Home / Browse projects / Belagavi, Karnataka / GANESH RAVITEJ
GANESH RAVITEJ
By SHREE SAMARTH CONSTRUCTIONS
RG-KA-46290 · RERA PRM/KA/RERA/1249/447/PR/201126/009118 · Last updated on RERA Karnataka portal: 31 Jul 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Nothing adverse is on this record. The buyer report still lays out every unit as filed and places this filing against the promoter's other registrations and every project registered within 2 km.
See what the report covers Free either way: .Saved.
GANESH RAVITEJ is a Residential/Group Housing project by SHREE SAMARTH CONSTRUCTIONS in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/201126/009118 on 20 Nov 2026. Possession is promised by 31 Dec 2029.
At a glance
Project
- NameGANESH RAVITEJ
- TypeResidential/Group Housing
- Location
- Belagavi
- 590016
- Pincode590016
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1249/447/PR/201126/009118
- ReraGenie IDRG-KA-46290
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on20 Nov 2026
- Promised completion31 Dec 2029
- Revised completionNone
- Buildings1 building record
- Documents filed97 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| GANESH RAVITEJ | - | - | - | 19 | 0 | 19 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | - |
| Terrace | No | Not applicable |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| RAVI MARTAND BOVIYAVAR | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 4.22 cr | - |
| INTEREST ON BORROWING | Rs 36.00 lakh | - |
| On-site expenditure-Consultants Fees | Rs 3.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ANIKET TASHILDAR |
| Engineer | ANIKET TASHILDAR |
| Chartered Accountant | SANDEEP KAJUKAR |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed97
As listed on the registration, under the names the promoter filed them with; the newest 80 of 97 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/201126/009118 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Corrected AFS as per noticeFile: Format of agreement of sale as per notification.pdf | 31 Jul 2026 |
| bank letter for 100%, 70%, and 30% account detailsFile: canara bank letter.pdf | 22 Jul 2026 |
| Form 1 CA as per prescribed formatFile: FORM-1-CA IN PRESCRIBED FORMAT.pdf | 22 Jul 2026 |
| Bank affidavit as per prescribed formatFile: Bank Affidavit.pdf | 22 Jul 2026 |
| Defect free EC from 1-4-2011 to till dateFile: ECC-01042011 to till date.pdf | 22 Jul 2026 |
| otarized affidavit signed by owner and developer with details of project and litigation/acquisationFile: No litigation affidavit.pdf | 22 Jul 2026 |
| detailed stability certificate with structural engineer licenseFile: STRUCTURAL STABILITY CERTIFICATE WITH ENG LICENSE.pdf | 22 Jul 2026 |
| AFS as per RERA performaFile: Format of Agreement of sale as per notification.pdf | 22 Jul 2026 |
| HESCOM NOCFile: HESCOM NOC Ganesh ravitej.pdf | 22 Jul 2026 |
| sewer line drawing with full project name and address along with engineer signatureFile: sewer line drawing with project name.pdf | 22 Jul 2026 |
| SELF ATTESTED LAND COST CALCULATIONS SHEETFile: Land cost calculations.pdf | 22 Jul 2026 |
| GUIDANCE VALUE AT SR NO. 67File: SR Rate for Belagavi North 23-24.pdf | 22 Jul 2026 |
| notice replyFile: notice reply.pdf | 22 Jul 2026 |
| 100% Bank account passbookFile: 100% Account.pdf | 18 Jun 2026 |
| 70% Bank account passbookFile: 70% account.pdf | 18 Jun 2026 |
| 30% Bank account passbookFile: 30% account.pdf | 18 Jun 2026 |
| CA certificate in prescribed formatFile: FORM-1-CA.pdf | 18 Jun 2026 |
| Bank account affidavitFile: Bank affidavit.pdf | 18 Jun 2026 |
| P n L and Balance sheet 2023-24 with CA UDINFile: Balance sheet, P n L 2023-24 with CA UDIN .pdf | 18 Jun 2026 |
| Balance sheet 2024-25 with CA UDINFile: BALANCE SHEET.pdf | 18 Jun 2026 |
| P n L 2024-25 with CA UDINFile: PROFIT & LOSS ACCOUNT.pdf | 18 Jun 2026 |
| Source of Fund with supporting documentsFile: Source of fund_supporting documents.pdf | 18 Jun 2026 |
| about revenue from sales/ operationFile: about revenue-operation.pdf | 18 Jun 2026 |
| Schedule (Statement of income) for 2023-24File: Scheduel of statement IT 23-24.pdf | 18 Jun 2026 |
| current RTC (CTS record)File: AUTHENTICATED CTS AND MUTATION RECORD.pdf | 18 Jun 2026 |
| connected MR showing flow of titles in favour of landowner (CTS record)File: AUTHENTICATED CTS AND MUTATION RECORD.pdf | 18 Jun 2026 |
| about conversion order DCFile: ABOUT CONVERSION ORDER.pdf | 18 Jun 2026 |
| certificate of registration of partnership firmFile: firm registration Samarth Constructions & GST.pdf | 18 Jun 2026 |
| No litigation affidavit signed by Owner and DeveloperFile: No litigation affidavit signed by owner and developer.pdf | 18 Jun 2026 |
| Single Plot layout/Development plan Approved by the competent authorityFile: ABOUT SINGEL PLOT LAYOUT ORDER AND PLAN.pdf | 18 Jun 2026 |
| Single Plot layout/Development plan order Approved by the competent authorityFile: ABOUT SINGEL PLOT LAYOUT ORDER AND PLAN.pdf | 18 Jun 2026 |
| ADLR certified CTS sketch and boundariesFile: ADLR CERTIFIED SURVE SKETCH MAP WITH BOUNDARY-3.pdf | 18 Jun 2026 |
| Location details of the project , alongwith boundaries including latitude and longitudeFile: about location cordinate.pdf | 18 Jun 2026 |
