ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Elanza

Registration approved No litigation declared Residential/Group Housing project

Elanza

By Lodha Developers Limited

RG-KA-72297 · RERA PRM/KA/RERA/1251/308/PR/191225/008353 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Sep 2031Possession promisedno revision filed
1 of 18Construction stages donefurthest along: Foundation footing work, 80%
367 of 698Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 200 documents Report an error

Elanza is a Residential/Group Housing project by Lodha Developers Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/191225/008353 on 19 Dec 2025. Possession is promised by 30 Sep 2031. 331 of the 698 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete.

At a glance

Project

  • NameElanza
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562125
  • Pincode562125
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/191225/008353
  • ReraGenie IDRG-KA-72297

Builder

  • NameLodha Developers Limited
  • Entity typeCompany
  • CINL45200MH1995PLC093041
  • GSTIN29AAACL1490J1ZC
  • Authorized SignatorySamrat Das
  • CeoRajendra Joshi
  • DirectorsAbhishek Mangalprabhat Lodha, Mukund Manohar Chitale, Rajeev Bakshi, Harita Gupta, Rajinder Pal Singh, Lee Anthony Polisano, Shaishav Pankaj Dharia, Sushil Modi
  • Project HeadArun Rao
  • Other registrations6 more →
  • Declared earlier projects6 →

Key dates

this monthRegisteredDec 2025PromisedSep 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Dec 2025
  • Promised completion30 Sep 2031
  • Revised completionNone
  • Buildings6 building records
  • Documents filed200 files

Current status

47%331 of 698 units booked
12.6%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---1190119
B---1190119
C---1110111
D---1110111
E---1190119
F---1190119

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 18 construction stages are filed complete. The stage furthest along is Foundation footing work, at 80%.

Building: 10% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work80%
Upto Plinth Level8%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership10

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,344 sq m
Named landowners10
LandownerVillageDistrict
Lodha Developers Limited (formerly known as Macrotech Developers Limited)--
Shravanth P and Novin Pilla Reddy--
Lodha Developers Limited (formerly known as Macrotech Developers Limited)--
Lodha Developers Limited (formerly known as Macrotech Developers Limited)--
Lodha Developers Limited (formerly known as Macrotech Developers Limited)--
Lodha Developers Limited (formerly known as Macrotech Developers Limited)--
K N Manjunatha--
Lodha Developers Limited (formerly known as Macrotech Developers Limited)--
Lodha Developers Limited (formerly known as Macrotech Developers Limited)--
Lodha Developers Limited (formerly known as Macrotech Developers Limited)--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 830.83 cr
Cost incurredRs 104.52 cr
Spent of the estimate12.58%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 663.87 crRs 27.87 cr
On-site expenditure-Site OverheadRs 166.96 crRs 76.64 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPradeep M Kamble
EngineerPrasanna Kumar R
Chartered AccountantChirag Sarvaiya & Co

