Home / Browse projects / Vadodara, Gujarat / EARTH ALLYSSUM

Valid until 30 Jul 2022 Residential/Group Housing project

EARTH ALLYSSUM

By ALLYSSUM INFRA

RG-GJ-34723 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA00167/EX2/070322 · Last updated on GujRERA portal: 6 Jul 2022

Source: official GujRERA filing

Red flags

  • Completion date moved by 17 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Jul 2022Possession promisedmoved 17 months from the original
47 of 55Construction stages doneacross 8 buildings; furthest along: Installation of lifts, 93%
21 of 160Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

EARTH ALLYSSUM is a Residential/Group Housing project by ALLYSSUM INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA00167/EX2/070322 on 16 Sep 2017. Possession is promised by 30 Jul 2022. The completion date has moved by 17 months from the original filing. 139 of the 160 units on this registration are recorded sold or booked, and 47 of 55 construction stages are filed complete.

At a glance

Project

  • NameEARTH ALLYSSUM
  • TypeResidential/Group Housing
  • Location
    • "EARTH ALLYSSUM" OPP SIDDHESHWAR KRISHNA
    • T.P.4 BHAYLI
    • Bhayali
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA00167/EX2/070322
  • ReraGenie IDRG-GJ-34723

Builder

  • NameALLYSSUM INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2017First promiseFeb 2021Revised toJul 2022

Key facts

Registration and timeline

  • StatusValid until 30 Jul 2022
  • Registered on16 Sep 2017
  • Promised completion30 Jul 2022
  • Revised completionRevised to 30 Jul 2022 (originally 1 Feb 2021)
  • Buildings8 building records
  • Documents filed45 files

Current status

87%139 of 160 units booked
90.5%Of the estimated cost spent so far

Figures as on 6 Jul 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
H---20020
A---20020
B---20020
C---20020
D---20020
E---20020
F---20020
G---20020

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 6 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

47 of 55 construction stages are filed complete across 8 buildings. The stage furthest along is Installation of lifts, at 93%.

H99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing92%
A99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flatsNot applicable
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing93%
B99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing92%
C99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing92%
D99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing92%
E99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing92%
F99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing92%
G99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt Floor100%
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing92%

Progress on shared amenities19

As on 6 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes85%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,888 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 19.88 cr
Cost incurredRs 17.98 cr
Spent of the estimate90.46%
BuildingWingEstimatedIncurred
ANARs 2.48 crRs 2.25 cr
BNARs 2.48 crRs 2.25 cr
CNARs 2.48 crRs 2.25 cr
DNARs 2.48 crRs 2.25 cr
ENARs 2.48 crRs 2.25 cr
FNARs 2.48 crRs 2.25 cr
GNARs 2.48 crRs 2.25 cr
HNARs 2.48 crRs 2.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUCHIR MANOJBHAI SHETH
EngineerVINUBHAI PATEL

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA00167/EX1/291220Applied Dec 2020; approved Dec 2020
PR/GJ/VADODARA/VADODARA/Others/RAA00167/EX2/070322Applied Mar 2022; approved Mar 2022

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA00167/EX2/070322 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)6 Jul 2022
Architect's certificate (Form 1)4 Jul 2022
Engineer's certificate (Form 2)4 Jul 2022
Engineer's certificate annexure4 Jul 2022
Site photograph, H4 Jul 2022
Site photograph, A4 Jul 2022
Site photograph, B4 Jul 2022
Site photograph, C4 Jul 2022
Site photograph, D4 Jul 2022
Site photograph, E4 Jul 2022
Site photograph, F4 Jul 2022
Site photograph, G4 Jul 2022
RERA registration certificate16 Sep 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

87%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 17 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep EARTH ALLYSSUM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhayali2,900+ in Vadodara

2 kmEARTH ALLYSSUMOther 325Dot size: filed unitsN

Filed coordinates, straight-line distance. 325 registered projects within 2 km.

Builder: ALLYSSUM INFRA

ALLYSSUM INFRA has 1 registration on GujRERA, including EARTH ALLYSSUM. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if EARTH ALLYSSUM is delayed beyond 30 Jul 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of EARTH ALLYSSUM?

The registered promoter entity is ALLYSSUM INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in EARTH ALLYSSUM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EARTH ALLYSSUM?

The professionals named in the filing: Architect: RUCHIR MANOJBHAI SHETH; Engineer: VINUBHAI PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EARTH ALLYSSUM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EARTH ALLYSSUM. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EARTH ALLYSSUM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.