ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / EVEREST DIGNITY

Valid until 30 Apr 2019 Residential/Group Housing project

EVEREST DIGNITY

By AKASH CORPORATION

RG-GJ-94236 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA02345/EX1/261218 · Last updated on GujRERA portal: 28 Mar 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 10 months
  • 1 extension taken

Clear

  • Separate project account declared
Apr 2019Possession promisedmoved 10 months from the original
27 of 27Construction stages doneacross 3 buildings; every applicable stage filed complete
Jump to the 38 documents Report an error

EVEREST DIGNITY is a Residential/Group Housing project by AKASH CORPORATION in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA02345/EX1/261218 on 12 Apr 2018. Possession is promised by 30 Apr 2019. The completion date has moved by 10 months from the original filing.

At a glance

Project

  • NameEVEREST DIGNITY
  • TypeResidential/Group Housing
  • Location
    • BHAYLI TP 5
    • OPP BANCO
    • Samiyala
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA02345/EX1/261218
  • ReraGenie IDRG-GJ-94236

Builder

  • NameAKASH CORPORATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2018First promiseJun 2018Revised toApr 2019

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2019
  • Registered on12 Apr 2018
  • Promised completion30 Apr 2019
  • Revised completionRevised to 30 Apr 2019 (originally 30 Jun 2018)
  • Buildings3 building records
  • Documents filed38 files

Current status

102.3%Of the estimated cost spent so far

Figures as on 28 Mar 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-----38
B+C-----66
D-----30

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 28 Mar 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 27 construction stages are filed complete across 3 buildings.

A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B+C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 28 Mar 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,734 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 9.36 cr
Cost incurredRs 9.57 cr
Spent of the estimate102.28%
BuildingWingEstimatedIncurred
ANARs 3.12 crRs 3.19 cr
B+CNARs 3.12 crRs 3.19 cr
DNARs 3.12 crRs 3.19 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRIT PATEL
EngineerSUHAS MAJUMDAR

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA02345/EX1/261218Applied Oct 2018; approved Dec 2018

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA02345/EX1/261218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)28 Mar 2019
Engineer's certificate (Form 2)28 Mar 2019
Site photograph, A28 Mar 2019
Site photograph, B+C28 Mar 2019
Site photograph, D28 Mar 2019
RERA registration certificate12 Apr 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

23%of Vadodara projects moved their completion datethis one moved by 10 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep EVEREST DIGNITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Samiyala2,900+ in Vadodara

2 kmEVEREST DIGNITYOther 258Dot size: filed unitsN

Filed coordinates, straight-line distance. 258 registered projects within 2 km.

Builder: AKASH CORPORATION

AKASH CORPORATION has 2 registrations on GujRERA, including EVEREST DIGNITY and GAJANAN INDUSTRIAL HUB 2. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if EVEREST DIGNITY is delayed beyond 30 Apr 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EVEREST DIGNITY?

The registered promoter entity is AKASH CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EVEREST DIGNITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EVEREST DIGNITY?

The professionals named in the filing: Architect: KIRIT PATEL; Engineer: SUHAS MAJUMDAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EVEREST DIGNITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EVEREST DIGNITY. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EVEREST DIGNITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.