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed200

As listed on the registration, under the names the promoter filed them with; the newest 80 of 200 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/191225/008353 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Elanza Sep 26 - For RERA.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect's Certificate Elanza Ph1 T-ABCDEF Q2 FY26-27--.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 6 Engineer Elanza Sep-26.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Elanza June 26 - For RERA_compressed.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form - 6 Engineer Elanza June-26.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 5 Architect's Certificate Elanza Signed.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant Elanza Mar 26_compressed.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect's Certificate Elanza Tower A,B,C,D,E,F--.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form - 6 Engineer Elanza Mar-26 (1).pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Airport Authority of India14 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant Elanza Dec 25_compressed.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: elanza Architech.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form - 6 Engineer Elanza.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Q3 2025-26 Fire and Safety15 Jan 2026
Q3 2025-26 Airport Authority of India15 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department15 Jan 2026
Site PlanFile: Site plan.pdf18 Dec 2025
Basement - 1File: Basement - 1.pdf18 Dec 2025
Basement - 2File: Basement - 2.pdf18 Dec 2025
Ground floorFile: Ground floor.pdf18 Dec 2025
First floorFile: First floor Podium.pdf18 Dec 2025
Second floorFile: Second floor podium-2.pdf18 Dec 2025
Thrid floorFile: Third Floor Podium terrace.pdf18 Dec 2025
Fourth floorFile: Fourth floor.pdf18 Dec 2025
Typical floorFile: Typical floor -1.pdf18 Dec 2025
Typical floor with Refuge areaFile: Refuge area.pdf18 Dec 2025
Section PlanFile: Section & Elevation.pdf18 Dec 2025
31st floorFile: 31st floor.pdf18 Dec 2025
32nd floorFile: 32nd floor.pdf18 Dec 2025
33rd floorFile: 33rd floor.pdf18 Dec 2025
Terrace floorFile: Terrace floor.pdf18 Dec 2025
Work Order/Building License/Commencement CertificateFile: Work Order dt 12-12-2025.pdf18 Dec 2025
Updated APA - Development PlanFile: APA - Development Plan.pdf18 Dec 2025
Quarterly update Report - Azur and Azur tower DFile: Quarterly update details 6728 6746.pdf18 Dec 2025
Section 3(1) AffidavitFile: Annexure 90 Section 31 Notarized Affidavit.pdf18 Dec 2025
Source of FundsFile: Source of Funding Declaration Letter 1.pdf18 Dec 2025
KSPCB NOCFile: Annexure 97 KSPCB CFE.pdf18 Dec 2025
Land Cost CalculationFile: Land Cost Calculation Sheetsigned (1).pdf18 Dec 2025
Guidance value CertificateFile: Guidance Value Certificate - Yamare.pdf18 Dec 2025
Agreement for Sale proforma UpdatedFile: Sarjapur AFS for RERA.pdf18 Dec 2025
Allotment Letter UpdatedFile: Lodha Allotment Letter.pdf18 Dec 2025
Updated Phase wise Bifurcation of AreaFile: Updated Phase-wise Bifurcation of Area.pdf18 Dec 2025
Change of Land UseFile: Change of Land Use.pdf18 Dec 2025
Reply to QueryFile: Elanza RERA query reply.pdf18 Dec 2025
RTC, survey 154/4-
Mutation, survey 154/4-
Encumbrance Certificate, survey 154/4-
Conversion/Alienation Order, survey 154/4-
Sale/Title/Gift Deed, survey 154/4-
JDA, survey 154/4-
Khatha, survey 154/4-
RTC, survey 155/4-
Mutation, survey 155/4-
Encumbrance Certificate, survey 155/4-
Conversion/Alienation Order, survey 155/4-
Sale/Title/Gift Deed, survey 155/4-
JDA, survey 155/4-
Khatha, survey 155/4-
RTC, survey 156/1-
Mutation, survey 156/1-

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 under way, not due yet
ProjectLocationStatusPromisedDelivered
Azur Phase 2Katha No. 46, Sy. No.s 328/2(P), 332/2 of Begur Village, Begur Hobli, Bengaluru SouthOngoingDec 2030Not due yet
HavenSy Nos. 60/1, 60/2 & 61/2 , Choodasandra Village, Sarjapura Hobli, AnekalOngoingJun 2030Not due yet
Azur Tower DKatha No. 46, Sy. No. 332/2 of Begur Village, Begur Hobli, Bengaluru SouthOngoingApr 2030Not due yet
AzurKatha No. 46, Sy. No.s 328/2(P), 332/2 of Begur Village, Begur Hobli, Bengaluru SouthOngoingOct 2029Not due yet

How this compares with Bengaluru Urban

47%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Elanza on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmElanzaOther 66Dot size: filed unitsN

Filed coordinates, straight-line distance. 66 registered projects within 2 km.

Builder: Lodha Developers Limited

Lodha Developers Limited has 7 registrations on RERA Karnataka, including Elanza and Haven Phase 2. Its filings declare 6 earlier projects, none of them declared completed. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Elanza is delayed beyond 30 Sep 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Elanza?

The registered promoter entity is Lodha Developers Limited, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 29AAACL1490J1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Elanza?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Elanza?

The professionals named in the filing: Architect: Pradeep M Kamble; Engineer: Prasanna Kumar R; Chartered Accountant: Chirag Sarvaiya & Co. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Elanza?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Elanza. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Elanza to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.