Home / Browse projects / Bengaluru Rural, Karnataka / GREEN PARK

Registration approved No litigation declared Residential/Group Housing project

GREEN PARK

By SSV DEVELOPERS

RG-KA-14084 · RERA PRM/KA/RERA/1250/304/PR/130126/008398 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2029Possession promisedno revision filed
6 of 17Construction stages donefurthest along: Masonry Construction, 85%
155 of 208Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 135 documents Report an error

GREEN PARK is a Residential/Group Housing project by SSV DEVELOPERS in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/130126/008398 on 13 Jan 2026. Possession is promised by 20 Nov 2029. 53 of the 208 units on this registration are recorded sold or booked, and 6 of 17 construction stages are filed complete.

At a glance

Project

  • NameGREEN PARK
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 562114
  • Pincode562114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/130126/008398
  • ReraGenie IDRG-KA-14084

Builder

  • NameSSV DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29AFFFS2685M1Z7
  • Authorized SignatoryL LOKESH

Key dates

this monthRegisteredJan 2026PromisedNov 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Jan 2026
  • Promised completion20 Nov 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed135 files

Current status

25%53 of 208 units booked
27.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower---2080208

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 17 construction stages are filed complete. The stage furthest along is Masonry Construction, at 85%.

Building: 40% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction85%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes70%
Water conservation/rain water harvesting/recharge of ground waterYes50%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes70%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsYes0%
Corridor/LobbiesYes45%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes45%
BasementYes100%
TerraceYes0%
Outer WallYes30%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership10

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,522 sq m
Named landowners10
LandownerVillageDistrict
H A Manjunath--
H A Ramesh--
H A Sukanya--
Meena H A--
L Lokesh--
G BALAJI--
V CHITANYA--
V Chaitanya--
G BALAJI--
L LOKESH--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 82.17 cr
Cost incurredRs 22.61 cr
Spent of the estimate27.51%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 74.09 crRs 22.61 cr
On-site expenditure-Consultants FeesRs 4.58 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 3.50 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectG Bhanumathy
EngineerArun Kumar S R
Chartered AccountantVenkataramanappa

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed135

As listed on the registration, under the names the promoter filed them with; the newest 80 of 135 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/130126/008398 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA form 4 Q 2 SSV.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: SSV GREEN PARK-FORM-5 ARCHITECT.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: SSV GREEN PARK-FORM-6 ENGINEER.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: SSV DEVELOPERS FORM 4 Q4.pdf15 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: ARCHITECTURE CERTIFICATE FORM - 5 Q4 SSV DEVELOPERS.pdf15 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: ENGINEER CERTIFICATE FORM - 6 Q4 SSV DEVELOPERS.pdf15 Jul 2026
Q4 2025-26 Water supply and sewage board15 Jul 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q4 2025-26 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA SSV DEVLOPER Q1 FORM 4.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: ARCHITECTURE CERTIFICATE FORM - 5 Q1 SSV DEVELOPERS.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENGINEER CERTIFICATE FORM - 6 Q1 SSV DEVELOPERS.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Bank AffidavitFile: 1 Bank Affidavit.pdf7 Jan 2026
SBI Loan Application LetterFile: 2 SBI Loan Application Letter.pdf7 Jan 2026
SSV Developer B Plan Basement 1-4File: 3 SSV Developer B Plan Basement 1-4.pdf7 Jan 2026
SSV Developer B Plan Ground F 2-4File: 3 SSV Developer B Plan Ground F 2-4.pdf7 Jan 2026
SSV Developer B Plan Site 4-4File: 3 SSV Developer B Plan Site 4-4.pdf7 Jan 2026
SSV Developer B Plan Typical 3-4File: 3 SSV Developer B Plan Typical 3-4.pdf7 Jan 2026
Self-attested structural engineer licenceFile: 6 Self-attested structural engineer licence.pdf7 Jan 2026
Proforma Agreement of SaleFile: 7 Proforma Agreement of Sale.pdf7 Jan 2026
SSV DEVELOPERS GREEN PARK 150KLD STP DESIGNFile: 8 SSV DEVELOPERS GREEN PARK 150KLD STP DESIGN.pdf7 Jan 2026
Land calculation sheet with Gauidance value CertFile: 9 Land calculation sheet with Gauidance value Cert.pdf7 Jan 2026
RTC, survey 15/4-
Mutation, survey 15/4-
Encumbrance Certificate, survey 15/4-
Conversion/Alienation Order, survey 15/4-
JDA, survey 15/4-
Khatha, survey 15/4-
RTC, survey 15/5-
Mutation, survey 15/5-
Encumbrance Certificate, survey 15/5-
Conversion/Alienation Order, survey 15/5-
JDA, survey 15/5-
Khatha, survey 15/5-
RTC, survey 15/6-
Mutation, survey 15/6-
Encumbrance Certificate, survey 15/6-
Conversion/Alienation Order, survey 15/6-
JDA, survey 15/6-
Khatha, survey 15/6-
RTC, survey 15/7-
Mutation, survey 15/7-
Encumbrance Certificate, survey 15/7-
Conversion/Alienation Order, survey 15/7-
JDA, survey 15/7-
Khatha, survey 15/7-
RTC, survey 15/8-
Mutation, survey 15/8-
Encumbrance Certificate, survey 15/8-
Conversion/Alienation Order, survey 15/8-
JDA, survey 15/8-
Khatha, survey 15/8-
RTC, survey 15/9-
Mutation, survey 15/9-
Encumbrance Certificate, survey 15/9-
Conversion/Alienation Order, survey 15/9-
JDA, survey 15/9-
Khatha, survey 15/9-
Registration CertificateFile: SSV developer registration certificate.pdf-
GST CertificateFile: GST CERTIFICATE.pdf-
Partnership DeedFile: SSV Developers Partnership deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1 - SSV DEVELOPERS.pdf-
Certificate issued by Architect Form 2File: Form 2 - SSV DEVELOPERS.pdf-
Certificate issued by Engineer Form 3File: Form 3 - SSV DEVELOPERS.pdf-

How this compares with Bengaluru Rural

25%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep GREEN PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmGREEN PARKOther 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: SSV DEVELOPERS

SSV DEVELOPERS has 1 registration on RERA Karnataka, including GREEN PARK. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if GREEN PARK is delayed beyond 20 Nov 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GREEN PARK?

The registered promoter entity is SSV DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AFFFS2685M1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GREEN PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GREEN PARK?

The professionals named in the filing: Architect: G Bhanumathy; Engineer: Arun Kumar S R; Chartered Accountant: Venkataramanappa. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GREEN PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GREEN PARK. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GREEN PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.