ReraGenieLog inGet a buyer report

Home / Browse projects / Belagavi, Karnataka / GOLDEN PEARL

Registration approved No litigation declared Plotted Development project

GOLDEN PEARL

By AMOGH BUILDERS AND DEVELOPERS

RG-KA-86777 · RERA PRM/KA/RERA/1249/447/PR/170924/007027 · Last updated on RERA Karnataka portal: 20 Aug 2024

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 139 documents Report an error

GOLDEN PEARL is a Plotted Development project by AMOGH BUILDERS AND DEVELOPERS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/170924/007027 on 17 Sep 2024. Possession is promised by 30 Sep 2025.

At a glance

Project

  • NameGOLDEN PEARL
  • TypePlotted Development
  • Location
    • Belagavi
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1249/447/PR/170924/007027
  • ReraGenie IDRG-KA-86777

Builder

  • NameAMOGH BUILDERS AND DEVELOPERS
  • Entity typeProprietorship
  • GSTIN29AKKPH5911M2ZP
  • Authorized SignatoryMr. BHARAT MALLIKARJUN HAGARAGI

Key dates

this monthRegisteredSep 2024PromisedSep 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 Sep 2024
  • Promised completion30 Sep 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed139 files

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners4
LandownerVillageDistrict
Mr. Ravi Achuta Rao--
Mrs. Sarika Ravi Siddannavar--
Mrs. Sneha Ratnakar Bagewadi--
Mrs. Sneha Ratnakar Bagewadi--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 97.28 lakh
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 82.44 lakh-
Payment of taxesRs 14.84 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerEr. SHUBHAM JAYAVANT NAIK
Chartered AccountantCA Tukesh S Patil

