Home / Browse projects / Bengaluru Urban, Karnataka / GRAVITY ARANYA

Registration approved No litigation declared Residential/Group Housing project

GRAVITY ARANYA

By GRAVITY ESTATES

RG-KA-89932 · RERA PRM/KA/RERA/1251/310/PR/080922/005224 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Nov 2026Possession promisedmoved 24 months from the original
15 of 15Construction stages doneevery applicable stage filed complete
19 of 36Units unsoldnot recorded sold or booked
2Complaints at RERA Karnatakaon this registration
Jump to the 143 documents Report an error

GRAVITY ARANYA is a Residential/Group Housing project by GRAVITY ESTATES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/080922/005224 on 8 Sep 2022. Possession is promised by 15 Nov 2026. The completion date has moved by 24 months from the original filing. 17 of the 36 units on this registration are recorded sold or booked, and 15 of 15 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGRAVITY ARANYA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560060
  • Pincode560060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/080922/005224
  • ReraGenie IDRG-KA-89932

Builder

  • NameGRAVITY ESTATES
  • Entity typePartnership Firm
  • GSTIN29AAYFG0793J1ZJ
  • Authorized SignatorySURYA N. C
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2022First promiseNov 2024Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on8 Sep 2022
  • Promised completion15 Nov 2026
  • Revised completionRevised to 15 Nov 2026 (originally 15 Nov 2024)
  • Buildings1 building record
  • Documents filed143 files

Current status

47%17 of 36 units booked
177.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Villaments---36036

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 15 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes80%
Sewage and Drainage SystemYes90%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes55%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes60%
Storm water drainsYes100%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes90%
Parks & Tree plantingYes90%
Street LightingYes60%
ElectricityYes95%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes0%
Common storage spacesYes100%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,330 sq m
Named landowners1
LandownerVillageDistrict
M/S.ALMIGHTY BUILDERS AND DEVELOPERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 39.85 cr
Cost incurredRs 70.77 cr
Spent of the estimate177.58%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 32.10 crRs 32.10 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 3.20 crRs 7.91 cr
On-site expenditure-Salaries of workersRs 2.03 cr-
Payment of taxesRs 1.61 crRs 3.21 cr
On-site expenditure-Consultants FeesRs 60.00 lakhRs 27.55 cr
Payment of cessRs 16.05 lakh-
Payment of feesRs 15.69 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDinesh Kumar S
EngineerRajesh. H. M
Chartered AccountantNaveen Kumar G

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/250306/005224Nov 2024 → Nov 2025

Reason as filed by the promoterShortage of Labour; Shortage of Building Materials, Concrete, Jalli etc

ExtensionNov 2025 → Nov 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
00389/2026-GRAVITY ESTATES15/04/2026
00390/2026-GRAVITY ESTATES15/04/2026

