Home / Browse projects / Bengaluru Urban, Karnataka / GMC CONFLUENCE
GMC CONFLUENCE
By Grihamithra Confra Private Limited
RG-KA-93149 · RERA PRM/KA/RERA/1251/308/PR/170426/008589 · Last updated on RERA Karnataka portal: 8 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
GMC CONFLUENCE is a Residential/Group Housing project by Grihamithra Confra Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/170426/008589 on 17 Apr 2026. Possession is promised by 28 Feb 2031. 20 of the 270 units on this registration are recorded sold or booked, and 2 of 18 construction stages are filed complete.
At a glance
Project
- NameGMC CONFLUENCE
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 562125
- Pincode562125
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/170426/008589
- ReraGenie IDRG-KA-93149
Builder
- NameGrihamithra Confra Private Limited
- Entity typeCompany
- CINU45309KA2021PTC150554
- GSTIN29AAJCG1945N1Z0
- Authorized SignatoryKumara Giri Reddy Konda
- DirectorsDurga Chandu Valluri, Kumara Giri Reddy Konda, Durga Chandu Valluri, Ali Babu Kalluru
- Project HeadAli Babu Kalluru
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on17 Apr 2026
- Promised completion28 Feb 2031
- Revised completionNone
- Buildings3 building records
- Documents filed113 files
Current status
Figures as on 8 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower A | - | - | - | 103 | 0 | 103 |
| Tower B | - | - | - | 64 | 0 | 64 |
| Tower C | - | - | - | 103 | 0 | 103 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 8 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 18 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 50%.
Building: 17% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 50% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 10% |
| Retaining wall (All types) | 40% |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 8 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 35% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 5% |
| Lifts | Yes | 5% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 7% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| K V Venkata Swamy Reddy and Indiramma | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 124.00 cr | Rs 4.19 cr |
| Payment of taxes | Rs 10.25 cr | - |
| Administrative Costs | Rs 95.00 lakh | Rs 2,242 |
| On-site expenditure-Consultants Fees | Rs 11.80 lakh | Rs 29.20 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Santosh |
| Engineer | Sahana. G |
| Chartered Accountant | Vishwas Keremutt Rudraradhya |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed113
As listed on the registration, under the names the promoter filed them with; the newest 80 of 113 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/170426/008589 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - CA Certificate.pdf | 8 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf | 8 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf | 8 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 8 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 8 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 8 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 8 Oct 2026 |
| Q2 2026-27 Fire and Safety | 8 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 8 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - CA Certificate.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf | 14 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 14 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 14 Jul 2026 |
| Q1 2026-27 Fire and Safety | 14 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 14 Jul 2026 |
| Affidavit for building LicenseFile: 1 Affidavit for building License.pdf | 1 Apr 2026 |
| Building License ACK_PR0025124014553File: 1 Building License ACK_PR0025124014553.pdf | 1 Apr 2026 |
| Licence Application Fess ReceiptFile: 1 Licence Application Fess Receipt.pdf | 1 Apr 2026 |
| Project location demarcationFile: 2 Project location demarcation.pdf | 1 Apr 2026 |
| Site PlanFile: 3 Site Plan.pdf | 1 Apr 2026 |
| Basement PlanFile: 3 Basement Plan.pdf | 1 Apr 2026 |
| GF PlanFile: 3 GF Plan.pdf | 1 Apr 2026 |
| All Floor PlanFile: 3 All Floor Plan.pdf | 1 Apr 2026 |
| Terrace, Setion and Elevation PlanFile: 3 Terrace, Setion and Elevation Plan.pdf | 1 Apr 2026 |
