ReraGenieLog inGet a buyer report

Home / Browse projects / Belagavi, Karnataka / GIRNAR ENCLAVE

Registration approved No litigation declared Residential/Group Housing project

GIRNAR ENCLAVE

By SHREE BALAJEE CONSTRUCTIONS

RG-KA-67721 · RERA PRM/KA/RERA/1249/447/PR/181122/005464 · Last updated on RERA Karnataka portal: 21 Oct 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2026Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 83 documents Report an error

GIRNAR ENCLAVE is a Residential/Group Housing project by SHREE BALAJEE CONSTRUCTIONS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/181122/005464 on 18 Nov 2022. Possession is promised by 30 Jun 2026.

At a glance

Project

  • NameGIRNAR ENCLAVE
  • TypeResidential/Group Housing
  • Location
    • Belagavi
    • 590010
  • Pincode590010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1249/447/PR/181122/005464
  • ReraGenie IDRG-KA-67721

Builder

  • NameSHREE BALAJEE CONSTRUCTIONS
  • Entity typeProprietorship Firm
  • GSTIN29AJLPP9778L3ZU
  • Authorized SignatoryVIKRAM PANNALAL PORWAL
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2022PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Nov 2022
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed83 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GIRNAR ENCLAVE---19019

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 21 Oct 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 21 Oct 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area677 sq m
Named landowners1
LandownerVillageDistrict
SHREE BALAJEE CONSTRUCTIONS THROUGH ITS PROP. VIKRAM PORWAL--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.06 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 5.03 cr-
On-site expenditure-Consultants FeesRs 3.50 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKULDEEP MORE
EngineerVINAY BEHERE
Chartered AccountantVIJAY CHHAPPAR

