ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Godrej Woodscapes Phase 2

Registration approved No litigation declared Residential/Group Housing project

Godrej Woodscapes Phase 2

By Godrej Properties Limited

RG-KA-12197 · RERA PRM/KA/RERA/1251/446/PR/170524/006888 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jun 2030Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 97%
12 of 232Units unsoldnot recorded sold or booked
2Complaints at RERA Karnatakaon this registration
Jump to the 153 documents Report an error

Godrej Woodscapes Phase 2 is a Residential/Group Housing project by Godrej Properties Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/170524/006888 on 17 May 2024. Possession is promised by 1 Jun 2030. 220 of the 232 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGodrej Woodscapes Phase 2
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/170524/006888
  • ReraGenie IDRG-KA-12197

Builder

  • NameGodrej Properties Limited
  • Entity typeCompany
  • GSTIN29AAACG3995M1ZX
  • Authorized SignatoryPramod Bisht
  • Zonal Chief Executive OfficerPramod Bisht
  • DirectorPramod Bisht
  • Project HeadSanthosh Kumar
  • Other registrations16 more →
  • Declared earlier projects8 →

Key dates

this monthRegisteredMay 2024PromisedJun 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on17 May 2024
  • Promised completion1 Jun 2030
  • Revised completionNone
  • Buildings2 building records
  • Documents filed153 files

Current status

95%220 of 232 units booked
22.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower P---1160116
Tower Q---1160116

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 97%.

Building: 19% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work97%
Foundation footing work97%
Upto Plinth Level39%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)45%
Retaining wall (All types)39%
RCC or MS Framed structure19%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes10%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes10%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area24,316 sq m
Named landowners2
LandownerVillageDistrict
Godrej Properties Limited--
Godrej Properties Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 262.53 cr
Cost incurredRs 59.13 cr
Spent of the estimate22.52%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 211.71 crRs 37.91 cr
On-site expenditure-Site OverheadRs 16.58 crRs 14.15 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 11.66 cr-
Payment of feesRs 8.77 cr-
On-site expenditure-Consultants FeesRs 7.63 cr-
Payment of chargesRs 5.85 cr-
Payment of PremiumsRs 33.01 lakh-
Payment of taxes-Rs 1.01 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 6.05 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTILAK THOMAS
EngineerMadhura Manjrekar
Chartered AccountantBHAVESH D. SHAH & CO.

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
00801/2024-Godrej Properties Limited27/08/2024
01190/2024-Godrej Properties Limited19/11/2024