Documents filed143

As listed on the registration, under the names the promoter filed them with; the newest 80 of 143 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/080922/005224 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: ARANYA PHASE 1 CA CERTIFICATE.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Phase 1 Architect certificate.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Phase 1 Engineers certificate.pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Rera-CA cert Aranya Phase 1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect certificate phase 1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate Phase 1.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate Aranya phase 1.pdf20 Jun 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect certificate Phase 1.pdf20 Jun 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer certificate Phase 1.pdf20 Jun 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate 1st Phase.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect_Certificate_1st_phase.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer_Certificate__1st_phase.pdf20 Feb 2026
COMMENCEMENT CERTIFICATEFile: COMMENCEMENT CERTIFICATE.pdf10 Feb 2025
Form B - Project ExtensionFile: Form B - Project Extension.pdf10 Feb 2025
Yield test reportFile: Yield test report.jpeg6 Sep 2022
DD for BWSSB NOC and Treated WaterFile: DD for BWSSB NOC and Treated Water.pdf6 Sep 2022
Addendum To Partnership DeedFile: Addendum To Partnership Deed.pdf6 Sep 2022
Affidavit for BWSSB and ChallanFile: Affidavit BWSSB and Challan.pdf26 Aug 2022
Affidavit for KSPCB and Fees ReceiptFile: Affidavit KSPCB and Fees Receipt.pdf26 Aug 2022
Project Specification Signed CopyFile: Project Specification Signed Copy.pdf26 Aug 2022
Basement Floor PlanFile: 1 Basement Floor Plan.pdf9 Aug 2022
First Floor PlanFile: 1 First Floor Plan.pdf9 Aug 2022
Ground Floor PlanFile: 1 Ground Floor Plan.pdf9 Aug 2022
Second Floor PlanFile: 1 Second Floor Plan.pdf9 Aug 2022
Site PlanFile: 1 Site Plan.pdf9 Aug 2022
Third Floor PlanFile: 1 Third Floor Plan.pdf9 Aug 2022
RTC 31File: 2 RTC 31.pdf9 Aug 2022
RTC 37File: 2 RTC 37.pdf9 Aug 2022
RTC 38File: 2 RTC 38.pdf9 Aug 2022
M RFile: 3 M R.pdf9 Aug 2022
DECLARATIONFile: 4 DECLARATION.pdf9 Aug 2022
KHATHAFile: 5 KHATHA.pdf9 Aug 2022
ECFile: 6 EC.pdf9 Aug 2022
AkarbandFile: 7 Akarband.pdf9 Aug 2022
Sketch Sy no 37File: 7 Sketch Sy no 37.pdf9 Aug 2022
Legal Opinion AranyaFile: 8 Legal Opinion Aranya.pdf9 Aug 2022
Declaration Area StatementFile: 12 Declaration Area Statement.pdf9 Aug 2022
Declaration Car ParkingFile: 15 Declaration Car Parking.pdf9 Aug 2022
Arch COA LicenseFile: 18 Arch COA License.pdf9 Aug 2022
KSPCB ackFile: 19 KSPCB ack.pdf9 Aug 2022
Project SpecificationsFile: 21 Project Specifications.pdf9 Aug 2022
DD for BWSSB NOC and Treated WaterFile: 22 DD for BWSSB NOC and Treated Water.pdf9 Aug 2022
Demand For BWSSB NOCFile: 22 Demand For BWSSB NOC.pdf9 Aug 2022
Stability of structureFile: 23 Stability of structure.pdf9 Aug 2022
Agreement of sale DraftFile: 24 Agreement of sale Draft.pdf9 Aug 2022
STP PLAN AND SECTIONSFile: 25 STP PLAN AND SECTIONS.pdf9 Aug 2022
Section 3 1 AffidavitFile: 26 Section 3 1 Affidavit.pdf9 Aug 2022
Breif Estimated cost of constructionFile: 27 Breif Estimated cost of construction.pdf9 Aug 2022
GRAVITY ARANYA VillamentsFile: GRAVITY ARANYA Villaments.xlsx9 Aug 2022
Agreement of sale - Sale deedFile: Agreement of sale - Sale deed.pdf9 Aug 2022
GPA Almighty to Gravity EstatesFile: GPA Almighty to Gravity Estates.pdf9 Aug 2022
SALE DEED TIPPAIAHA -ALMIGHTY BUILDRSFile: SALE DEED TIPPAIAHA -ALMIGHTY BUILDRS.pdf9 Aug 2022
KATHA - ALMIGHTY BUILDRSFile: KATHA - ALMIGHTY BUILDRS.pdf9 Aug 2022
SALE DEED - TIPPAYYAFile: SALE DEED- TIPPAYYA 1.pdf9 Aug 2022
SETTLEMENT DEED - TIPPAIHA - OTHERSFile: SETTLEMENT DEED - TIPPAIHA - OTHERS.pdf9 Aug 2022
PARTNERSHIP DEED - ALMIGHTYFile: PARTNERSHIP DEED - ALMIGHTY.pdf9 Aug 2022
MEMORANDUMFile: MEMORANDUM.pdf9 Aug 2022
DEED OF CANCELLATIONFile: DEED OF CANCELLATION.pdf9 Aug 2022
GPA PERFile: GPA PER.pdf9 Aug 2022
RTC, survey 37-
Mutation, survey 37-
Encumbrance Certificate, survey 37-
Conversion/Alienation Order, survey 37-
Sale/Title/Gift Deed, survey 37-
Khatha, survey 37-
Registration CertificateFile: Partnership firm Reg Cert.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1 CA Cert.pdf-
Certificate issued by Architect Form 2File: Form 2 Arc cert.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engg Cert.pdf-
Project Details-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 CA Cert.pdf-
Balance Sheet 2020 - 2021File: BL.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL.pdf-

How this compares with Bengaluru Urban

47%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 24 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GRAVITY ARANYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGRAVITY ARANYAOther 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 14 registered projects within 2 km.

Builder: GRAVITY ESTATES

GRAVITY ESTATES has 2 registrations on RERA Karnataka, including GRAVITY ARANYA and GRAVITY ARANYA PHASE - 2. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GRAVITY ARANYA is delayed beyond 15 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GRAVITY ARANYA?

The registered promoter entity is GRAVITY ESTATES, a partnership firm as per the filing. Its GSTIN 29AAYFG0793J1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GRAVITY ARANYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GRAVITY ARANYA?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at GRAVITY ARANYA?

The professionals named in the filing: Architect: Dinesh Kumar S; Engineer: Rajesh. H. M; Chartered Accountant: Naveen Kumar G. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GRAVITY ARANYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GRAVITY ARANYA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GRAVITY ARANYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.