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed83

As listed on the registration, under the names the promoter filed them with; the newest 80 of 83 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/181122/005464 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
FORM 1 OF CA AS PRESCRIBED FORMATFile: CA form no 1.pdf21 Oct 2022
EC FROM 01/05/2005 FROM SUB REGISTRAR OFFICEFile: EC.pdf21 Oct 2022
CERTIFIED COPY OF TRANSLATION OF TITLE DEED FROM MARATHI TO ENGLISHFile: attested translation of Will by translator.pdf21 Oct 2022
HISSA FORM 12 IN THE NAME OF PREVIOUS LAND OWNERSFile: Hissa Form 12.pdf21 Oct 2022
CONVERSION ORDER OF ORIGINAL LAND SURVEY NUMBERFile: NA order.pdf21 Oct 2022
LOCAL AUTHORITY KHATAFile: Form No 2.pdf21 Oct 2022
CERTIFIED COPY OF AREA CALCULATION BY PROJECT ARCHITECTFile: AREA HANUMAN NAGAR.pdf21 Oct 2022
PROPRIETORSHIP REGISTRATION CERTIFICATEFile: Properietorship certificate-GST Certificate.jpg13 Sep 2022
CA FORM WITH RERA DESIGNATED BANK ACCOUNTFile: CA form with RERA bank details.pdf13 Sep 2022
SELF ATTESTED PANFile: self attested PAN.pdf13 Sep 2022
ONLINE EC FROM 01/04/2005 TO TILL DATEFile: EC from 01042005 to till date.pdf13 Sep 2022
PRESENT LAND OWNER SIGNATURE ON NO LITIGATION AFFIDAVITFile: no litigation affidavit with signature of the land owner.pdf13 Sep 2022
TITLE DEED OF AJIT WITH ITS TRANSLATIONFile: Title document of Ajit with its english translation.pdf13 Sep 2022
LAND VALUATION CERTIFICATE FROM CONCERN SUB REGISTRAR OFFICEFile: Land valuation certificate from SRo.jpeg13 Sep 2022
SINGLE PLOT LAYOUT ORDERFile: single plot layout order.pdf13 Sep 2022
SINGLE PLOT LAYOUT PLANFile: single plot layout plan.pdf13 Sep 2022
CDP MAP OF PROPOSED PROJECT LANDFile: CDP.jpg13 Sep 2022
VILLAGE MAP FROM CITY SURYVE OFFICEFile: Village Map by City Survey office.pdf13 Sep 2022
CERTIFIED CARPET AREA CALCULATION FROM PROJECT ARCHFile: certified carpet area calculation.pdf13 Sep 2022
SELF ATTESTED PROJECT SPECIFICATIONFile: signed project specifications.pdf13 Sep 2022
STABILITY CERTIFICATEFile: stability certificate Hanuman Nagar.pdf13 Sep 2022
DRAFT OF AGREEMENTFile: Draft of Agreement of sale.pdf13 Sep 2022
DRAWING OF PROPOSED OF SEPTIC TANKFile: 21 WATER TANK & SEPTIC TANK DETAILS -- 11-02-2022.pdf13 Sep 2022
NA ORDERFile: na layout porwal (1).pdf13 Sep 2022
Registration CertificateFile: GST Certificate.jpg-
Certificate issued by CA Form 1File: CA certificate (At the time of registration)_compressed.pdf-
Certificate issued by Architect Form 2File: Arch certificate (At the time of registration).pdf-
Certificate issued by Engineer Form 3File: Engineer certificate (At the time of registration).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: no litigation affidavit with signature of the land owner.pdf-
Certificate from Chartered AccountFile: CA certificate (At the time of registration)_compressed.pdf-
Balance Sheet 2020 - 2021File: P and L and Balance Sheet 2020-21.pdf-
Balance Sheet 2019 - 2020File: P and L and Balance Sheet 2019-20.pdf-
Balance Sheet 2018 - 2019File: P and L and Balance Sheet 2018-19.pdf-
Audited Profit and Loss Statement 2020 - 2021File: P and L and Balance Sheet 2020-21.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P and L and Balance Sheet 2019-20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P and L and Balance Sheet 2018-19.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 21-22.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR 2020-21.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR 19-20.pdf-
APPROVAL LETTER-
HESCOM NOC-
Water NOC-
DWG 1_Layout_Layout1_BGM_LBPAS_17987_21_22_BP-
DWG 1_Layout_Layout1_BGM_LBPAS_17987_21_22_BP-
DWG 1_Layout_Layout1_BGM_LBPAS_17987_21_22_BP-
DWG 1_Layout_Layout1_BGM_LBPAS_17987_21_22_BP-
DWG 1_Layout_Layout1_BGM_LBPAS_17987_21_22_BP-
SPECIFICATION FOR RERA-
DWG 1_Layout_Layout1_BGM_LBPAS_17987_21_22_BP-
DWG 1_Layout_Layout1_BGM_LBPAS_17987_21_22_BP-
DWG 1_Layout_Layout1_BGM_LBPAS_17987_21_22_BP-
Advocate legal opinion-
Draft of Agreement of sale-
Draft of allotment letter-
FORM B_compressed-
sec 3 affidavit-
HESCOM NOC-
Water NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Application for Plinth Level certificate-
na layout porwal (1)-
Loan raised documentFile: RERA Completion CA Certificate.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Girnar PrideCTS. No. 10626/2, at Sector No. III, Shiv Basav Nagar, M M ExtensionCompleted-No date filed

How this compares with Belagavi

24%of Belagavi projects moved their completion datethis one has not
0%of Belagavi registrations are shown as withdrawn or revokedthis one is not

Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.

Keep GIRNAR ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Belagavi460+ in Belagavi

2 kmGIRNAR ENCLAVEOther 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: SHREE BALAJEE CONSTRUCTIONS

SHREE BALAJEE CONSTRUCTIONS has 2 registrations on RERA Karnataka, including GIRNAR ENCLAVE and Girnar Pride. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Belagavi district page.

Frequently asked questions

What are my rights if GIRNAR ENCLAVE is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of GIRNAR ENCLAVE?

The registered promoter entity is SHREE BALAJEE CONSTRUCTIONS, a proprietorship firm as per the filing. Its GSTIN 29AJLPP9778L3ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in GIRNAR ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at GIRNAR ENCLAVE?

The professionals named in the filing: Architect: KULDEEP MORE; Engineer: VINAY BEHERE; Chartered Accountant: VIJAY CHHAPPAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GIRNAR ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GIRNAR ENCLAVE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GIRNAR ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.