computation Income 23-24.pdf2 Jun 2025
Profit and loss account and balance sheet for 2023-24 with schedules and CA UDINFile: Schedules 23-24.pdf2 Jun 2025
sources of fund to complete the project with supporting documentsFile: B Sheet 23-24.pdf2 Jun 2025
sources of fund to complete the project with supporting documentsFile: Source of Funds Declaration.pdf2 Jun 2025
Bank account affidavit in prescribed formatFile: RERA Bank Affidavit.pdf2 Jun 2025
EC from 9/7/2024 To till date continuousFile: New EC226-B.pdf2 Jun 2025
EC from 9/7/2024 To till date continuousFile: EC 2022 to Till Date.pdf2 Jun 2025
conversion order issued by the deputy commissionerFile: DC Conversion Copy.pdf2 Jun 2025
CTS MAP Instead of Single Plot PlanFile: CTS Map.pdf2 Jun 2025
Village map certified by the concern officer with demarcation of proposed landFile: Village Map.pdf2 Jun 2025
Village map certified by the concern officer with demarcation of proposed landFile: Village Map & ADLR Survey Sketch.pdf2 Jun 2025
What are all sources of fund to complete the project with supporting documentsFile: Source of Funds Declaration.pdf5 May 2025
CA KYC and registration certificateFile: Form-1 CA.pdf5 May 2025
EC from 9/7/2024 To till date continuousFile: EC Ack No Form-22.pdf5 May 2025
title deed of the current land owner as per latest transactionFile: Gift Deed.pdf5 May 2025
ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: Village Map & ADLR Survey Sketch.pdf5 May 2025
Building License Original CopyFile: Commencement Certificate.pdf5 May 2025
Approved building plan - Original CopyFile: Clarification of Sanctioned Drawings.pdf5 May 2025
Approved building planFile: Approvel Drawing.pdf5 May 2025
original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Clarification of Sanctioned Drawings.pdf5 May 2025
original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Sectional Drawing.pdf5 May 2025
original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Front Elevation.pdf5 May 2025
commencement certificateFile: Commencement Certificate.pdf5 May 2025
conversion order issued by the deputy commissionerFile: DC Conversion Copy.pdf5 May 2025
Master plan Extract marked the proposed land and certified by the concern AuthorityFile: CDP Plan (Master Plan).pdf5 May 2025
Village map certified by the concern officer with demarcation of proposed landFile: Village Map & ADLR Survey Sketch.pdf5 May 2025
Village map certified by the concern officer with demarcation of proposed landFile: CTS Map.pdf5 May 2025
self attested copy of the renwed Engineer license certificateFile: Engineer Licence Copy_compressed (2).pdf5 May 2025
Amenities and Common area details are incorrect. Please update the same properly as per the sanctionFile: Certified Amenties & Common Area Details.pdf5 May 2025
Engineer certificate in the prescribed formatFile: F6 Engineer (PR) Hanamanta Krupa.pdf5 May 2025
Registration CertificateFile: GST Certificate.pdf-
GST CertificateFile: GST Certificate.pdf-
Certificate issued by CA Form 1File: Form-1 CA.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation.pdf-
Commencement Certificate-
Approvel Drawing-
Sectional Drawing-
Stability Certificate-
Project Specification-
Agreement of Sale Proforma-
ALLOTMENT LETTER-
Form-B (1)-
Non-Violation-
JD Cum Declaration-
Advocate Search Report-

How this compares with Belagavi

8%of this project is bookeddistrict median 39%
24%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep HANAMANTA KRUPA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

Builder: VELMAVIRASHRI NIRMITI

VELMAVIRASHRI NIRMITI has 1 registration on RERA Karnataka, including HANAMANTA KRUPA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if HANAMANTA KRUPA is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of HANAMANTA KRUPA?

The registered promoter entity is VELMAVIRASHRI NIRMITI, a proprietorship as per the filing. Its GSTIN 29ACVPM1509K1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in HANAMANTA KRUPA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at HANAMANTA KRUPA?

The professionals named in the filing: Architect: Ar. SUNIL S AJAGAONKAR; Engineer: Er. VINAY JANARDAN BEHRE. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HANAMANTA KRUPA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HANAMANTA KRUPA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HANAMANTA KRUPA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.