Home / Browse projects / Bengaluru Rural, Karnataka / EAST FIELD

Registration approved No litigation declared Residential/Group Housing project

EAST FIELD

By URBANEST REALTY

RG-KA-25055 · RERA PRM/KA/RERA/1250/304/PR/131224/007290 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
4 of 16Construction stages donefurthest along: RCC or MS Framed structure, 90%
146 of 200Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 178 documents Report an error

EAST FIELD is a Residential/Group Housing project by URBANEST REALTY in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/131224/007290 on 13 Dec 2024. Possession is promised by 31 Dec 2029. 54 of the 200 units on this registration are recorded sold or booked, and 4 of 16 construction stages are filed complete.

At a glance

Project

  • NameEAST FIELD
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 562114
  • Pincode562114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/131224/007290
  • ReraGenie IDRG-KA-25055

Builder

  • NameURBANEST REALTY
  • Entity typePartnership Firm
  • GSTIN29AAFFU7438K1ZI
  • Authorized SignatoryMOHAN R
  • Other registrations2 more →

Key dates

this monthRegisteredDec 2024PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Dec 2024
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed178 files

Current status

27%54 of 200 units booked
30.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EAST FIELD TOWER A---1000100
EAST FIELD TOWER B---1000100

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 16 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 90%.

Building: 35% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure90%
Masonry Construction60%
Plastering inside , outside & Ceiling16%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities36

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes35%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymYes0%
ParksYes0%
StaircasesYes55%
LiftsYes55%
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes55%
BasementYes90%
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,976 sq m
Named landowners5
LandownerVillageDistrict
SVASTAM ENTERPRISES--
SVAST ENTERPRISES represented by its Partner Mrs. Vandita Batra--
SVAST ENTERPRISES represented by its Partner Mrs. Vandita Batra--
R GAJENDRA--
SVAST ENTERPRISES represented by its Partner Mrs. Vandita Batra--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 60.49 cr
Cost incurredRs 18.51 cr
Spent of the estimate30.61%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 60.33 crRs 18.51 cr
Payment of taxesRs 16.52 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRaghavendra S
EngineerAmbrish G
Chartered AccountantSRIKARAN UTPALA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed178

As listed on the registration, under the names the promoter filed them with; the newest 80 of 178 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/131224/007290 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - CA certification East field Q2 2026.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Q2 Eastfield Form 5- Architect Certificate -2026 -27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6- Engineer Cerificate Eastfield Q2 2026 -27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - CA certification East field Q1 2026.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Q1 Eastfield Form 5- Architect Certificate -2026 .pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: East Field Form 6- Engineered Cerificate Q1 2026.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: eastfield Form 4 Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Q4 Eastfield Form 5- Architect Certificate.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6- Engineer Cerificate Q4.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - CA certification East field Q3 25-26.pdf7 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Q3 25-26- Eastfield Form 5- Architect Certificate.pdf7 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6- Engineered Cerificate Q3 25-26.pdf7 Feb 2026
Q3 2025-26 Water supply and sewage board7 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)7 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)7 Feb 2026
Q3 2025-26 KPTCL- BESCOM7 Feb 2026
Q3 2025-26 Fire and Safety7 Feb 2026
Q3 2025-26 Airport Authority of India7 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department7 Feb 2026
Sale Agreement ProformaFile: sale agreement Proforma.pdf2 Dec 2024
Engineer License AttestedFile: Engineer License Attested.pdf2 Dec 2024
Basement PlanFile: Basement Plan_compressed.pdf2 Dec 2024
Ground Floor PlanFile: Ground Floor Plan_compressed.pdf2 Dec 2024
Section and Elevation PlanFile: Section and Elevation_compressed.pdf2 Dec 2024
Typical Floor PlanFile: Typical Floor Plan_compressed.pdf2 Dec 2024
Current Year RTC Sy No 21/12File: RTC Sy No 21-12.pdf2 Dec 2024
EC From 2004 to 2021 with respect to Sy No 21/2 and 21/12File: EC from 2004 to 2021 Sy No 21-2 and 21-12.pdf2 Dec 2024
EC From 2020 to till date with respect to Sy No 21/2 and 21/12File: EC from 2020 to till date Sy No 21-2 and 21-12.pdf2 Dec 2024
Current Year RTC Sy No 21/2File: RTC Sy No 21-2.pdf2 Dec 2024
E-KhathaFile: E-Khatha.pdf2 Dec 2024
Sources of FundFile: SOURCES OF FUND.pdf25 Nov 2024
Financials 2023-24 with CA UDINFile: Urbanest realty FY2023-24.pdf25 Nov 2024
E-KhathaFile: E-Khatha.pdf25 Nov 2024
Old Sale Deed Sy No 21/12File: Old Sale Deed Sy No 21-12.pdf25 Nov 2024
Old Sale Deed Sy No 21/2File: Sy No 21-2 - Sale Deed 7514_2021-22.pdf25 Nov 2024
Development PlanFile: Development Plan.pdf25 Nov 2024
DP Approval OrderFile: DP Approval Order.pdf25 Nov 2024
Building LicenseFile: Building License.pdf25 Nov 2024
Commencement CertificateFile: Commencement Certificate.pdf25 Nov 2024
SEIAA NOCFile: SEIAA NOC.pdf25 Nov 2024
ADLR Survey SketchFile: ADLR Survey self attested.pdf25 Nov 2024
ZR copyFile: Zonal Regulations copy - Hoskote.pdf25 Nov 2024
Master PlanFile: Master Plan_compressed.pdf25 Nov 2024
AAI NOCFile: AAI.pdf25 Nov 2024
Fire NOCFile: Fire NOC.pdf25 Nov 2024
HAL NOCFile: HAL NOC.pdf25 Nov 2024
BSNL NOCFile: BSNL Noc.pdf25 Nov 2024
STP DrawingsFile: STP Drawings self Attested.pdf25 Nov 2024
Sale Agreement ProformaFile: sale agreement Draft.pdf25 Nov 2024
Allotment LetterFile: Allotment letter.pdf25 Nov 2024
Cost BreakupFile: East Field - Cost Breakup.pdf25 Nov 2024
Land CostFile: Land Cost.pdf25 Nov 2024
SpecificationsFile: SPECIFICATIONS.pdf25 Nov 2024
RTC, survey 21/2-
Mutation, survey 21/2-
Encumbrance Certificate, survey 21/2-
Conversion/Alienation Order, survey 21/2-
JDA, survey 21/2-
Khatha, survey 21/2-
RTC, survey 21/12-

How this compares with Bengaluru Rural

27%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep EAST FIELD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmEAST FIELDOther 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: URBANEST REALTY

URBANEST REALTY has 3 registrations on RERA Karnataka, including EAST FIELD and URBANEST ELITE 35. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if EAST FIELD is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of EAST FIELD?

The registered promoter entity is URBANEST REALTY, a partnership firm as per the filing. Its GSTIN 29AAFFU7438K1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in EAST FIELD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EAST FIELD?

The professionals named in the filing: Architect: Raghavendra S; Engineer: Ambrish G; Chartered Accountant: SRIKARAN UTPALA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EAST FIELD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EAST FIELD. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EAST FIELD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.