Home / Browse projects / Gandhinagar, Gujarat / ELIXIR

Valid until 29 Jun 2023 Commercial project

ELIXIR

By Shreeji Corporation

RG-GJ-97397 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA03752/EX2/080523 · Last updated on GujRERA portal: 27 Jun 2023

Source: official GujRERA filing

Red flags

  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • Separate project account declared
Jun 2023Possession promisedmoved 18 months from the original
9 of 9Construction stages doneevery applicable stage filed complete
32 of 144Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

ELIXIR is a Commercial project by Shreeji Corporation in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA03752/EX2/080523 on 20 Oct 2018. Possession is promised by 29 Jun 2023. The completion date has moved by 18 months from the original filing. 112 of the 144 units on this registration are recorded sold or booked, and 9 of 9 construction stages are filed complete.

At a glance

Project

  • NameELIXIR
  • TypeCommercial
  • Location
    • Elixir
    • Nr. GNLU and PDPU
    • Opp
    • Shreerang Upvan Bungalows
    • PDPU-Gift City Main Road
    • Raysan
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA03752/EX2/080523
  • ReraGenie IDRG-GJ-97397

Builder

  • NameShreeji Corporation
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →
  • Past their filed date3

Key dates

this monthRegisteredOct 2018First promiseDec 2021Revised toJun 2023

Key facts

Registration and timeline

  • StatusValid until 29 Jun 2023
  • Registered on20 Oct 2018
  • Promised completion29 Jun 2023
  • Revised completionRevised to 29 Jun 2023 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed38 files

Current status

78%112 of 144 units booked
102.3%Of the estimated cost spent so far

Figures as on 27 Jun 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building-A---096144

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 27 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 9 construction stages are filed complete.

Building-A: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 27 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingNoNot applicable
Street lightingNoNot applicable
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,907 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 12.00 cr
Cost incurredRs 12.28 cr
Spent of the estimate102.3%
BuildingWingEstimatedIncurred
Building-ANARs 12.00 crRs 12.28 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectThe Grid Architrecs- Snehal Suthar
EngineerAmee Associates

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA03752/EX1/160222Applied Dec 2021; approved Feb 2022
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA03752/EX2/080523Applied May 2023; approved May 2023

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA03752/EX2/080523 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)27 Jun 2023
Architect's certificate (Form 1)24 Jun 2023
Engineer's certificate (Form 2)24 Jun 2023
Engineer's certificate annexure24 Jun 2023
Site photograph, Building-A24 Jun 2023
RERA registration certificate20 Oct 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

78%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 18 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep ELIXIR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmELIXIROther 173Dot size: filed unitsN

Filed coordinates, straight-line distance. 173 registered projects within 2 km.

Builder: Shreeji Corporation

SHREEJI CORPORATION has 3 registrations on GujRERA, including JAINAM 16 and ELIXIR. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if ELIXIR is delayed beyond 29 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of ELIXIR?

The registered promoter entity is Shreeji Corporation, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in ELIXIR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ELIXIR?

The professionals named in the filing: Architect: The Grid Architrecs- Snehal Suthar; Engineer: Amee Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ELIXIR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELIXIR. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELIXIR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.