| GCPL CCFile: 4 GCPL CC.pdf | 1 Apr 2026 |
| GCPL Declaration for BUA in plan and NOCsFile: 5 GCPL Declaration for BUA in plan and NOCs.pdf | 1 Apr 2026 |
| Demarcated CDP MapFile: 6 Demarcated CDP Map.pdf | 1 Apr 2026 |
| GCPL CC and Conversion OrderFile: 7 GCPL CC and Conversion Order.pdf | 1 Apr 2026 |
| Query 1 Answer Documnet 01-04-2026File: Query 1 Answer Documnet 01-04-2026.pdf | 1 Apr 2026 |
| RTC, survey 7/3 | - |
| Mutation, survey 7/3 | - |
| Encumbrance Certificate, survey 7/3 | - |
| Conversion/Alienation Order, survey 7/3 | - |
| JDA, survey 7/3 | - |
| Khatha, survey 7/3 | - |
| Registration CertificateFile: GCPL INCORPORATION.pdf | - |
| Memorandum of AssociationFile: GCPL MOA.pdf | - |
| Article of AssociationFile: GCPL AOA.pdf | - |
| GST CertificateFile: GCPL GST.pdf | - |
| Organization StructureFile: GCPL ORGANISATION CHART.pdf | - |
| Certificate issued by CA Form 1File: GCPL Form 1 CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: GCPL Form 2 Architect Certificate.pdf | - |
| Certificate issued by Engineer Form 3File: GCPL Form 3 Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: GCPL No Litigation Affidavit.pdf | - |
| Balance Sheet 2024 - 2025File: GCPL BS with Schedules 2024-25.pdf | - |
| Balance Sheet 2023 - 2024File: GCPL BS with Schedules 2023-24.pdf | - |
| Balance Sheet 2022 - 2023File: GCPL BS with Schedules 2022-23.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: GCPL P and L with Schedules 2024-25.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: GCPL P and L with Schedules 2023-24.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: GCPL P and L with Schedules 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: GCPL ITR 2024-25.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: GCPL ITR 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: GCPL ITR 2022-23.pdf | - |
| Director's Report 2024 - 2025File: GCPL Directors Report 2024-25.pdf | - |
| Director's Report 2023 - 2024File: GCPL Directors Report 2023-24.pdf | - |
| Director's Report 2022 - 2023File: GCPL Directors Report-FY 2022-23.pdf | - |
| Auditor's Report 2024 - 2025File: GCPL Auditors Report 2024-25.pdf | - |
| Auditor's Report 2023 - 2024File: GCPL Auditors Report 2023-24.pdf | - |
| Auditor's Report 2022 - 2023File: GCPL Audit Report FY 2022-23.pdf | - |
| GCPL CC | - |
| GCPL Site Plan | - |
| GCPL Section and Elevation | - |
| GCPL Structural Certificate with SE licence | - |
| GCPL Project Specifications | - |
| GCPL Brochure Declaration | - |
| GCPL RELINQUISHMENT DEED | - |
| GCPL Agreement for sale | - |
| GCPL Allotment Letter | - |
| GCPL FORM -B Affidavit | - |
| Section 3(1) No-Violation AFFIDAVIT | - |
| GCPL JDA AFFIDAVIT | - |
| GCPL LEGAL REPORT | - |
| GCPL BESCOM NOC | - |
| GCPL WATER NOC | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep GMC CONFLUENCE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 23 registered projects within 2 km.
Nambiar District 25 Phase 3
Nambiar EnsembleResidential Projects LLP
Meridian Park Phase II @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase I @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase III @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Nambiar District 25 Phase 2
Nambiar EnsembleResidential Projects LLP
SEVEN SARJAPUR
FORTUNE PRIMERO LLP
See every Bengaluru Urban project, with the district possession charts
Builder: Grihamithra Confra Private Limited
Grihamithra Confra Private Limited has 1 registration on RERA Karnataka, including GMC CONFLUENCE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if GMC CONFLUENCE is delayed beyond 28 Feb 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of GMC CONFLUENCE?
The registered promoter entity is Grihamithra Confra Private Limited, a company as per the filing. Its CIN U45309KA2021PTC150554 and GSTIN 29AAJCG1945N1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in GMC CONFLUENCE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at GMC CONFLUENCE?
The professionals named in the filing: Architect: Santosh; Engineer: Sahana. G; Chartered Accountant: Vishwas Keremutt Rudraradhya. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GMC CONFLUENCE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback