Forreste is a Residential/Group Housing project by ARVIND LIMITED in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA06788/A4R/EX1/280525/300626 on 14 Feb 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 24 months from the original filing. 289 of the 351 units on this registration are recorded sold or booked, and 125 of 171 construction stages are filed complete.
At a glance
Project
- NameForreste
- TypeResidential/Group Housing
- Location
- at Village Karoli
- Jethalaj
- Near Khatraj Cross Road
- Near Arvind Limited
- Village : Jethalaj
- Taluko: Kalol
- Gandhinagar
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA06788/A4R/EX1/280525/300626
- ReraGenie IDRG-GJ-25165
Builder
- NameARVIND LIMITED
- Entity typeCOMPANY
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 30 Jun 2027
- Registered on14 Feb 2020
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2025)
- Buildings19 building records
- Documents filed37 files
Current status
Figures as on 19 May 2025, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Type D | - | - | - | 158 | 0 | 158 |
| Type C1 | - | - | - | 1 | 0 | 1 |
| Type D2 | - | - | - | 2 | 0 | 2 |
| Type D1 | - | - | - | 1 | 0 | 1 |
| Type F | - | - | - | 2 | 0 | 2 |
| Type E | - | - | - | 30 | 0 | 30 |
| Type H | - | - | - | 1 | 0 | 1 |
| Type G | - | - | - | 1 | 0 | 1 |
| Type J | - | - | - | 1 | 0 | 1 |
| Type I | - | - | - | 1 | 0 | 1 |
| Type L | - | - | - | 18 | 0 | 18 |
| Type K | - | - | - | 1 | 0 | 1 |
| Type R | - | - | - | 3 | 0 | 3 |
| Type A1 | - | - | - | 1 | 0 | 1 |
| Type A | - | - | - | 39 | 0 | 39 |
| Type A3 | - | - | - | 3 | 0 | 3 |
| Type A2 | - | - | - | 1 | 0 | 1 |
| Type C | - | - | - | 4 | 0 | 4 |
| Type B | - | - | - | 83 | 0 | 83 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building19
As on 19 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
125 of 171 construction stages are filed complete across 19 buildings. The stage furthest along is Internal walls, at 95%.
Type D74%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 73% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 49% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 44% |
Type C197%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 75% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type D292%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 75% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 50% |
Type D189%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type F100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type E84%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 83% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 67% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 60% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 50% |
Type H100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type G100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type J100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type I100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type L90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 83% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 67% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 89% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 67% |
Type K99%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 90% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type R11%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Type A181%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 25% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Type A74%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 69% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 95% |
| Sanitary fittings within the flats | 44% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 31% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 38% |
Type A3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Type A256%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Type C82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 75% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 75% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 60% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 50% |
Type B87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 89% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 66% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 65% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 61% |
Progress on shared amenities23
As on 19 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 87% |
| Water supply | Yes | 73% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 90% |
| Storm water drains | Yes | 100% |
| Landscaping and tree planting | Yes | 45% |
| Street lighting | Yes | 60% |
| Community buildings | Yes | 82% |
| Treatment and disposal of sewage and sullage water | Yes | 100% |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | Yes | 0% |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | Yes | 0% |
| Letter box | Yes | 25% |
| Compound wall | Yes | 60% |
| Plinth protection | Yes | 0% |
| Water tank | Yes | 50% |
| Other requirements | Yes | 0% |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Type D | NA | Rs 24.55 cr | Rs 24.55 cr |
| Type A | NA | Rs 11.06 cr | Rs 11.06 cr |
| Type B | NA | Rs 8.11 cr | Rs 8.11 cr |
| Type E | NA | Rs 6.94 cr | Rs 6.94 cr |
| Type L | NA | Rs 2.80 cr | Rs 2.80 cr |
| Type C | NA | Rs 1.36 cr | Rs 1.36 cr |
| Type A3 | NA | Rs 85.05 lakh | Rs 85.05 lakh |
| Type F | NA | Rs 49.91 lakh | Rs 49.91 lakh |
| Type H | NA | Rs 42.02 lakh | Rs 42.02 lakh |
| Type C1 | NA | Rs 34.04 lakh | Rs 34.04 lakh |
| Type D2 | NA | Rs 31.08 lakh | Rs 31.08 lakh |
| Type A1 | NA | Rs 28.35 lakh | Rs 28.35 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KRUNAL PATEL |
| Engineer | HIRAL MAKADIA |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed37
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA06788/A4R/EX1/280525/300626 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer's certificate (Form 2) | 19 May 2025 |
| Engineer's certificate annexure | 19 May 2025 |
| RERA registration certificate | 14 Feb 2020 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Gandhinagar
Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.
Keep Forreste on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Gandhinagar1,600+ in Gandhinagar
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
SIBAN
UNITED YOGI LLP
AMBA TOWNSHIP SECTOR 4 Part A - Phase 1
AMBA TOWNSHIP PRIVATE LIMITED
TPS 09 FP 175 EWS II
GANDHINAGAR URBAN DEVELOPMENT AUTHORITY
TPS 07 FP 186 EWS II
GANDHINAGAR URBAN DEVELOPMENT AUTHORITY
WTC GIFT Tower A, B & D
WTC Noida Development Company Pvt Ltd
ZUNDAL FP 123 TP 72
AHMEDABAD URBAN DEVELOPMENT AUTHORITY
See every Gandhinagar project, with the district possession charts
Builder: ARVIND LIMITED
ARVIND LIMITED has 2 registrations on GujRERA, including Forreste and Forreste 5. Read the full track record. See more projects on the Gandhinagar district page.
Frequently asked questions
What are my rights if Forreste is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of Forreste?
The registered promoter entity is ARVIND LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in Forreste?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Forreste?
The professionals named in the filing: Architect: KRUNAL PATEL; Engineer: HIRAL MAKADIA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Forreste?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.
Report an error Share feedback