Home / Browse projects / Bengaluru Urban, Karnataka / GODREJ TIARA

Registration approved No litigation declared Residential/Group Housing project

GODREJ TIARA

By Godrej Properties Limited

RG-KA-39188 · RERA PRM/KA/RERA/1251/309/PR/110625/007817 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
May 2030Possession promisedno revision filed
1 of 18Construction stages donefurthest along: Foundation footing work, 95%
8 of 346Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 104 documents Report an error

GODREJ TIARA is a Residential/Group Housing project by Godrej Properties Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/110625/007817 on 11 Jun 2025. Possession is promised by 31 May 2030. 338 of the 346 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGODREJ TIARA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 560022
  • Pincode560022
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/110625/007817
  • ReraGenie IDRG-KA-39188

Builder

  • NameGodrej Properties Limited
  • Entity typeCompany
  • CINL74120MH1985PLC035308
  • GSTIN29AAACG3995M1ZX
  • Authorized SignatoryTamil Arivu Jayaraman
  • Md & CeoGAURAV PANDEY
  • DirectorsGAURAV PANDEY, PIROJSHA ADI GODREJ, NADIR B GODREJ, SUTAPA BANERJEE, DR INDU BHUSHAN, JAYASHREE VAIDHYANATHAN, SUMEET NARANG
  • Project HeadTamil Arivu J
  • Other registrations16 more →
  • Declared earlier projects8 →

Key dates

this monthRegisteredJun 2025PromisedMay 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Jun 2025
  • Promised completion31 May 2030
  • Revised completionNone
  • Buildings3 building records
  • Documents filed104 files

Current status

98%338 of 346 units booked
21.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---1140114
Tower B---1160116
Tower C---1160116

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 18 construction stages are filed complete. The stage furthest along is Foundation footing work, at 95%.

Building: 23% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work95%
Upto Plinth Level70%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)70%
Retaining wall (All types)70%
RCC or MS Framed structure15%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities56

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolNoNot applicable
GymYes0%
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
Convenience StoreNoNot applicable
Banquet Hall + Pre-FunctionYes0%
SquashYes0%
BadmintonYes0%
Business LoungeYes0%
Private DiningYes0%
CaféYes0%
LibraryYes0%
Cigar RoomYes0%
Wellness CentreYes0%
Indoor PoolNoNot applicable
Outdoor PoolYes0%
Kids PoolYes0%
Dance StudioYes0%
Yoga ZoneYes0%
Roof Top CinemaYes0%
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area19,964 sq m
Named landowners3
LandownerVillageDistrict
M/s Godrej properties pvt ltd--
M/s Godrej properties pvt ltd--
M/s Godrej properties pvt ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 657.56 cr
Cost incurredRs 139.15 cr
Spent of the estimate21.16%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 481.47 crRs 20.20 cr
Payment of taxesRs 63.35 cr-
Administrative CostsRs 51.08 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 48.36 cr-
On-site expenditure-Consultants FeesRs 13.29 crRs 65.87 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShreyas M
EngineerAkash Shahaji Dalvi
Chartered AccountantBHAVESH D SHAH

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00063/2026-Godrej Properties Limited29/01/2026