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed139

As listed on the registration, under the names the promoter filed them with; the newest 80 of 139 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/170924/007027 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Land Shown As JDA, CorrectedFile: Jda Hagaragi.pdf20 Aug 2024
Upload the profit and loss account and balance sheet for 2023-24 with CA UDINFile: Financial Statement.pdf1 Aug 2024
The sources of funds to complete the project, With supporting documentsFile: Source of Funds Declaration Golden Pearl.pdf1 Aug 2024
JDA land owner Survey Number 434/49 Digitally Signed Sale DeedFile: SY NO 49 DIGITALLY SIGNED SALE DEED.pdf1 Aug 2024
JDA land owner Survey Number 434/49 Encumbrance And MRFile: SY NO 49 EC FROM 03-12-2015 TO TILL DATE.pdf1 Aug 2024
C D PFile: CDP Plan BLGM.pdf18 Jul 2024
Bank Affidavit Revised with Total Estimation Cost of the ProjectFile: Bank Affidavit RERA Account Revised.pdf4 Jul 2024
What are all the sources of funds to complete the project? With supporting documentsFile: Source of Funds Declaration Golden Pearl.pdf4 Jul 2024
Upload the chartered accountant certificate in the prescribed format form -01 with UDINFile: Form-1 CA Revised.pdf4 Jul 2024
Upload the profit and loss account and balance sheet for 2020-21, 2021-22 & 2022-23 with CA UDIN andFile: Financial Statement.pdf4 Jul 2024
Sale Deed Sy.No-434/24File: Sale Deed 434-24.pdf4 Jul 2024
Sale Deed Sy.No-434/39File: Sale Deed 434-39.PDF4 Jul 2024
Sale Deed Sy.No-434/40File: Sale Deed 434-40.pdf4 Jul 2024
RTC 2023-24 for All Project Sy. No'sFile: RTC 2023-24.pdf4 Jul 2024
Conversion Order Sy.No-434/39File: NA Order Copy.pdf4 Jul 2024
RTC Sy.No-434/39File: RTC 2023-24 39.pdf4 Jul 2024
Mutation Copy Sy.No-434/39File: MR Sale Deed.pdf4 Jul 2024
Sale Deed/Title Deed Sy.No-434/39File: Sale Deed 434-39.PDF4 Jul 2024
Phody-MRFile: Phody MR.pdf4 Jul 2024
Phody-MR-2File: Phody MR-2.pdf4 Jul 2024
Phody-MR-3File: Phody MR-3.pdf4 Jul 2024
Extent of Land for the Sy.No-434/39 & 434/40 with JDAFile: Extent Land with JDA.pdf4 Jul 2024
EC 2004-2020 All Sy.No'sFile: EC 2004-20.pdf4 Jul 2024
EC 2020-2024 All Sy.No'sFile: EC 2020-24.pdf4 Jul 2024
Advocate Search Report for All Project Sy.No'sFile: Legal Opinion Report_compressed.pdf4 Jul 2024
Relinquishment DeedFile: Relinquishment Deed.pdf4 Jul 2024
Layout Work OrderFile: Layout Work Order.pdf4 Jul 2024
Horticulture Department NOC for Park DevelopmentFile: Horticulture NOC.pdf4 Jul 2024
Demarcation CDP Map Showing the Proposed SiteFile: CDP Plan.pdf4 Jul 2024
Village Map showing the proposed siteFile: Village Map.pdf4 Jul 2024
ZR copy for park and open space and CA relaxationFile: Zonal Regulation Page No-75.pdf4 Jul 2024
self attested copy of the renewed Engineer license certificateFile: Engineer Licence Copy (1).pdf4 Jul 2024
Calculation Sheet Common Area Details Certified by the EngineerFile: Certified Amenties & Common Area Details PDF.pdf4 Jul 2024
Engineer Certificate in the prescribed formatFile: F6 Engineer (PR) Golden Pearl PDF.pdf4 Jul 2024
STP/Septic tank, Soak pit, and Sewer Line Drawing Certified by the EngineerFile: Septic Tank, Soak Pit & Drainage Sketch.pdf4 Jul 2024
Gift Deed Sy.No-434/24File: Gift Deed 434-24.pdf4 Jul 2024
Plot Area Details Certified by EngineerFile: Certified Plot Area Details PDF.pdf4 Jul 2024
EC Sy.No-434/40File: New EC 434-40.pdf4 Jul 2024
PT SHEET 434/24File: 434-24.pdf4 Jul 2024
PT SHEET 434/39File: 434-39.pdf4 Jul 2024
PT SHEET 434/40File: 434-40.pdf4 Jul 2024
PT SHEET 434/49File: 434-49.pdf4 Jul 2024
All Sy.No SketchFile: Sketch Map.pdf4 Jul 2024
RTC, survey 434/24-
Mutation, survey 434/24-
Encumbrance Certificate, survey 434/24-
Conversion/Alienation Order, survey 434/24-
JDA, survey 434/24-
Khatha, survey 434/24-
RTC, survey 434/39-
Mutation, survey 434/39-
Encumbrance Certificate, survey 434/39-
Conversion/Alienation Order, survey 434/39-
JDA, survey 434/39-
Khatha, survey 434/39-
RTC, survey 434/40-
Mutation, survey 434/40-
Encumbrance Certificate, survey 434/40-
Conversion/Alienation Order, survey 434/40-
JDA, survey 434/40-
Khatha, survey 434/40-
RTC, survey 434/49-
Mutation, survey 434/49-
Encumbrance Certificate, survey 434/49-
Conversion/Alienation Order, survey 434/49-
JDA, survey 434/49-
Khatha, survey 434/49-
Registration CertificateFile: Udyam Registration Certificate_compressed.pdf-
Certificate issued by CA Form 1File: Form-1 CA Revised.pdf-
Certificate issued by Engineer Form 3File: F3 Engineer (PR) (3) PDF.pdf-
Project Chartered Accountant-
Project Engineer-
AffidavitFile: Non-Litigation.pdf-
Certificate from Chartered AccountFile: Form-1 CA Revised.pdf-
Balance Sheet 2022 - 2023File: Declaration of Financial Statement PDF.pdf-
Balance Sheet 2021 - 2022File: Declaration of Financial Statement PDF.pdf-
Balance Sheet 2020 - 2021File: Declaration of Financial Statement PDF.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Declaration of Financial Statement PDF.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Declaration of Financial Statement PDF.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Declaration of Financial Statement PDF.pdf-

How this compares with Belagavi

24%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep GOLDEN PEARL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

Builder: AMOGH BUILDERS AND DEVELOPERS

AMOGH BUILDERS AND DEVELOPERS has 1 registration on RERA Karnataka, including GOLDEN PEARL. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if GOLDEN PEARL is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GOLDEN PEARL?

The registered promoter entity is AMOGH BUILDERS AND DEVELOPERS, a proprietorship as per the filing. Its GSTIN 29AKKPH5911M2ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GOLDEN PEARL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GOLDEN PEARL?

The professionals named in the filing: Engineer: Er. SHUBHAM JAYAVANT NAIK; Chartered Accountant: CA Tukesh S Patil. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GOLDEN PEARL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GOLDEN PEARL. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GOLDEN PEARL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.