Documents filed153

As listed on the registration, under the names the promoter filed them with; the newest 80 of 153 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/170524/006888 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - GODREJ WOODSCAPES PH 2-FINAL_compressed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5 Architects Woodscapes Ph 2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer -Woodscapes PH2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 GODREJ WOODSCAPES PH 2-FINAL.pdf10 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5 Architects Certificate- Godrej Woodscapes Phase 2_30-Jun-2026.pdf10 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer - Godrej Woodscapes - 30-06-26-PH2.pdf10 Jul 2026
Q1 2026-27 Water supply and sewage board10 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)10 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)10 Jul 2026
Q1 2026-27 KPTCL- BESCOM10 Jul 2026
Q1 2026-27 Fire and Safety10 Jul 2026
Q1 2026-27 Airport Authority of India10 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department10 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 GODREJ WOODSCAPES PH 2- FINAL.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form -5 Architects Certificate- Godrej Woodscapes Phase 2_31-Mar-2026.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer - Godrej Woodscapes - 31-03-26-PH2.pdf13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form4_ CA Certificate _GODREJ WOODSCAPES_ PH 2_Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: 1_Form -5 Architects Certificate- Godrej Woodscapes Phase 2_31-Dec-2025.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer - Godrej Woodscapes - 31-12-25-PH2.pdf14 Jan 2026
BS FY 2020-21File: BS FY 202021.pdf16 May 2024
BS FY 2021-22File: BS FY 202122.pdf16 May 2024
BS FY 2022-23File: BS FY 202223.pdf16 May 2024
CF FY 2020-21File: CF FY 202021.pdf16 May 2024
CF FY 2021-22File: CF FY 202122.pdf16 May 2024
CF FY 2022-23File: CF FY 202223.pdf16 May 2024
P & L FY 2020-21File: P L FY 202021.pdf16 May 2024
P & L FY 2021-22File: P L FY 202122.pdf16 May 2024
P & L FY 2022-23File: P L FY 202223.pdf16 May 2024
Auditor Report FY 2020-21File: Auditor Report FY 202021.pdf16 May 2024
Auditor Report FY 202122File: Auditor Report FY 202122.pdf16 May 2024
GPL Standalone FS March 2023 signedFile: GPL Standalone FS March 2023 signed.pdf16 May 2024
Auditor Report FY 2021-22File: Auditor Report FY 202122 (1).pdf16 May 2024
Auditor Report FY 2022-23File: Auditor Report FY 202223.pdf16 May 2024
Konadasapura Conversion OrderFile: Konadasapura Conversion Order.pdf16 May 2024
GPL Standalone FS March 2023 signedFile: GPL Standalone FS March 2023 signedcompressed.pdf16 May 2024
EC 01041960 to 31071986 - SyNo3File: EC 01041960 to 31071986 SyNo3.pdf16 May 2024
EC - 010886 to 31051989 - SyNo3File: EC 010886 to 31051989 SyNo3.pdf16 May 2024
EC 010689 to 31032004 - SyNo3File: EC 010689 to 31032004 SyNo3.pdf16 May 2024
EC 01042004 to 21082022 - SyNo3File: EC 01042004 to 21082022 SyNo3.pdf16 May 2024
EC 01041960 to 31071986 - SyNo4File: EC 01041960 to 31071986 SyNo4.pdf16 May 2024
EC 010686 to 31051989 - SyNo4File: EC 010686 to 31051989 SyNo4.pdf16 May 2024
EC 010689 TO 31032004 - SyNo4File: EC 010689 TO 31032004 SyNo4.pdf16 May 2024
EC 01042004 to 21082022 - SyNo4File: EC 01042004 to 21082022 SyNo4.pdf16 May 2024
FORM 1File: FORM 1 - GODREJ WOODSCAPE PHASE-2.PDF16 May 2024
Advocate Search ReportFile: Godrej Woodscapes Title report .pdf16 May 2024
CDPFile: Avalahalli CDPcompressed.pdf16 May 2024
Village mapFile: Village map Konadasapura.pdf16 May 2024
Nakshe ManjuraatiFile: Approval Letter BDA.pdf16 May 2024
Relinquishment deedFile: Relinquishment Deed.pdf16 May 2024
KSPCB FORM 1File: KSPCBFORM 1.pdf16 May 2024
KSPCB FORM 13File: KSPCBFORM 13.pdf16 May 2024
DP Work OrderFile: Work Order DP BDA.pdf16 May 2024
Architect certified demarcation drawingFile: BL-signed - PHASE 2.pdf16 May 2024
Area StatementFile: Area Statement.pdf16 May 2024
Area Statement-1File: Area Statement1.pdf16 May 2024
Area Statement-2File: Area Statement2.pdf16 May 2024
Basement-1File: Basement1.pdf16 May 2024
Basement-2File: Basement2.pdf16 May 2024
Ground Floor-minFile: Ground Floor-min.pdf16 May 2024
Site Plan-minFile: Site Plan-min.pdf16 May 2024
Form 1File: FORM 1 - GODREJ WOODSCAPE PHASE-2.PDF16 May 2024
Form 2File: Form-2 Architect Certificate - Phase 2-R.pdf16 May 2024
Form 3File: Form - 3- Phase 2.pdf16 May 2024
Structural safetyFile: Structure Certificate 24012024.pdf16 May 2024
Guidance Value Certificate - Bengal LampsFile: Guidance Value Certificate Bengal Lamps.pdf16 May 2024
FY 2019-20 Directors ReportFile: FY 201920 Directors Report.pdf16 May 2024
FY 2020-21 Director ReportFile: FY 202021 Director Report.pdf16 May 2024
FY 2021-22 Director ReportFile: FY 202122 Director Report.pdf16 May 2024
FY 2022-23 DIRECTOR REPORTFile: FY 202223 DIRECTOR REPORT.pdf16 May 2024
AAI - NoC - BLL-FinalFile: AAI NoC BLLFinal.pdf16 May 2024
Bengal lamps Fire NoC- AcknowledgementFile: Bengal lamps Fire NoC Acknowledgement.pdf16 May 2024
BESCOM - NoC - Bengal LampsFile: BESCOM NoC Bengal Lamps.pdf16 May 2024
BSNLFile: BSNL.pdf16 May 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 under way, not due yet
ProjectLocationStatusPromisedDelivered
Godrej Splendour Phase IIGODREJ SPLENDOUR PHASE II, 46/1, 46/2, 46/3, 46/4, 46/5, 47 OF DOMMASANDRA VILLAGE AND PORTION OF SY. NO. 107/1 OF KUMBENA AGRAHARA VILLAGE,BIDARAHALLI HOBLI, , WHITEFIELD , BENGALURU EAST , BENGALURU URBAN, KARNATAKA - 560049OngoingJan 2028Not due yet
Godrej Splendour46/1, 46/2, 46/3, 46/4, 46/5, 46/6, 47, 49/3, 57(P), 61/2 OF DOMMASANDRA VILLAGESY NO.107/1, 107/2 OF KUMBENA AGRAHARA VILLAGE,BIDARAHALLI HOBLI,, BENGALURU EAST, BENGALURU URBANOngoingMar 2027Not due yet
Godrej Park RetreatGODREJ PARK RETREAT, SY.NO.77,175/1,175/2A,175/2B,176/2A,176/2B & 177,KODATHI VILLAGE,VARTHUR HOBLI, BENGALURU EAST, BENGALURU URBANOngoingFeb 2027Not due yet

How this compares with Bengaluru Urban

95%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Godrej Woodscapes Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGodrej Woodscapes Phase Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: Godrej Properties Limited

Godrej Properties Limited has 17 registrations on RERA Karnataka, including Godrej Woodland Phase 2 and GODREJ PARKSHIRE. Its filings declare 8 earlier projects, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Godrej Woodscapes Phase 2 is delayed beyond 1 Jun 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Godrej Woodscapes Phase 2?

The registered promoter entity is Godrej Properties Limited, a company as per the filing. Its GSTIN 29AAACG3995M1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Godrej Woodscapes Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Godrej Woodscapes Phase 2?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Godrej Woodscapes Phase 2?

The professionals named in the filing: Architect: TILAK THOMAS; Engineer: Madhura Manjrekar; Chartered Accountant: BHAVESH D. SHAH & CO.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Godrej Woodscapes Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Godrej Woodscapes Phase 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Godrej Woodscapes Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.