Documents filed104

As listed on the registration, under the names the promoter filed them with; the newest 80 of 104 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/110625/007817 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4_ Godrej Tiara_ 30th Sep 26.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Godrej Tiara- Form-5 Architect (QU) 06-Oct-26.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Godrej Tiara- Form -6 Engineer (QU) -30-Sep-26.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Godrej Tiara- Form-4 CA Certificate 30-Jun-26.pdf10 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Godrej Tiara- Form-5 Architect (QU) 30-Jun-26.pdf10 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Godrej Tiara- Form -6 Engineer (QU) -30-Jun-26.pdf10 Jul 2026
Q1 2026-27 Water supply and sewage board10 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)10 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)10 Jul 2026
Q1 2026-27 KPTCL- BESCOM10 Jul 2026
Q1 2026-27 Fire and Safety10 Jul 2026
Q1 2026-27 Airport Authority of India10 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department10 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Godrej Tiara_Form 4 CA certificate.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Godrej Tiara- Form-5 Architect (QU) 31-Mar-26.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Godrej Tiara- Form -6 Engineer (QU) -31-03-2026.pdf13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q3 FY 25-26 GODREJ TIARA.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Q3 FY 25-26 GODREJ TIARA.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q3 FY 25-26 GODREJ TIARA.pdf13 Jan 2026
Engineer License self-attestedFile: 1 Engineer License self-attested.pdf11 Jun 2025
Proforma Allotment LetterFile: 2 Proforma Allotment Letter.pdf11 Jun 2025
Construction Cost SummaryFile: 3 Construction Cost Summary.pdf11 Jun 2025
Project Specifications and AmenitiesFile: 4 Project Specifications and Amenities.pdf11 Jun 2025
RERA_AREA_STATEMENTFile: 5 RERA_AREA_STATEMENT.pdf11 Jun 2025
Registration CertificateFile: Certificate of Incorporation-GPL-New.pdf-
Memorandum of AssociationFile: MOA.pdf-
Article of AssociationFile: AOA.pdf-
GST CertificateFile: GPL - GST Certificate.pdf-
Certificate issued by CA Form 1File: Form-1 CA Certificate.PDF-
Certificate issued by Architect Form 2File: Form-2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non litigation - Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.PDF-
Balance Sheet 2023 - 2024File: GPL SFS Mar24.pdf-
Balance Sheet 2022 - 2023File: BS FY 202223.pdf-
Balance Sheet 2021 - 2022File: BS FY 2021-22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: GPL SFS Mar24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: P L FY 202223.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P & L FY 2021-22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: GPL SFS Mar24.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR FY2022-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: GPL standalone Signed financial 2021-22.pdf-
Director's Report 2023 - 2024File: GPL SFS Mar24.pdf-
Director's Report 2022 - 2023File: FY 2022-23 DIRECTOR REPORT.pdf-
Director's Report 2021 - 2022File: FY 2021-22 Director Report.pdf-
Cash Flow Statement 2023 - 2024File: GPL SFS Mar24.pdf-
Cash Flow Statement 2022 - 2023File: CF FY 202223.pdf-
Auditor's Report 2023 - 2024File: GPL ITR ACK FY 24-25.pdf-
Auditor's Report 2022 - 2023File: Auditor Report FY 202223.pdf-
Auditor's Report 2021 - 2022File: Auditor Report FY 2021-22.pdf-
Building Licence-
Approved Building Plan-
Approved Building Plan-
Godrej Yeshwanthpur_Stability Certificate-
Project Specification Amenities and open area details-
Brouchure-
Relinquishment Deed-
Proforma ATS-
Allotment Letter as per RERA-
Form B Affidavit-
Affidavit sec 3(1)-
Legal Opinion-
BESCOM NOC with fee paid receipt-
BWSSB NOC with fee paid receipt-
KSPCB NOC with fee paid receipt-
SEIAA NOC with fee paid receipt-
Fire NOC with fee paid receipt-
AAI NOC-
BSNL NOC-
Unnamed document-

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 under way, not due yet
ProjectLocationStatusPromisedDelivered
Godrej WoodscapesSy.No 3 and 4 Konadasapura Village , , Bidarahalli Hobli, Bangalore East Taluk , Near Budigere cross , old Madras Road , Bengaluru East , Bengaluru Urban, Karnataka - 560049OngoingJan 2028Not due yet
Godrej Splendour Phase II46/1, 46/2, 46/3, 46/4, 46/5, 46/6, 47, 49/3, 57(P), 61/2 OF DOMMASANDRA VILLAGESY NO.107/1, 107/2 OF KUMBENA AGRAHARA VILLAGE,BIDARAHALLI HOBLI, BENGALURU EAST, BENGALURU URBANOngoingJan 2028Not due yet
Godrej Splendour46/1, 46/2, 46/3, 46/4, 46/5, 46/6, 47, 49/3, 57(P), 61/2 OF DOMMASANDRA VILLAGESY NO.107/1, 107/2 OF KUMBENA VILLAGE,BIDARAHALLI AGRAHARA HOBLI,, BENGALURU EAST, BENGALURU URBANOngoingMar 2027Not due yet
Godrej Park Retreat Ph1 and Ph2GODREJ PARK RETREAT, SY.NO. 77, 175/1, 175/2A, 175/2B, 176/2A, 176/2B & 177,KODATHI VILLAGE,VARTHUR HOBLI, BENGALURU BENGALURU URBANOngoingFeb 2027Not due yet

How this compares with Bengaluru Urban

98%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep GODREJ TIARA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmGODREJ TIARAOther 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: Godrej Properties Limited

Godrej Properties Limited has 17 registrations on RERA Karnataka, including Godrej Woodland Phase 2 and GODREJ PARKSHIRE. Its filings declare 8 earlier projects, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if GODREJ TIARA is delayed beyond 31 May 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GODREJ TIARA?

The registered promoter entity is Godrej Properties Limited, a company as per the filing. Its CIN L74120MH1985PLC035308 and GSTIN 29AAACG3995M1ZX can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GODREJ TIARA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GODREJ TIARA?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at GODREJ TIARA?

The professionals named in the filing: Architect: Shreyas M; Engineer: Akash Shahaji Dalvi; Chartered Accountant: BHAVESH D SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GODREJ TIARA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GODREJ TIARA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GODREJ TIARA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.