| Schedule of statement with signature 2024-25File: Scheduel of statment 24-25.pdf | 18 Jun 2026 |
| Approved Building plan with QR codeFile: Original Building permission plan with QR Code.pdf | 18 Jun 2026 |
| all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Original Sectioned drawing, floor plan, sectional drawing and elevation.pdf | 18 Jun 2026 |
| about commencment certificateFile: about commencment certificate.pdf | 18 Jun 2026 |
| about Approval/NOC under section 14 of the KTCP ActFile: about NOC u-Section 14.pdf | 18 Jun 2026 |
| amenities/common areas details properlyFile: Common area and amenitied declaration.pdf | 18 Jun 2026 |
| amenities declarationFile: Common area and amenitied declaration.pdf | 18 Jun 2026 |
| self attested engineer valid certificateFile: Licence of Engineer.pdf | 18 Jun 2026 |
| Form 3 signed by the Engineer whose license is validFile: Form3 RERA RAVITEJ.pdf | 18 Jun 2026 |
| Elobrated structureal stability certificateFile: STABILITY CERTIFICATE.pdf | 18 Jun 2026 |
| Project specification with project name and address alongwith signatureFile: project specification.pdf | 18 Jun 2026 |
| AFS as per notificationFile: Draft of agreement of sale.pdf | 18 Jun 2026 |
| allotment letter with all necessary blanks fill one with Annexure A datesFile: Allotment letter.pdf | 18 Jun 2026 |
| HESCOM NocFile: HESCOM NOC Ganesh ravitej.pdf | 18 Jun 2026 |
| land cost calculationsFile: Land cost calculations.pdf | 18 Jun 2026 |
| Defect Free EC since 01/04/2011 to till dateFile: ECC-08062026-2143009.pdf | 18 Jun 2026 |
| Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: location of land in CDP.pdf | 18 Jun 2026 |
| Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: 10 (1).jpg | 18 Jun 2026 |
| Sewer line drawing with project name and address signe by engineerFile: sewer line drawing with project name.pdf | 18 Jun 2026 |
| brief project estimation with licenced engineer signatureFile: brief estimation .pdf | 18 Jun 2026 |
| Notice ReplyFile: Notice Reply.pdf | 18 Jun 2026 |
| Registration CertificateFile: firm registration Samarth Constructions & GST.pdf | - |
| GST CertificateFile: firm registration Samarth Constructions & GST.pdf | - |
| Partnership DeedFile: Supplementary Partnership Agreement.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form 1 CA .pdf | - |
| Certificate issued by Architect Form 2File: Form 2.pdf | - |
| Certificate issued by Engineer Form 3File: Form3 RERA RAVITEJ.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: No litigation affidavit.pdf | - |
| Balance Sheet 2024 - 2025File: BALANCE SHEET.pdf | - |
| Balance Sheet 2023 - 2024File: BSheet (1).pdf | - |
| Balance Sheet 2022 - 2023File: ITR SSC 22-23 P&l Balance Sheet.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: PROFIT & LOSS ACCOUNT.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: PROFIT & LOSS ACCOUNT.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: ITR SSC 22-23 P&l Balance Sheet.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: Statement_of_Income_AEQFS1999L.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: IT ack.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: ITR SSC 22-23 P&l Balance Sheet.pdf | - |
| aproval letter permission | - |
| permission drawing | - |
| permission drawing | - |
| Stability Ravitej | - |
| permission drawing | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Buyer report
Built from this project's RERA Karnataka filing, in plain language.
- Red flags and clear checks, the possession story and who you are dealing with
- Every unit as filed, tower by tower: carpet area, undivided share of the land and parking, with the sizes placed against the other projects of the taluk
- Joined against the promoter's other registrations on RERA Karnataka and every project registered within 2 km, which the register never shows together
- What to check before you book, drawn from this filing
Not included: the filed documents themselves (the report lists which are on file and does not read them) and a project watch.
Keep GANESH RAVITEJ on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Sunlight
Sunlight Builders and Developers
HONEYWELL ENCLAVE
SHUBHA SHANKAR DEVELOPERS
ELLITE RESIDENCY I
M/s. UNIQUE CONSTRUCTIONS
GARDENIA
SAUDAGAR URBAN LIFESTYLES
EVERGREEN RESIDENCY
M/s. UNIQUE CONSTRUCTIONS
CITY HEIGHTS
MNC INFRASTRUCTURE
See every Belagavi project, with the district possession charts
Builder: SHREE SAMARTH CONSTRUCTIONS
SHREE SAMARTH CONSTRUCTIONS has 3 registrations on RERA Karnataka, including GANESH RAVITEJ and GANESH GOKUL. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if GANESH RAVITEJ is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of GANESH RAVITEJ?
The registered promoter entity is SHREE SAMARTH CONSTRUCTIONS, a partnership firm as per the filing. Its GSTIN 29AEQFS1999L1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in GANESH RAVITEJ?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at GANESH RAVITEJ?
The professionals named in the filing: Architect: ANIKET TASHILDAR; Engineer: ANIKET TASHILDAR; Chartered Accountant: SANDEEP KAJUKAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GANESH RAVITEJ?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback